ACTIVITY: REINFORCEMENT
Location: Date: _ _

Sr. No. DESCRIPTION YES N.A. REMARKS

1 Name, Date and Number of the Drawing


2 Are the latest "Good for Construction" drawings available?
Is the area prepared for starting reinforcement (shuttering complete,
3
cleaned, oiled, and taped)?
Are test results of bars available at site before starting the fabrication work
4
?
5 Has the required barricading and safety measures been taken?
Is the area to be reinforced compatible with the drawings that are provided?
6

7 Are the required tools available at site to ensure correct work?

8 Is the reinforcement kept ready on wooden runners to keep them clean?

Is the reinforcement free from oil, mud, grease and other forms of
9
contamination?
10 Is the overlapping ensured and the laps are staggered?
11 Has the anchoring been checked ?
Are the dowels for columns, beams and slabs in place and checked for
12
proper length ?
Are the required hooks fixed and is the chair height for the upper layer of
13
reinforcement correct ?
14 Is the reinforcement done as per specification and drawing ?
Are cover blocks provided and fixed in a systematically correct manner and
15
as per specifications?

16 Have beam and column joints checked for sufficient cover blocks?

Is the lock set properly mixed and the reinforcement turned into the fresh
17
lock set ?
Has the consultant inspected the reinforcement before the concreting has
18
started?
19 Has adequate lap lengths been provided for all the column bars ?
Is the steel scrap and the rings used for bundling collected in a safe place
20
to avoid any accidents ?

Checked By; Approved By;