Date: October 7, 2019

Project: Proposed 3 Storey Commercial Building (Phase 2)


Owner: Crystalspace Development Corporation
Location: Arbortowne Village, Gen. T De Leon St., Karuhatan, Valenzuela City

Dear Sir/Madame,

Good day!

In relation with the above mentioned project, main concerns are listed below which were
tackled during the meeting last Saturday (October 4, 2019).

1. Temporary fence minimum of 2.5m (H) for security purposes,

Note: TSD requested a setback of 0.5m from property line (Subdivision side) to
give way for the construction of permanent fence, and will be removed 2 months from
Day 1 of the project.

2. Notice Letter for concrete pouring schedule must be sent to the neighbors thru
subdivision’s admin office prior to the pouring date.

3. Worker’s orientation of rules and regulation of the company including the neighbor’s
concern such as the following:

a. Waste management strategy.


b. Disturbing activities must be restricted during night time.

4. Activities every Sunday must be minimal.

Should you have any concern, please do not hesitate to contact us to the following numbers:

1. General Contractor (Total Safe Development Construction Inc.)

Engr. Rodel Elagac- 09957002591


Engr. Marie Joana Basco- 09776034146
Engr. Lyza Montaray- 09420191342

2. Crystalspace Development Corporation

Ms. Heyz Ramos- 09171827450

Thank you very much. God Bless.

Respectfully Yours,

Marie Joana Basco


Office Engineer
TSD Construction Inc.