Introduction

Senior High School is one of the educational institutions. It is far from the main
town and surrounded by trees and mountains. The students and teacher’s study and
work here since the school is nearby to the student’s residents and this is where the
teachers designated job. However, since the school is merely a developing school, the
surrounding is a bit disorganized and there are many things to work on in order
improve the way it is structed.

One of the issue the school has is that whenever it rains, flooding always happens
that causes to have a muddy and slippery pathways, which causes a lot of problem to
students and teachers because it stains with their pants and shoes soiled. They also
don’t feel secure because if ever they slip, it will result in catastrophe in their lives. In
Addition to that, the school ground has grasses and stone that makes it difficult for the
teachers and pupils to move around without tripping over them.

Therefore, the pathway outside the school gate and the quadrangle of Senior High
School must be fixed in order to avoid flooding. The result of renovating the school’s
walkways will be clean because there won't be any weeds or stones, two things that
contribute to the school's negative reputation. And after renovating the school grounds
then it will be appealing to them and they will feel comfortable, so other children will
be enticed to attend this school.

Rationale or Background
One of the schools in Samar that is still under development. Since it was founded
more than six years ago, it has added a new structure, classrooms, and practical
equipment that both teachers and students may utilize.

However, a lot of deficiencies in it as a developing institution. When rainstorm


happens, flooding occurs that make the teachers and students at risk since the pathways
will be blocked that makes them hard to evacuate. Also, the school ground are a bit
disorganized because there are many weeds and grasses that keeps growing and there
are also stones and sands that makes even hard for the teachers and student to walk
leisurely and comfortably since there is a possibility that it can cause instructors and
pupils to trip them over.

Hence, the purpose of this proposal is to create a secure and safe school walkways,
in order for those who come and go can have a comfortable walk inside and outside the
school gate.

Action Plan
The project is entitled Proposal for the Repair of the Pathways in Quadrangle and
Outside of School Gate. The main purpose of this proposal is to renovate the pathways
of the school in order to avoid unnecessary accidents that may danger the life of the
students and teachers. This will be done through delicately planning and from the help
constructors and the patron involve with this project. In order to carry out the project,
the proponent must adhere to a work plan that details how to fix the school’s
walkways.

Activity Objective Strategies Person Materials Time Expected


Involved Needed Frame Outcome
Submission, Approving The identified The patron, Requesting 10 days Approved
requesting an the issues and the proposals budget
approval to the project's suggested constructor, via letter
release of the required fixes will be and the
budget spending presented. School Head
plan and of Daram
funding National
High School.
Holding a To Measure the Head of the Blue print 7 days An organized
meeting between coordinate, distance of construction of the and well-
the Patron, schedule, the school worker and school planned
School Head, and handle ground and the assigned grounds initiative wil
and the the further outside of manager act as a
Constructor suggestion school gate to catalyst for
s that will have better the project's
be measurement launch.
discussed on spending
with the the material
designated needed.
worker
directly.
The repairment To repair Replacing the Construction Cement, 2 The
of the school the pathways workers and Sand, months repairment o
grounds and walkways that cause to assigned Stone, the pathways
pathways of the flood manager Asphalt in school is
outside of school school Concrete successful
gate. and
composite
pavement

Support or Budget
Personel Responsibility
Constructor The one who will repair the pathways to
the quadrangle and outside of the school
gate.

Assigned manager The one who will lead to the renovation of


the school’s walkways and the person in
charge of carrying out this project's main
objectives

Item Quantity Description Price Per Unit Amount


Cement 50 A binder, a substance used for Php 295.00 Php 14,750.00
construction that sets, hardens,
and adheres to other material
to bind them together.

Stone 40 m3 The hard substance, formed of Php 1,200.00 Php 48,000


mineral matter, of which rock
consists.

Sand 20 m3 A granular material composed Php 800.00 Php 16,000


of finely divided mineral
particles.

Asphalt 25 tons A mixture mainly composed Php 600.00 Php 15,000.00


concrete of mineral aggregates, asphalt
binder, and additive, and has
been widely applied in
pavement construction.