Professional Documents
Culture Documents
The project was splitted in to three contracts, Contract 1: Hawassa – Chuko (66 km), Contract 2:
Chuko – Yirgachefe (60 km) and Contract 3: Yirgachefe – Ageremariam (72 Km).
Project Objective
Civil Work
Project Name : Chuko – Yirgachefe
Project Length : 60 km
Construction type : Asphalt Concrete
Contractor : China Railway no 3 Engineering Group
Funded by : ADB and GOE
Proportion of Payment
Date of contract signature : March 13,2017
Commencement Date : April 24, 2017
Original Completion Date : Feb 22,2019
Extension of time (EOT) : 331 Calendar days
Revised Completion Date : Jan 08, 2020 Rev. Jan 11,2021
Actual Completion Date Jun 1,2021, (EOT request to September)
Original Total Contract Sum : ETB 889,003,033.32
Estimated/Revised Final : ETB 885,169,608.41 (15% ETB and 85% USD) with all
Contract Sum Variation orders
Exchange Rate
Supervision Contract
Consultant : LEA International Ltd. In JV with LEA Associates South
Asia Pvt. Ltd. In association with Net Consultant Consulting
Engineers and Architects PLC
Contract Signing Date : Oct. 24,2012
Commencement Date : Dec 28,2012
Original Completion date : Dec 28,2015
Revised Completion date : Oct. 27,2012 REV Dec.2020 Rev. March 31,2021, (March
2022, EOT Request)
Original Contract Price : USD 1,170,500.00 and ETB 7,084,500.00
Revised Contract Price : USD 2,153,228.75 and ETB 10,306,414.29
Proportion of Payment