■FDH JV
FLUOR I OAEWOO E&C I HYUNDAI
KIPIC AI-Zour Refinery Project (ZOR)
Contract No.:L9ZR-Dl-50-K205
SMP - Utilities Area

Correspondence No.: Dl-50-K205-FDH/NBTC-0051-L

13 June 2018

NASER M. AL-BADDAH & PARTNER GENERAL TRADING & CONTRACTING CO. W.L.L.
P.O. Box 9088,
AHMADI 61001,
KUWAIT

Dear Mr. Chandrasekaran Sundar - Project Manage『

Subject: Key Personnel - Company Review


Reply Requi『ed: No
Refe『ence(s): 1 ) Dl-50-1<205-NBTC/FDH-0107-L dated 3 June 2018
2) 01-50-1<205-NBTC/FDH-0061-L dated 31 March 2018
3) Dl-50-1<205-NBTC/FDH-0111-L dated 9 June 2018

Company has completed its review of Contractor's proposed candidates and hereby advises of the following
comments·
S/N Refe『ence Name Designation
1 Dl-50-1<205-NBTC/FDH-0107-L Sam Raj QA/QC Inspector - Welding
2 01-50-1<205-NBTC/FDH-0107-L Shibu Chacko Foreman - Painting
3 Dl-50-1<205-NBTC/FDH-0061-L Jamadar Riyaz Mubarak HSE Supervisor
4 01-50-1<205-NBTC/FOH-0111-L Dong Yeol Lee Mech. Construction Manager
Company's Comments;

S/N 1 to 2 Rejected by Company.


SIN 3 Rejected by Owner
S/N4 Approved by Company.

With reference to Contractor's request for replacement of Construction Manager, Company notifies
Contractor that Contractor's request does not fulfill the condition set forth in Part Ill; Sub-Clause 25.5,
therefore, Company 『eserves all its rights, entitlement and benefits under the Contract and wavies none.

Please acknowledge 『eceipt of this correspondence by signing whe『e indicated below and returning a copy
to the undersigned within two (2) business days.

Yours sincerely, Receipt Acknowledged

Date
NASER M. AL-BADDAH & PARTNER
GENERAL TRADING & CONTRACTING CO.
W.L.L.

For and on behalf of FDH JV

Attachment(s): None

cc: Eric Armstrong, JV Site Subcontracts Manager

Dl-50-K205-FDHINBTC-0051-L Page 1 of 2