Korelasi Nilai N-SPT

Borlog Layer Soil Type cu gn g' σv' Cv


Depth (m) Dh (m) N Value f ( 0) Eu (kN/m2) E' (kN/m2) mv (m2/kN) e0 Cc Cr K (m/s) Cv (cm2/sec)
ID. (kN/m )2
(kN/m )3
(kN/m3) (kN/m2) (m2/day)
DB-01 1 CLAY 0 - 17 17 2 10 - 2500 1500 4.00E-04 16 6 51 1.49 0.35 0.1 1E-11 2.50E-05 0.00022
DB-02 2 CLAY 0 - 15 15 3 15 - 3750 2250 2.67E-04 16 6 147 1.48 0.275 0 1E-11 3.75E-05 0.00032
DB-03 3 CLAY 3 - 17 14 2.4 12.1429 - 3035.714 1821.429 3.29E-04 16 6 234 1.49 0.3179 0.1 1E-11 3.04E-05 0.00026
Project : Pembangunan Jalan
Location : Jalan RE Martadinata Tanjung Priok
Borelog : DB-01
Elevation :

Undrained Parameter (kN/m2) Drained Parameter (kN/m2)


Depth (m) Soil Type qc average N - SPT Symbol 2 Poisson Poisson ϒ
cu f Eu (kN/m ) Ed (kN/m2) c' f'
ratio ratio
0.0 - 3.0 Urugan Batu 60.0 M 180 38 45960 0.25 27576 0.25 0 47 19.25
3.0 - 17.0 Silt Lempung 2.0 C 13 - 4250 0.35 2550 0.35 0 25 15.74

undrained drained
e nc 150-200 cu 0.6 (150-200 cu)
oc 400-450 cu 0.6 (400-450 cu)

Project : Pembangunan Jalan


Location : Jalan RE Martadinata Tanjung Priok
Borelog : DB-02
Elevation :

Undrained Parameter (kN/m2) Drained Parameter (kN/m2)


Depth (m) Soil Type qc average N - SPT Symbol Poisson Poisson ϒ
cu f Eu (kN/m2) Ed (kN/m2) c' f'
ratio ratio
0.0 - 3.0 Batu Pasir 60.0 M 180 38 45960 0.25 27576 0.25 0 47 19.25
3.0 - 17.0 Silt Lempung 2.0 C 13 - 4250 0.35 2550 0.35 0 25 15.74

undrained drained
e nc 150-200 cu 0.6 (150-200 cu)
oc 400-450 cu 0.6 (400-450 cu)

Project : Pembangunan Jalan


Location : Jalan RE Martadinata Tanjung Priok
Borelog : DB-03
Elevation :

Undrained Parameter (kN/m2) Drained Parameter (kN/m2)


Depth (m) Soil Type qc average N - SPT Symbol Poisson Poisson ϒ
cu f Eu (kN/m2) Ed (kN/m2) c' f'
ratio ratio
3.0 - 17.0 Silt Lempung 2 C 16 - 3946 0.35 2367.85714 0.35 0 25 16.0

undrained drained
e nc 150-200 cu 0.6 (150-200 cu)
oc 400-450 cu 0.6 (400-450 cu)
CONSOLIDATION SETTLEMENT ANALYSIS
BASED ON SPT

PROJECT : Pembangunan Jalan


LOCATION : Jalan RE Martadinata Tanjung Priok
BORING HOLE NO. : DB-01

1). Soil Bearing Capacity

DEPTH gt g' c f q qult qall


(t/m3) (t/m3) (t/m2) Nc Nq Ng (t/m2) (t/m2) (t/m2)
(m) degree

0.00 - 3.00 1.925 0.925 18.012 37.61 59.033 46.478 59.599 2.775 1192.27 476.91
3.00 - 17.00 1.574 0.574 1.300 0.00 5.740 1.000 0.000 10.811 18.27 7.31

Ultimate bearing capacity:


2
qu = 1192.27 t/m
2
qall = 476.91 t/m

Safety Factor SF (=qu/Ds ) = 701.34

2). Settlement due to load


Dhi = (hi.Cc/(1+eo)).log(1+Ds/s'vo)

where: hi = thickness of layer-i


Cc = Compression Index of soil.
eo = initial void ratio.
s'vo = effective overburden pressure = po.
Ds = excess pressure from the load =Dp.

Factor of Load 1.00


Excess load:
2
Ds = 8.70 , load =. 1.70 t/m
gt g' po Dp DHi
Depth Interval (m) 3 3
Cc eo
(t/m ) (t/m ) (t/m2) (t/m2) (m)

0.00 - 3.00 1.925 0.925 0.000 0.000 1.388 8.70 0.000


3.00 - 17.00 1.574 0.574 0.350 1.500 6.793 8.70 0.702

Total Settlement = 0.702 m

3). Time Consolidation

Representing Cv Cv H-ekiv
Depth Interval
(m) (m2/year) (m2/sec) (m)

0.00 - 3.00 - - -
3.00 - 17.00 2.20E-04 6.97E-12 1.40E+01

H-ekiv = 14.00 m

CONS SETTLEMENT_REM TP_00 3


CONSOLIDATION SETTLEMENT ANALYSIS
BASED ON SPT

PROJECT : Pembangunan Jalan


LOCATION : Jalan RE Martadinata Tanjung Priok
BORING HOLE NO. : DB-01
Vertical degree of consolidation:
Uv = SQRT(4 / pi x (Cv/H-ekiv^2) t) untuk T<0,197 (Taylor, 1948)
= 1-(8/pi^2)EXP(-(pi^2*T/4)) untuk T>0,197 (Fox, 1948)

t t Uv Settlement
(tahun) (detik) (%)
(m)

85.00 2,680,560,000 1.10 0.773


80.00 2,522,880,000 1.07 0.750
75.00 2,365,200,000 1.04 0.726
70.00 2,207,520,000 1.00 0.702
65.00 2,049,840,000 0.96 0.676
60.00 1,892,160,000 0.93 0.650
55.00 1,734,480,000 0.89 0.622
50.00 1,576,800,000 0.85 0.593
45.00 1,419,120,000 0.80 0.563
40.00 1,261,440,000 0.76 0.531
35.00 1,103,760,000 0.71 0.496
30.00 946,080,000 0.65 0.459
27.50 867,240,000 0.63 0.440
25.00 788,400,000 0.60 0.419
22.50 709,560,000 0.57 0.398
20.00 630,720,000 0.53 0.375
17.50 551,880,000 0.50 0.351
15.00 473,040,000 0.46 0.325
12.50 394,200,000 0.42 0.297
10.00 315,360,000 0.38 0.265
7.50 236,520,000 0.33 0.230
5.00 157,680,000 0.27 0.188
2.50 78,840,000 0.19 0.133
1.00 31,536,000 0.12 0.084
0.00 0 0.00 0.000

Settlement vs Time

1.000
0.900
0.800
Settlement (m)

0.700
0.600
0.500
0.400
0.300
0.200
0.100
0.000
0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 80.00 90.00

Time (Years)

Percent of Consolidation vs Time

1.20

1.00
Percent of Consolidation (%)

0.80

0.60

0.40

0.20

0.00
0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 80.00 90.00

Time (Years)

CONS SETTLEMENT_REM TP_00 4


CONSOLIDATION SETTLEMENT ANALYSIS
BASED ON SPT

PROJECT : Pembangunan Jalan


LOCATION : Jalan RE Martadinata Tanjung Priok
BORING HOLE NO. : DB-02

1). Soil Bearing Capacity

DEPTH gt g' c f q qult qall


(t/m3) (t/m3) (t/m2) Nc Nq Ng (t/m2) (t/m2) (t/m2)
(m) degree

0.00 - 3.00 1.925 0.925 18.012 0.00 5.740 1.000 0.000 2.775 106.16 42.47

Ultimate bearing capacity:


2
qu = 106.16 t/m
2
qall = 42.47 t/m

Safety Factor SF (=qu/Ds ) = 62.45

2). Settlement due to load


Dhi = (hi.Cc/(1+eo)).log(1+Ds/s'vo)

where: hi = thickness of layer-i


Cc = Compression Index of soil.
eo = initial void ratio.
s'vo = effective overburden pressure = po.
Ds = excess pressure from the load =Dp.

Factor of Load 1.00


Excess load:
2
Ds = 3.20 , load =. 1.70 t/m
gt g' po Dp DHi
Depth Interval (m) 3 3
Cc eo
(t/m ) (t/m ) (t/m2) (t/m2) (m)

0.00 - 3.00 1.925 0.925 0.275 1.480 1.388 3.20 0.173

Total Settlement = 0.173 m

3). Time Consolidation

Representing Cv Cv H-ekiv
Depth Interval
(m) (m2/year) (m2/sec) (m)

0.00 - 3.00 3.24E-04 1.03E-11 3.00E+00

H-ekiv = 3.00 m

CONS SETTLEMENT_REM TP_00 5


CONSOLIDATION SETTLEMENT ANALYSIS
BASED ON SPT

PROJECT : Pembangunan Jalan


LOCATION : Jalan RE Martadinata Tanjung Priok
BORING HOLE NO. : DB-02
Vertical degree of consolidation:
Uv = SQRT(4 / pi x (Cv/H-ekiv^2) t) untuk T<0,197 (Taylor, 1948)
= 1-(8/pi^2)EXP(-(pi^2*T/4)) untuk T>0,197 (Fox, 1948)

t t Uv Settlement
(tahun) (detik) (%)
(m)

85.00 2,680,560,000 6.24 1.078


80.00 2,522,880,000 6.05 1.046
75.00 2,365,200,000 5.86 1.013
70.00 2,207,520,000 5.66 0.979
65.00 2,049,840,000 5.46 0.943
60.00 1,892,160,000 5.24 0.906
55.00 1,734,480,000 5.02 0.867
50.00 1,576,800,000 4.79 0.827
45.00 1,419,120,000 4.54 0.785
40.00 1,261,440,000 4.28 0.740
35.00 1,103,760,000 4.00 0.692
30.00 946,080,000 3.71 0.641
27.50 867,240,000 3.55 0.613
25.00 788,400,000 3.38 0.585
22.50 709,560,000 3.21 0.555
20.00 630,720,000 3.03 0.523
17.50 551,880,000 2.83 0.489
15.00 473,040,000 2.62 0.453
12.50 394,200,000 2.39 0.414
10.00 315,360,000 2.14 0.370
7.50 236,520,000 1.85 0.320
5.00 157,680,000 1.51 0.262
2.50 78,840,000 1.07 0.185
1.00 31,536,000 0.68 0.117
0.00 0 0.00 0.000

Settlement vs Time

1.000
0.900
0.800
Settlement (m)

0.700
0.600
0.500
0.400
0.300
0.200
0.100
0.000
0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 80.00 90.00

Time (Years)

Percent of Consolidation vs Time

7.00

6.00
Percent of Consolidation (%)

5.00

4.00

3.00

2.00

1.00

0.00
0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 80.00 90.00

Time (Years)

CONS SETTLEMENT_REM TP_00 6


CONSOLIDATION SETTLEMENT ANALYSIS
BASED ON SPT

PROJECT : Pembangunan Jalan


LOCATION : Jalan RE Martadinata Tanjung Priok
BORING HOLE NO. : DB-03

1). Soil Bearing Capacity

DEPTH gt g' c f q qult qall


(t/m3) (t/m3) (t/m2) Nc Nq Ng (t/m2) (t/m2) (t/m2)
(m) degree

0.00 - 3.00 1.925 0.925 18.012 37.61 59.033 46.478 59.599 2.775 1192.27 476.91
3.00 - 17.00 1.574 0.574 1.300 0.00 5.740 1.000 0.000 10.811 18.27 7.31

Ultimate bearing capacity:


2
qu = 1192.27 t/m
2
qall = 476.91 t/m

Safety Factor SF (=qu/Ds ) = 701.34

2). Settlement due to load


Dhi = (hi.Cc/(1+eo)).log(1+Ds/s'vo)

where: hi = thickness of layer-i


Cc = Compression Index of soil.
eo = initial void ratio.
s'vo = effective overburden pressure = po.
Ds = excess pressure from the load =Dp.

Factor of Load 1.00


Excess load:
2
Ds = 8.70 , load =. 1.70 t/m
gt g' po Dp DHi
Depth Interval (m) 3 3
Cc eo
(t/m ) (t/m ) (t/m2) (t/m2) (m)

0.00 - 3.00 1.925 0.925 0.000 0.000 1.388 8.70 0.000


3.00 - 17.00 1.574 0.574 0.318 1.485 6.793 8.70 0.641

Total Settlement = 0.641 m

3). Time Consolidation

Representing Cv Cv H-ekiv
Depth Interval
(m) (m2/year) (m2/sec) (m)

0.00 - 3.00 - - -
3.00 - 17.00 2.62E-04 8.31E-12 1.40E+01

H-ekiv = 14.00 m

CONS SETTLEMENT_REM TP_00 7


CONSOLIDATION SETTLEMENT ANALYSIS
BASED ON SPT

PROJECT : Pembangunan Jalan


LOCATION : Jalan RE Martadinata Tanjung Priok
BORING HOLE NO. : DB-03
Vertical degree of consolidation:
Uv = SQRT(4 / pi x (Cv/H-ekiv^2) t) untuk T<0,197 (Taylor, 1948)
= 1-(8/pi^2)EXP(-(pi^2*T/4)) untuk T>0,197 (Fox, 1948)

t t Uv Settlement
(tahun) (detik) (%)
(m)

85.00 2,680,560,000 1.20 0.771


80.00 2,522,880,000 1.17 0.748
75.00 2,365,200,000 1.13 0.725
70.00 2,207,520,000 1.09 0.700
65.00 2,049,840,000 1.05 0.675
60.00 1,892,160,000 1.01 0.648
55.00 1,734,480,000 0.97 0.621
50.00 1,576,800,000 0.92 0.592
45.00 1,419,120,000 0.88 0.561
40.00 1,261,440,000 0.83 0.529
35.00 1,103,760,000 0.77 0.495
30.00 946,080,000 0.71 0.458
27.50 867,240,000 0.68 0.439
25.00 788,400,000 0.65 0.418
22.50 709,560,000 0.62 0.397
20.00 630,720,000 0.58 0.374
17.50 551,880,000 0.55 0.350
15.00 473,040,000 0.51 0.324
12.50 394,200,000 0.46 0.296
10.00 315,360,000 0.41 0.265
7.50 236,520,000 0.36 0.229
5.00 157,680,000 0.29 0.187
2.50 78,840,000 0.21 0.132
1.00 31,536,000 0.13 0.084
0.00 0 0.00 0.000

Settlement vs Time

1.000
0.900
0.800
Settlement (m)

0.700
0.600
0.500
0.400
0.300
0.200
0.100
0.000
0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 80.00 90.00

Time (Years)

Percent of Consolidation vs Time

1.40

1.20
Percent of Consolidation (%)

1.00

0.80

0.60

0.40

0.20

0.00
0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 80.00 90.00

Time (Years)

CONS SETTLEMENT_REM TP_00 8


Deskripsi Unit Borlog Id.
DB-01 DB-02 DB-03
Prediksi Total Consolidation [cm] 62.21 73.98 56.13
Total Time Consolidation, T90 [Tahun] 55.00 40.00 45.00