REPUBLIC OF THE PHILIPPINES

DEPARTMENT OF AGRARIAN REFORM


Tunay na Pagbabago sa Repormang Agraryo

ACTIVITY PROPOSAL

Title : Subdivision Survey of 366.8699 hectares Collective


CLOA

Proponent/s : DARPO, Sultan Kudarat Province


Amount : Php 1,804,266.00
Schedule : March to June 2021

I. RATIONALE

Land survey is one of the critical components of the Land Tenure Improvement (LTI) processes under
the Comprehensive Agrarian Reform Program (CARP).

In view of the continuing efforts of DAR Sultan Kudarat in the implementation of CARP, the LTI
Division has 41 landholdings covering 376.8994 hectares of lands for survey this year 2021 located in
Columbio, Sultan Kudarat.

Out of 41 LHs, eight are already included in Optool database and 33 LHs are for inclusion. These
landholdings were identified by field personnel in MARO Columbio and validated to be coverable
pursuant to RA 6657.

Per 2020 GAA of DAR and specifically for the Province of Sultan Kudarat, there is no budget
allocation for the New Lands Survey. Hence this request.

II. OBJECTIVE

To conduct field survey of the forty (41) landholdings located in Columbio, Sultan Kudarat
with a total area of 366.8699 hectares to be subdivided for the year 2021 but not included in the
previous years’ target.

III. PROJECT DESCRIPTION

a. Scope

The scope would cover 366.8699 hectares of collective CLOAs for subdivision survey and
individual titling located in the municipality of Columbio, Sultan Kudarat. The site is selected based
on the number of ARBs, area in hectares under collective CLOA and potential approved subdivision
plan within the year 2021.

b. Component
1
1. Subdivision Survey
1.1 Field validation of collective CLOAs
1.2 Verification of CLOAs with issues in cadastral surveys
1.3 Conduct of subdivision survey

IV. SCHEDULE OF ACTIVITIES/INDICATIVE WORK PLAN

PERSON/S
ACTIVITIES TIME FRAME
RESPONSIBLE

1. Conduct of Inventory March 2-6, 2021 LTID


2. Conduct of Orientation with the Field
March 9-10, 2021 DARPO
Personnel
3. Conduct of consultation/coordination meeting
with LGU March 11-13, 2021 MARO

4. Conduct meeting with sitio leaders March 16-20, 2021 MARO

5. Conduct of info dissemination March 23-27, 2021 MARO


MARO/legal
6. Conduct of Field Validation March 30-May 8, 2021 Officer/GE/
documentor

7. Conduct of preliminary survey activities May 11-14, 2021 LTID

8. Conduct of field survey work May 15-June 31, 2021 Surveyor/MARO

9. Preparation of survey returns July 3-14, 2021 Surveyor


10. Presentation of survey returns with the sitio
July 17-18, 2021 MARO/Surveyor
leaders

11. Submission of survey returns to DARPO July 21, 2021 MARO

12. Review of survey returns July 24-28, 2021 LTID


13. Conduct of Inspection by survey inspectorate Survey Inspectorate
August 1-4, 2021
team on survey conducted Team

14. Indorsement of Survey returns to DARRO August 9, 2021 LTID

15. Submission of Survey Returns to DENR August 16, 2021 LTID

16. Verification and Approval of survey returns


August 17-Sept. 9, 2021 SMD-DENR
by SMD

17. Approval of Survey Returns Sept. 12, 2021 DENR

VI. SOURCE OF FUND

Funding of the total budget of One Million Eight Hundred Four Thousand Two Hundred
Sixty-Six (Php 1,804,266.00) shall be charged against funds provided by the Survey Fund to be
downloaded by the DARCO BLTI.
2
Prepared by: Submitted by:

MAGDALENA T. VIDUYA RODOLFO T. ALBURO, CESE


CARPO for LTID PARPO II

Noted by: Funds Earmarked by:

ENGR. MARION Y. ABELLA, CESO V AURITA C.


ANG
Regional Director Director-FMS

Recommending Approval:

ATTY. DAVID D. ERRO ATTY. LUCIUS JUN JUN G.


MALSI
Undersecretary for FOO OIC-Undersecretary, FMAO

Approved by:

ATTY. JOHN R. CASTRICIONES


Secretary