Halliburton Hydraulic PrV Trailer Work Method WM-GL-HAL-PE-412

Halliburton Hydraulic PRV Trailer Work Method HALLIBURTON MANAGEMENT SYSTEM


REGION: PSL/FUNCTION: DOCUMENT NUMBER:
Global Production Enhancement WM-GL-HAL-PE-412
REVIEW/REVISION
JOB REVIEW/REVISION BY:
OWNER: APPROVED BY: DATE: Review/Revision PAGE:
Global PE HSE Mgr.
PE GSQM PE GSQM 01.OCT.2019 No. 6 see page number at bottom of page

QUALITY/CRITICAL CHECKS: SAFETY CHECKS:


1) Ensure customer is aware that a Pressure Relieve Valve (PRV) is a last line of defense to 1) Ensure all personnel involved with prime and test procedures discussed in ST-GL-HAL-PE-410
protect the integrity of the well and not a means to control Frac pressure. (Follow step 2a understand them
below to ensure line placement on truck side of check valve) 2) Ensure LOTO is used on wellhead assembly to prevent out of sequence operation of valves
2) Ensure all pressure kick outs are in working order and a global kick out pressure 3) Ensure all personnel in process have the ability to communicate to others during process.
is mapped to the TCC instrument skid pressure transducer located upstream of the main 4) During rig-up, Ground supervisor ensures all wheel and Lo-Torc® valves operate correctly.
check/wheel valve assembly. (High pressure pump side) 5) Ensure "Red Zone" safety perimeter is established around PRV trailer while pressure testing and
pumping is in progress.
6) Ensure PRV unit is isolated from line pressure before shutting down to perform maintenance.
7) NEVER install a choke or other restriction in flow line downstream of PRV. If necessary to have a
valve to control flow path, it shall be full opening and LOTO used to ensure valve is OPEN.

Step Work Instructions/Sequence Visual Instructions

Gather pressure requirements from customer:


a) Establish maximum Frac pressure and kick out pressure limits. 2a where
1 b) Communicate recommendation that PRV be set at 500 psi above maximum kick out pressure setting, without Pumping to locate
Equipment
exceeding lowest rated DME component.
PRV trailer

Wheel Hyd
valve Popoff
valve
Set up Frac string pumping lines:
a) Set up PRV on main Frac line on upstream side (High pressure pump side) of main check valve. Wheel
2 b) Ensure there is a "kick" between main line and PRV trailer. valve

c) Ensure the PRV trailer is spotted within 150 ft. of the TechCommand® center (TCC)
CV

To wellhead

REVIEW/REVISION DATE:
Printed version of this document is uncontrolled 1 15.OCT.2019
Halliburton Hydraulic PrV Trailer Work Method WM-GL-HAL-PE-412

Step Work Instructions/Sequence Visual Instructions

3b

Unit Preparation:
3 a) Ensure hatch is open on tank
b) If connecting to an external tank ensure drain valves are open to supporting tank

Unit Set Up: 4d


a) Run cables to TCC and remote control
b) Start the power pack. (ball valve open until warmed up)
c) Turn on master power switch on electrical enclosure 4e
d) Ensure the Relief Valve Back Pressure control is set to at least 500 psi over unloader mode on the
4 Remote Control Panel
e) Turn the power switch on the Remote Control Panel to ON
f) Allow components to warm to operating temperature
g) Tare the Remote Control Panel pressure displays to zero psi by holding the P key for three seconds 4g

5a

Prime Up:
a) Set the Relief Valve Back Pressure control to OFF position
5c
5 b) Set the manual isolation valve to fully open
c) Set the hydraulically-controlled isolation valve to OPEN
d) Pump fluid through the high pressure manifold until it is clearly flowing in the tank

REVIEW/REVISION DATE:
Printed version of this document is uncontrolled 2 15.OCT.2019
Halliburton Hydraulic PrV Trailer Work Method WM-GL-HAL-PE-412

Step Work Instructions/Sequence Visual Instructions

Set PRV: 4-in. Double Poppet Relief Valve Manual


a) Establish hydraulic oil supply to the relief valve
b) Bleed off the air from the hydraulic system
c) Check the maximum pressure setting by slowly turning the pressure-adjustment knob clockwise until it stops
turning. The pressure gauge should now indicate a pressure of 2,400 psi or greater. If the indicated pressure is less
than 2,400 psi, adjust the emergency relief valve; this valve is located on top of the hydraulic manifold and is screw
adjusted. Turn this adjustment screw clockwise until the pressure indicates 2,500 psi. Lock the emergency relief
valve at this setting, and then turn the adjustment knob counterclockwise until 2,400 psi is indicated
6 d) Set PRV 500 psi above maximum kick out pressure setting, without exceeding lowest rated DME component.
Follow manual for setting PRV
e) Set the desired relieving pressure for the treating job with the pressure-adjustment knob. Turning this knob
counterclockwise reduces the relieving pressure. To relate the hydraulic pressure to the approximate treating- 6c
relieving pressure, multiply the hydraulic pressure by 6.25.
f) Open remote valve at PRV trailer and ensure all valves are open to PRV trailer

Pre job Leak Test:


7d
a) Set the remote-control panel to specified pressure by monitoring the relief-pressure digital display.
b) Bring the line pressure up to 1,000 psi less than the set relief pressure
c) Set the hydraulically-controlled isolation valve to CLOSED
7 d) Monitor the Relief Pressure display to determine any leakage
7c

e) Set the hydraulically-controlled isolation valve to OPEN by holding the switch in the OPEN position until
the green OPEN light turns on
f) Bleed off Pressure

During Job Leak Test:

a) Set the hydraulically-controlled isolation valve to CLOSED


8 b) Monitor the Relief Pressure display to determine any leakage 10- 30 seconds
c) Set the hydraulically-controlled isolation valve to OPEN by holding the switch in the OPEN position until the green
OPEN light turns on.

REVIEW/REVISION DATE:
Printed version of this document is uncontrolled 3 15.OCT.2019
Halliburton Hydraulic PrV Trailer Work Method WM-GL-HAL-PE-412

Step Work Instructions/Sequence Visual Instructions

PRV Activation:
a) Typically a PRV activation is a stage ending event
9 b) To reset PRV, lower hydraulic pressure by turning the pressure adjustment knob counter clock wise, this will
reduce pressure prior to activating reset button and prevent damage to internal components

Contingency plan should customer increase pressure requirements during Frac job:
10 PRV MUST be set to 500 psi higher than anticipated kick out pressure BEFORE kick outs are set! Pressure-Relief Valve Trailer Operation and Maintenance Manual

REVIEW/REVISION DATE:
Printed version of this document is uncontrolled 4 15.OCT.2019
Halliburton Hydraulic PRV Trailer Work Method WM-GL-HAL-PE-412

NOTES:

Review/Revision
DATE Summary of Revisions
No
01.OCT.2019 6 Annual review; no revisions/updates
26.JUL.2017 5 Annual review; no revisions/updates
APR.2015 4 Complete revision to document
Revisions highlighted in BLUE to; Quality/Critical Checks, Work
MAY.2013 3
Instructions/Sequence, Prime Up, Visual Instructions
MAR.2013 2 Annual review; no revisions/updates
JAN.2012 1 Original release

REVIEW/REVISION DATE:
5 14.APR.2015