Judul Dokument Penulangan Pondasi Telapak
6. PONDASI TELAPAK
Pembebanan
Balok sloof = 0,30.0,40.2400 = 288 kg/m'
Tembok = 3,45 . 250 = 862,5 kg/m'
q 1150,5 kg/m'
Statika L = 1,10 m
Mtum = 1/18 x 1150,5 x 1,1^2 = 174,01313 kgm
bc = 300 = 1
300
Vu = 3,42 kN
Mu = 8,28 kNm
s tanah = 5,095 x 100 = 509,5 kNm2
d = 600 - 50 = 550 mm
bo = 4 x (550 + 300) = 3400 mm
Statika
bc = 300 = 1
300
Vu = 3,42 kN
Mu = 8,28 kNm
s tanah = 5,095 x 100 = 509,5 kNm2
d = 600 - 50 = 550 mm
bo = 4 x (550 + 300) = 3400 mm
No. Doc :
Judul Dokument Penulangan Pondasi Telapak
Penulangan
Penulangan lapangan
Mu 560,23 kgm b 1200 mm
fc' (beton) 21,7 Mpa h 600 mm
fy' (baja) 400 Mpa d' 70 mm
Penulangan
mm2 mm
Lapangan X (tul atas) 2226,00 D19 - 120 ( 2.363 mm2 ) ok
Tumpuan Y (tul atas) 2226,00 D19 - 120 ( 2.363 mm2 ) ok
Tumpuan X (tul bagi) 890,40 D16 - 150 ( 1.340 mm2 ) ok