You are on page 1of 50

ARGO NAVIS ENGINEERS LTD.

TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

W-ORIGINAL
FEASIBILITY STUDY OF BWTS
RETROFIT INSTALLATION

04/03/2022
Project No.: 21468
FIRST ISSUE

REV. NO. DATE DESCRIPTION DRAWN APPROVED

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 1 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

DISCLAIMER

This document was developed by ARGO NAVIS ENGINEERS LTD. (in Greek ΑΡΓΚΟ ΝΑΒΙΣ ΣΥΜΒΟΥΛΟΙ ΜΗΧΑΝΙΚΟΙ ΕΠΕ) for assisting the
involved parties select the BWTS for installation on board subject series of ships.

This document contains descriptions and references to technical data and drawings of the below origins:

a. The vessel’s Builder (as built drawings), used by the explicit permission of the vessel’s Owner, who is the end receiving party of
this document and shared only those drawings or parts of them, absolutely necessary and for this project and purpose only.
b. The Ballast Water Treatment System (BWTS) maker, by whose permission those drawings are used for this project and purpose
only.
c. ARGO NAVIS ENGINEERS LTD. who designed all those additional pieces of equipment and outfitting, necessary for the
integration of the retrofitted BWTS with the vessel’s piping and other auxiliary systems.

All technical data, specifications and other information contained herein is deemed to be the proprietary intellectual property of the
above entities as per case. The vessel’s Owner’s or BWTS maker’s representative(s) may not make use of and publicize subject Document
of ARGO NAVIS ENGINEERS LTD. without its express written consent.

Use of the technical data or specifications contained herein is at user's risk and ARGO NAVIS ENGINEERS LTD. expressly disclaims
responsibility for such use and the situations that may result therefrom.

ARGO NAVIS ENGINEERS LTD. makes no warranty, express or implied, that utilization of the technology or products disclosed herein will
not infringe any industrial or intellectual property rights of third parties.

The receiving - this document - party, being the Client’s representative(s), undertakes not to disclose to any third party any information
provided herein in confidence by ARGO NAVIS ENGINEERS LTD. and shall not permit access to it by any third party unless ARGO NAVIS
ENGINEERS LTD. expressly grants permission.

Otherwise ARGO NAVIS ENGINEERS LTD. General Terms and Conditions for the Provisions of Services shall apply (and prevail all above
conditions in case of conflict).

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 2 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

TABLE OF CONTENTS
Introduction .................................................................................................................................... 6
1.1 Vessel Particulars .................................................................................................................................... 7
1.2 Vessel’s Water Ballast System ................................................................................................................ 8
1.3 Scope of Work......................................................................................................................................... 9
1.4 Maker ERMA FIRST ............................................................................................................................... 10

BWTS Installation ......................................................................................................................... 14


2.1 New Ballast Diagram ............................................................................................................................. 14
2.2 New Cooling Water and Compressed Air Diagram ................................................................................ 14
2.3 Equipment Arrangement ...................................................................................................................... 14
2.4 ERMA FIRST Equipment Position – Engine Room Arrangement – Option A .......................................... 15
2.5 Information about New Pipes Collision with Existing Structure ............................................................ 31
2.6 ERMA FIRST Equipment Position – Engine Room Arrangement – Option B .......................................... 35
2.7 Information about New Pipes Collisions with Existing Structure .......................................................... 43

Power requirements ..................................................................................................................... 44


3.1 Vessel’s Electric Load Analysis .............................................................................................................. 44
3.2 Maker’s Power Consumption ................................................................................................................ 46
3.3 Spare Circuit Breakers ........................................................................................................................... 47

Conclusion ..................................................................................................................................... 50

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 3 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

TABLE OF FIGURES

Figure 1 - Ballast Water Treatment System fundamental components (example arrangement) ........ 10
Figure 2 - Maker Piping Diagram (For Reference only) ....................................................................... 12
Figure 3 - Maker Piping Diagram (For Reference only) ....................................................................... 13
Figure 4 – BWTS, Equipment Marked, Perspective View, Option A .................................................... 16
Figure 5 – BWTS, Pipe Lines Marked, Perspective View, Option A...................................................... 17
Figure 6 – BWTS, Floor (4240mmA/B), Top View ............................................................................... 18
Figure 7 – BWTS, 2nd Deck (9490mm A/B), Top View ......................................................................... 18
Figure 8 – BWTS, 1st Deck (14800mm A/B), Top View ........................................................................ 19
Figure 9 – BWTS, Floor and 2nd Deck, Forward View .......................................................................... 19
Figure 10 – BWTS, Floor, 2nd and 1st Deck, Forward View .................................................................. 20
Figure 11 – Filter position, 2nd Deck (9490mm A/B), Forward View.................................................... 21
Figure 12 – BWTS, Floor (4240mmA/B), Looking Port ........................................................................ 21
Figure 13 – Position of Filter, Electrolytic Cell and Suction Pump, 2nd Deck (9490mm A/B), Perspective
View .................................................................................................................................................. 22
Figure 14 – Equipment position, 2nd Deck (9490mm A/B), Perspective View ..................................... 22
Figure 15 – New Overboard, Perspective View .................................................................................. 23
Figure 16 – Position of Control, Connection and Filter Starter Panels, 2nd Deck (9490mm A/B),
Perspective View ............................................................................................................................... 23
Figure 17 – T/R position, 1st Deck (14800mm A/B), Perspective View ................................................ 24
Figure 18 – Position of NAT, TROs, Drain Tank and DAP03, Floor (4240mmA/B), Perspective View ... 24
Figure 19 – Sea Water Pump position, Floor (4240mmA/B), Perspective View .................................. 25
Figure 20 – APT connections, Floor (4240mmA/B), Perspective View ................................................ 25
Figure 21 – BWTS, Floor (4240mmA/B), Perspective View ................................................................. 26
Figure 22 – Position of V6-01 and BWN09 valves, Perspective View .................................................. 26
Figure 23 – Position of by-pass valve V1-01, Floor (4240mmA/B), Perspective View .......................... 27
Figure 24 – BWTS, Floor (4240mmA/B), Perspective View ................................................................. 27
Figure 25 – Tie-In Points on MBL-01 and MBL-03, Perspective View .................................................. 28
Figure 26 – Tie-In Points on MBL-08 and MBL-09, Perspective View .................................................. 29
Figure 27 – Tie-In Points on MBL-10, Perspective View...................................................................... 29
Figure 28 – Tie-In Points on MBL-11, Perspective View...................................................................... 30
Figure 29 – Tie-In Points on MBL-12, Perspective View...................................................................... 30
Figure 30 – Equipment relocation and new deck penetration, Option A & B...................................... 31
Figure 31 – Pipe modification, Option A & B ...................................................................................... 31
Figure 32 – Tools relocation, Option A & B ........................................................................................ 32
Figure 33 – Tools relocation, Option A & B ........................................................................................ 32
Figure 34 – Pipe and cables modifications, Option A ......................................................................... 33
Figure 35 – Light fixture modification, Option A ................................................................................ 33
Figure 36 – Tools relocation and structures modifications, Option A & B ........................................... 34
Figure 37 – BWTS, Equipment Marked, Perspective View, Option B .................................................. 36
Figure 38 – BWTS, Pipe Lines Marked, Perspective View, Option B .................................................... 37

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 4 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

Figure 39 – BWTS, Floor (4240mmA/B), Top View ............................................................................. 38


Figure 40 – BWTS, Floor and 2nd Deck, Forward View ........................................................................ 38
Figure 41 – Position of by-pass valve V1-01, Floor (4240mmA/B), Perspective View .......................... 39
Figure 42 – By-pass valve V1-01, Floor (4240mmA/B), Perspective View ........................................... 39
Figure 43 – Tie-In Points on MBL-01 and MBL-03, Perspective View .................................................. 40
Figure 44 – Tie-In Points on MBL-08 and MBL-09, Perspective View .................................................. 41
Figure 45 – Tie-In Points on MBL-10, Perspective View...................................................................... 41
Figure 46 – Tie-In Points on MBL-11, Perspective View...................................................................... 42
Figure 47 – Tie-In Points on MBL-12, Perspective View...................................................................... 42
Figure 48 – Pipe and cables modifications, Option B.......................................................................... 43
Figure 49 – Light fixture modification, Option B ................................................................................ 43
Figure 50 – Vessel’s Electric Load Analysis ......................................................................................... 44
Figure 51 – Vessel’s Electric Load Analysis ......................................................................................... 45

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 5 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

Introduction

The Vessel W-ORIGINAL is a Bulk Carrier with an overall length 229 m sailing under the flag of Liberia. Her Gross Tonnage is
44325 and Deadweight is 81874T. Vessel was built in 2012.

The undertaken work consists of the feasibility study for the potential installation of ERMA FIRST ballast water treatment
system inside Engine room with 1 x 1200m3/h capacity system along with its pipe routing to comply with the D2 regulation
(as per IMO/USCG).
An onboard survey was conducted to perform 3D laser scanning, site survey of the existing ballast system and identify
locations for installation of BWTS equipment. The vessel is equipped with two Ballast Pumps (each with capacity: 1200 m3/h,
25m) one working at time for operation, both located in Engine Room. This report is prepared to check the feasibility for
installation of BWTS system inside Engine Room.

ERMA FIRST BWTS (1 x 1200 m3/h) is considered for the feasibility study.

The report details the above mentioned BWTS system integration with vessels ballast system and the modifications that are
required in the vessel for the installation of BWTS system.

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 6 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

1.1 Vessel Particulars

Vessel Name: W-ORIGINAL

Vessel Type: Bulk Carrier


Flag/Port of Registry: Liberia/Monrovia
IMO Number: 9627758

Year of Built: 2012

Classification Society: LR
Gross Tonnage: 44325
Deadweight: 81874 T

Draft Designed: 12.20 m

Draft Scantling: 14.50 m

Depth: 20.20m

Breadth: 32.26 m

Length Overall: 229.00 m

Length between Perpendiculars: 225.00 m


Capacity of No.1 Ballast Pump: 1200 m3/h, 25m
Capacity of No.2 Ballast Pump: 1200 m3/h, 25m

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 7 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

1.2 Vessel’s Water Ballast System

As understood from the received as build vessels documents, below is the list of the Ballast Tanks that will have to be filled
with ballast water.

No.
Ballast Water Compartment Capacity [m3]

1 FORE PEAK TANK 1567.2


2 No.1 W.B.TK(P) 1511.3
3 No.1 W.B.TK(S) 1511.3
4 No.2 W.B.TK(P) 1543.2
5 No.2 W.B.TK(S) 1543.2
6 No.3 W.B.TK(P) 3104.7
7 No.3 W.B.TK(S) 3104.7
8 No.4 W.B.TK(P) 1548.9
9 No.4 W.B.TK(S) 1458.9
10 No.5 W.B.TK(P) 904.2
11 No.5 W.B.TK(S) 904.2
12 No.6 W.B.TK(P) 1078.0
13 No.6 W.B.TK(S) 1078.0
14 A.P.TK 1057.4
SUB TOTAL (WITHOUT CARGO HOLD) 22005.2
16 NO.4 HOLD 12986.2
TOTAL (WITH CARGO HOLD) 34991.4
No. Ballast Water Compartment Capacity [m3]

Equipment Table

No. Pump Capacity [m3/h x m] Location

1 Ballast Pump No.1 1200x25 E/R


2 Ballast Pump No.2 1200x25 E/R
3 Bilge/Fire & G.S. Pump No.1 90/250x75/25 E/R

4 Bilge/Fire & G.S. Pump No.2 90/250x75/25 E/R

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 8 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

1.3 Scope of Work

The undertaken work constitutes the feasibility study for the potential retrofit installation of ERMA FIRST BWTS. Based on
the survey on board and 3-D scanning of the vessel’s available spaces, different installation scenarios are designed and
investigated. The main goals are:

• To find a suitable location.


• To secure available maintenance space.
• To ensure that the installed components and new piping do not disturb the safe operation of the vessel.
• To minimize modifications on the existing piping systems and structural members.
• To provide the most cost-effective solution.
• To implement maker installation instructions (where available) to the extent appropriate for this stage of study.

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 9 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

1.4 Maker ERMA FIRST

Selected BWTS type: 1 x ERMA FIRST BWTS FIT 1200 + FWM

The ERMA FIRST FIT Water Treatment System applies established Chlorine (Cl 2) technology to oxidize and disinfect Aquatic
Invasive Species (AIS).
The ERMA FIRST Ballast Water Treatment System consists of a filter element for particles larger than 40 μm, a disinfection
unit (electrolytic cell), a Transformer/Rectifier unit, Total Residual Oxidants (TRO’s), neutralization module, monitoring and
control auxiliary equipment (Salinity or Conductivity meter – SMD - Flow Switch, Temperature sensor, pressure indicator)
and BWTS control panel (includes control switches, PLC, data logger and HMI).

FILTER
ELECTROLYTIC CELL

POWER SUPPLY BWTS PANEL


UNIT
TRANSFORMER/
RECTIFIER

Figure 1 - Ballast Water Treatment System fundamental components (example arrangement)

The operation of ERMA FIRST BWTS FIT is divided in two different operational modes: ballasting and de-ballasting.

In both modes, the ballast pumps are in operation but the valve arrangement is such that during ballasting mode, water is
directed from the sea chest, through the BWTS to the ballast tanks, and during de-ballasting mode, water is directed from
ballast tanks to the overboard discharge point. By-pass is also an option in case of an emergency situation.

Ballasting mode description

During uptake, water is being pumped from the sea chest by the ballast pump. Ballast water is directed from the pump
delivery to the BWTS inlet.

The filter’s effluent is then directed to electrolyzer for the second stage of BWTS process. A flow switch, installed on the
inlet line of the electrolyzer, activates the electrolytic process when flow is detected. In the electrolyzer, ballast water
already treated at the primary stage, is exposed to a low-voltage direct current causing electrolysis. During this process,
TRO is produced at concentration up to 6 mg/L. A temperature sensor installed downstream of the electrolyzer stops the
BWTS process when high temperature is measured. The electrolyzer operates optimally at waters with salinity equal or
greater than 0,9 PSU and temperature down to -2°C. Chlorine concentration is continuously monitored via a TRO device.
The result of the TRO device is used to drive the current across the electrodes for the production up to 4-6 mg/L of TRO.
The potential across the electrodes is continuously changed when the resistance, i.e. salinity of the ballast water changes.

The products of the BWTS treatment process flow from the BWTS outlet into the ballast water tanks of the vessel, so that
the residual oxidants disinfect any harmful organisms taken on board.

The treated ballast water remains in the ballast tanks until the de-ballasting operation is due to start. TRO is consumed by
any viable remaining microorganisms and therefore is gradually reduced. It is calculated that after 4 days no TRO is still
contained in the treated water.

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 10 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

De-ballasting mode description

During de-ballasting ERMA FIRST BWTS FIT is by-passed, as no further treatment of ballast water is needed. Residual
chlorine possibly remaining in the ballast water tanks is neutralized by the BWTS neutralization module, which consists of
TRO monitors, a chemical dosing pump and a portable chemical storage tank of adequate volume.

During de-ballasting a TRO monitor measures TRO in the ballast water to be discharged and determines neutralization
dosing rate. A second TRO monitor verifies that TRO concentration is below 0.1ml/lt prior to discharge. If the chlorine
concentration is greater than 0.1 mg/L (Maximum Allowable Discharge Concentration, MADC) the neutralizing agent dosing
rate is automatically increased to the dosing pump’s maximum capacity.

Major BWTS components to be transported and installed / connected / wired as necessary inside Engine Room are:

• FILTER (F-1-A)
• ELECTROLYTIC CELL (C-1-A)
• TRANSFORMER RECTIFIER (T/R-1-A)
• NEUTRALIZING AGENT SODIUM BISULPHITE STORAGE TANK (NAT)
• FILTER SUCTION PUMP (SP-1-A)
• SEA WATER PUMP (SWP1)
• TRO (CHLORINE SENSOR MEASURING DEVICE) (TRO1 & TRO2)
• FLOW METER UNIT (FM-1-A)
• TRO GRAVITY DRAIN TANK (TGDT)
• CONTROL PANEL (CP1)
• FILTER STARTER PANEL (FSP-1-A)
• CONNECTION PANEL (JB)
• SEA WATER PUMP STARTER PANEL (SWPSP)
• PNEUMATIC DIAPHRAGM PUMPS (DAPs)
• SALINITY MEASURING MODULE PANEL (SMD-1-A)

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 11 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

Figure 2 - Maker Piping Diagram (For Reference only)

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 12 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

Figure 3 - Maker Piping Diagram (For Reference only)

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 13 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

BWTS Installation
2.1 New Ballast Diagram

For new Ballast diagram including BWTS connections with existing piping please refer to:
• 21468-P-PD-01-BALLAST SYSTEM DIAGRAM–OPTION A-PRELIMINARY
• 21468-P-PD-01-BALLAST SYSTEM DIAGRAM–OPTION B-PRELIMINARY

2.2 New Cooling Water and Compressed Air Diagram

For new piping diagrams including BWTS connections with existing piping please refer to:
• 21468-P-PD-03-COMPRESSED AIR SYSTEM DIAGRAM-PRELIMINARY
• 21468-P-PD-04-COOLING FRESH WATER SYSTEM DIAGRAM-PRELIMINARY

2.3 Equipment Arrangement

For new BWTS equipment arrangement please refer to:


• 21468-G-04-BWTS EQUIPMENT ARRANGEMENT-PRELIMINARY

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 14 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

2.4 ERMA FIRST Equipment Position – Engine Room Arrangement – Option A

ERMA FIRST equipment in Option A, positioned according to following table:


Longitudinal position, Transversal Vertical Position,
Equipment
Between frames position Deck
Filter (F-1-A) FR31 – FR33 Stbd Side 2nd Deck
Electrolytic Cells (C-1-A & C-2-A) FR34 – FR35 Stbd Side 2nd Deck
Suction Pump (SP-1-A) FR31 – FR32 Port Side 2nd Deck
Sea Water Pump (SWP1) FR37 Stbd Side Floor
Neutralizing Agent Tank (NAT) FR30 – FR32 Stbd Side Floor
Control Panel (CP1) FR35 Stbd Side 2nd Deck
Chorine Sensor Module (TRO1 & TRO2) FR28 – FR31 Stbd Side Floor
TRO Gravity Drain Tank FR29 – FR30 Stbd Side Floor
Transformer Rectifier (T/R-1-A) FR28 Stbd Side 1st Deck
Repeater Panel (RP1) FR31 – FR34 Port Side A Deck
Connection Panel (JB) FR35 Stbd Side 2nd Deck
Filter Starter Panel (FSP-1-A) FR35 Stbd Side 2nd Deck

Please refer to 21468-G-04-BWTS EQUIPMENT ARRANGEMENT-PRELIMINARY for more information about BWTS
equipment position.
New BWTS lines legend:

MBL-01- Inlet Piping to Filter


MBL-02- Inlet Piping to Electrolytic Cells
MBL-03- Outlet Piping from Electrolytic Cells
MBL-04- Inlet Piping to Suction Pump
MBL-05- Outlet Piping from Suction Pump
MBL-06- Inlet Piping to Sea Water Pump
MBL-07- Outlet Piping from Sea Water Pump
MBL-08- APT Inlet to System Piping
MBL-09- APT Outlet from System Piping
MBL-10- Main Overboard Piping Port Side
MBL-11- Main Overboard Piping Stbd Side
MBL-12- Bilge Overboard Piping

The following snapshots indicate the arrangement of the treatment system inside Ship’s Engine Room.

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 15 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

CP1 FM-1-A C-1-A SP-1-A

FSP-1-A
T/R-1-A

TRO1 & 2 NAT DAP2

TGDT
DAP3
SWPSP
SWP1

F-1-A DAP1

Figure 4 – BWTS, Equipment Marked, Perspective View, Option A

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 16 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

MBL-11
MBL-02

MBL-03

MBL-04

MBL-07 MBL-10

MBL-12

MBL-06 MBL-09 MBL-08 MBL-01 MBL-05

Figure 5 – BWTS, Pipe Lines Marked, Perspective View, Option A

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 17 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

Figure 6 – BWTS, Floor (4240mmA/B), Top View

C-1-A

F-1-A

Figure 7 – BWTS, 2nd Deck (9490mm A/B), Top View

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 18 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

T/R-1-A

Figure 8 – BWTS, 1st Deck (14800mm A/B), Top View

CP1 MBL-03 F-1-A MBL-02 MBL-01

NAT

Figure 9 – BWTS, Floor and 2nd Deck, Forward View

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 19 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

T/R-1-A

MBL-02

SWP1

Figure 10 – BWTS, Floor, 2nd and 1st Deck, Forward View

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 20 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

CP1 MBL-03 F-1-A MBL-02

Figure 11 – Filter position, 2nd Deck (9490mm A/B), Forward View

SWPSP TRO1 & 2

NAT
SWP1

MBL-09 MBL-08

Figure 12 – BWTS, Floor (4240mmA/B), Looking Port

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 21 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

FM-1-A V1-03 Spool for future


installation of Vacuum
Relief Valve

MBL-03

V3-01
C-1-A

MBL-02
V3-02

V1-02

F-1-A SP-1-A

MBL-01
Figure 13 – Position of Filter, Electrolytic Cell and Suction Pump, 2nd Deck (9490mm A/B), Perspective View

MBL-02

MBL-03
F-1-A

MBL-01

MBL-05 MBL-04 C-1-A


SP-1-A
Figure 14 – Equipment position, 2nd Deck (9490mm A/B), Perspective View

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 22 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

MBL-02 MBL-05 New penetration

MBL-03

F-1-A

MBL-01

Figure 15 – New Overboard, Perspective View

FSP-1-A JB CP1

Figure 16 – Position of Control, Connection and Filter Starter Panels, 2nd Deck (9490mm A/B), Perspective View

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 23 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

T/R-1-A

Figure 17 – T/R position, 1st Deck (14800mm A/B), Perspective View

TRO2 TRO1

NAT

TGDT DAP3

Figure 18 – Position of NAT, TROs, Drain Tank and DAP03, Floor (4240mmA/B), Perspective View

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 24 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

MBL-07

MBL-06 SWP1

Figure 19 – Sea Water Pump position, Floor (4240mmA/B), Perspective View

SWP1

MBL-09

BWN15 MBL-08
Figure 20 – APT connections, Floor (4240mmA/B), Perspective View

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 25 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

MBL-07

SWP1

MBL-06

Figure 21 – BWTS, Floor (4240mmA/B), Perspective View

V6-01 BWN09

MBL-01

MBL-07
Figure 22 – Position of V6-01 and BWN09 valves, Perspective View

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 26 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

MBL-01

BWN01
MBL-03
V1-01

MBL-09

Figure 23 – Position of by-pass valve V1-01, Floor (4240mmA/B), Perspective View

MBL-03

MBL-01

MBL-08

MBL-09

Figure 24 – BWTS, Floor (4240mmA/B), Perspective View

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 27 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

MBL-01

TP02
TP03

MBL-03

TP01

TP07 TP04

TP05

TP06

Figure 25 – Tie-In Points on MBL-01 and MBL-03, Perspective View

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 28 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

MBL-08

MBL-09
TP13
TP12

Figure 26 – Tie-In Points on MBL-08 and MBL-09, Perspective View

MBL-10

TP09

TP08

Figure 27 – Tie-In Points on MBL-10, Perspective View

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 29 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

TP11 MBL-11

TP10

Figure 28 – Tie-In Points on MBL-11, Perspective View

MBL-12

TP14

TP15

Figure 29 – Tie-In Points on MBL-12, Perspective View

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 30 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

2.5 Information about New Pipes Collision with Existing Structure

Equipment behind
Electrolytic Cell should be
relocated

MBL-03

MBL-02
C-1-A

Deck
penetration

Figure 30 – Equipment relocation and new deck penetration, Option A & B

Existing pipe in collision


with MBL-03 to be
modified accordingly

MBL-03

C-1-A

Figure 31 – Pipe modification, Option A & B

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 31 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

Tools behind Filter


should be relocated

MBL-01 F-1-A

SP-1-A
MBL-04

Figure 32 – Tools relocation, Option A & B

Tools behind panels


should be relocated

CP1

FSP-1-A
JB

Figure 33 – Tools relocation, Option A & B

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 32 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

Existing cooling sea


water pipe and cables to
be modified accordingly

MBL-01

MBL-03

Figure 34 – Pipe and cables modifications, Option A

Light fixture to be
modified accordingly

Figure 35 – Light fixture modification, Option A

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 33 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

Tools to be relocated
accordingly

Existing structure to be
modified accordingly

Pressure Reducing Valve


BWN10

Figure 36 – Tools relocation and structures modifications, Option A & B

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 34 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

2.6 ERMA FIRST Equipment Position – Engine Room Arrangement – Option B

ERMA FIRST equipment in Option B is on the same position as well in Option A.


Longitudinal position, Transversal Vertical Position,
Equipment
Between frames position Deck
Filter (F-1-A) FR31 – FR33 Stbd Side 2nd Deck
Electrolytic Cells (C-1-A & C-2-A) FR34 – FR35 Stbd Side 2nd Deck
Suction Pump (SP-1-A) FR31 – FR32 Port Side 2nd Deck
Sea Water Pump (SWP1) FR37 Stbd Side Floor
Neutralizing Agent Tank (NAT) FR30 – FR32 Stbd Side Floor
Control Panel (CP1) FR35 Stbd Side 2nd Deck
Chorine Sensor Module (TRO1 & TRO2) FR28 – FR31 Stbd Side Floor
TRO Gravity Drain Tank FR29 – FR30 Stbd Side Floor
Transformer Rectifier (T/R-1-A) FR28 Stbd Side 1st Deck
Repeater Panel (RP1) FR31 – FR34 Port Side A Deck
Connection Panel (JB) FR35 Stbd Side 2nd Deck
Filter Starter Panel (FSP-1-A) FR35 Stbd Side 2nd Deck

Please refer to 21468-G-04-BWTS EQUIPMENT ARRANGEMENT-PRELIMINARY for more information about BWTS
equipment position.
New BWTS lines legend:

MBL-01- Inlet Piping to Filter


MBL-02- Inlet Piping to Electrolytic Cells
MBL-03- Outlet Piping from Electrolytic Cells
MBL-04- Inlet Piping to Suction Pump
MBL-05- Outlet Piping from Suction Pump
MBL-06- Inlet Piping to Sea Water Pump
MBL-07- Outlet Piping from Sea Water Pump
MBL-08- APT Inlet to System Piping
MBL-09- APT Outlet from System Piping
MBL-10- Main Overboard Piping Port Side
MBL-11- Main Overboard Piping Stbd Side
MBL-12- Bilge Overboard Piping

The following snapshots indicate the arrangement of the treatment system inside Ship’s Engine Room and differences
between Option A and Option B.

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 35 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

CP1 FM-1-A C-1-A SP-1-A

FSP-1-A
T/R-1-A

TRO1 & 2 NAT DAP2

TGDT
DAP3
SWPSP
SWP1

F-1-A DAP1

Figure 37 – BWTS, Equipment Marked, Perspective View, Option B

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 36 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

MBL-11
MBL-02

MBL-03

MBL-04

MBL-07 MBL-10

MBL-12

MBL-06 MBL-09 MBL-08 MBL-01 MBL-05

Figure 38 – BWTS, Pipe Lines Marked, Perspective View, Option B

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 37 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

Figure 39 – BWTS, Floor (4240mmA/B), Top View

Figure 40 – BWTS, Floor and 2nd Deck, Forward View

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 38 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

MBL-01

V1-01

MBL-03

Figure 41 – Position of by-pass valve V1-01, Floor (4240mmA/B), Perspective View

V6-01 BWN09

V1-01

MBL-01

Figure 42 – By-pass valve V1-01, Floor (4240mmA/B), Perspective View

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 39 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

MBL-01
TP02
TP03

MBL-03

TP04
TP05

TP01

Figure 43 – Tie-In Points on MBL-01 and MBL-03, Perspective View

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 40 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

MBL-08

MBL-09
TP11
TP10

Figure 44 – Tie-In Points on MBL-08 and MBL-09, Perspective View

MBL-10

TP07

TP06

Figure 45 – Tie-In Points on MBL-10, Perspective View

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 41 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

TP09 MBL-11

TP08

Figure 46 – Tie-In Points on MBL-11, Perspective View

MBL-12

TP12

TP13

Figure 47 – Tie-In Points on MBL-12, Perspective View

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 42 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

2.7 Information about New Pipes Collisions with Existing Structure

Existing cooling sea


water pipe and cables to
be modified accordingly

MBL-03

MBL-01

Figure 48 – Pipe and cables modifications, Option B

Light fixture to be
modified accordingly MBL-03

MBL-01

Figure 49 – Light fixture modification, Option B

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 43 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

Power requirements
3.1 Vessel’s Electric Load Analysis

Figure 50 – Vessel’s Electric Load Analysis

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 44 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

Figure 51 – Vessel’s Electric Load Analysis

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 45 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

3.2 Maker’s Power Consumption

ERMA FIRST FIT 1x1200 installed power should approximately be 97kW.

Ballast Pumps with new BWTS installed will be running at one condition:

a) Cargo Unload:
• Total power with BWTS: 714.6kW
• Number of running generators: 2 (2x690kW)
• Maximum load of each generator: 51.78%

• Number of running generators: 3 (3x690kW)


• Maximum load of each generator: 34.52%

It is concluded that there is enough available power for BWTS operation.

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 46 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

3.3 Spare Circuit Breakers

Following the survey on board which was preformed along with the 3DLS the following available spare circuit
breakers were found.

Location Description Depiction

No.2 440V P2707


Feeder (100/40A)
Panel

No.1 440V P2207


Feeder (100/50A)
Panel

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 47 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

No.1 440V P2411


Feeder (100/30A)
Panel

AC 220V 60/15A
Feeder
Panel

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 48 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

AC 220V 60/15A
Feeder
Panel

Photo not P2501


available. 400A
To be (To be
confirmed confirmed
on site. on site)

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 49 of 50
ARGO NAVIS ENGINEERS LTD. TMPL-03
Template Revision No.: 3
FEASIBILITY STUDY REPORT Revision Date: 01/2022

Conclusion

It is considered that installation of Erma First Fit 1 x 1200 system for the subject vessel is feasible.

Comparation Tables:

BWTS Option A
Advantage Disadvantages / Challenges
Due to two return connections, easier way to
More Tie-In Points.
ballast tanks on port and stbd side separately.
Installation of BWTS return pipe will be
challenging.

BWTS Option B
Advantage Disadvantages / Challenges
More closed valves in case of ballasting tanks
Less Tie-In Points.
on one side (port or stbd side).

Easier installation of BWTS return pipe.

Feasibility Study for BWTS Retrofit Installation


Vessel Name: W-ORIGINAL
Project No.:21468 Page 50 of 50

You might also like