This document is a joint inspection observation sheet for a 96.8 MW wind power project. It notes various civil works that require completion or repair at different wind turbine generator locations, such as road repairing, filling and compaction, culvert work, vegetation removal, and ramp construction. A total of 190 observations are recorded across different dates and locations, primarily pertaining to unfinished or damaged civil infrastructure works. Target completion dates are not provided for most observations which currently have an "Open" status.
This document is a joint inspection observation sheet for a 96.8 MW wind power project. It notes various civil works that require completion or repair at different wind turbine generator locations, such as road repairing, filling and compaction, culvert work, vegetation removal, and ramp construction. A total of 190 observations are recorded across different dates and locations, primarily pertaining to unfinished or damaged civil infrastructure works. Target completion dates are not provided for most observations which currently have an "Open" status.
This document is a joint inspection observation sheet for a 96.8 MW wind power project. It notes various civil works that require completion or repair at different wind turbine generator locations, such as road repairing, filling and compaction, culvert work, vegetation removal, and ramp construction. A total of 190 observations are recorded across different dates and locations, primarily pertaining to unfinished or damaged civil infrastructure works. Target completion dates are not provided for most observations which currently have an "Open" status.
Sl. Nb. Date Element Description of Observation rid charge completion (Open / Close)
Road repairing, Murom filling and its compaction is
11 21/07/21 GJ026 SGRE Civil Open required at 4 places Causeway construction balance at the entrance of 19 21/07/21 GJ024 SGRE Civil Open location 20 21/07/21 GJ024 SGRE Civil CD work is required at one place, near the location. Open Road repairing, Murom filling and its compaction is 28 21/07/21 GJ039 SGRE Civil Open required at 3 places from GJ024 to GJ039 Road repairing, Murom filling and its compaction is 35 21/07/21 GJ034 SGRE Civil Open required at 4 places Road repairing, Murom filling and its compaction is 43 21/07/21 GJ035 SGRE Civil Open required at 2 places 44 21/07/21 GJ035 SGRE Civil 1 no Culvert side wall brickwork repairing is required Open Vegetation grew up all around the location which needs 45 21/07/21 GJ035 SGRE Civil Open to be remove Road repairing, Murom filling and its compaction is 53 21/07/21 GJ038 SGRE Civil Open required at 4 places 54 21/07/21 GJ038 SGRE Civil Tree cutting is required at one place Open Road repairing, Murom filling and its compaction is 70 21/07/21 GJ022 SGRE Civil Open required at 5 places Water accumulation and undulations found around the 71 21/07/21 GJ022 SGRE Civil Open foundation pedestal which needs to be repair Road repairing, Murom filling and its compaction is 82 21/07/21 GJ029 SGRE Civil Open required 3 places proper ramp needs to be develop at the entrance of 83 21/07/21 GJ029 SGRE Civil Open location 97 21/07/21 GJ31 SGRE Civil proper ramps development is required at 2 places Open Road repairing, Murom filling and its compaction is 104 21/07/21 GJ032 SGRE Civil Open required 2 places Road repairing, Murom filling and its compaction is 112 21/07/21 GJ036 SGRE Civil Open required 2 places Road repairing, Murom filling and its compaction is 120 21/07/21 GJ30 SGRE Civil Open required 4 places Road repairing, Murom filling and its compaction is 129 21/07/21 GJ037 SGRE Civil Open required 4 places 130 21/07/21 GJ037 SGRE Civil Staircase foundation is found damaged Open Road repairing, Murom filling and its compaction is 144 22/07/21 GJ003 SGRE Civil Open required at 2 places vegetation grew up all around the location which needs to 145 22/07/21 GJ003 SGRE Civil Open be remove 153 22/07/21 GJ042 SGRE Civil Culvert work is WIP, murrum filling and rolling is pending Open At the entrance of location Proper ramp with both side 162 22/07/21 GJ006 SGRE Civil Open drainage needs to be developed Road repairing, Murom filling and its compaction is 168 22/07/21 GJ010 SGRE Civil Open required at 2 places Road damaged at several places, needs to be repaired 182 22/07/21 GJ020 SGRE Civil Open properly with compaction Road repairing, Murom filling and its compaction is 190 22/07/21 GJ015 SGRE Civil Open required at 3 places Proper ramp with drainage needs to be developed at the 191 22/07/21 GJ015 SGRE Civil Open entrance of location Project Capacity : 96.8 MW Site Name : VENA Site, JIVAPUR
Compliance Date of Action Taken Photograph / Status Compliance