Mombasa–Nairobi–Addis Ababa Phase III Road Corridor Development Project (Hawassa-

Ageremariam) Road Rehabilitation Project

Background of the project

Hawassa – Ageremariam Road Project is part of Mombasa-Nairobi-Addis Ababa Corridor


Project and aims at promoting trade and regional integration between Ethiopia and Kenya. The
project road section, Hawassa - Ageremariam, is located in the southern Ethiopia, in the
Southern Nations, Nationalities & People’s Region (SNNPR) and its last section is connected to
the Oromia Region, BuleHora woreda of Guji Zone. The start of the project is Hawassa town at
the junction of Shashemene - Dilla Road and the road to Hawassa town about 257 km from the
capital city of Ethiopia on the main road of Modjo- Shashemene asphalt road. The end of the
project is Ageremariam town in Oromiya Regional State about 198 km from Hawasa town. Table
3 shows loan agreement data of Hawassa – Ageremariam.

The project was splitted in to three contracts, Contract 1: Hawassa – Chuko (66 km), Contract 2:
Chuko – Yirgachefe (60 km) and Contract 3: Yirgachefe – Ageremariam (72 Km).

Project Objective

Hawassa – Ageremariam Road Project is part of Mombasa-Nairobi-Addis Ababa Corridor


Project and aims at promoting trade and regional integration between Ethiopia and Kenya by
improving transport communications between the two countries.
Table 1: Hawassa-Ageremariam Loan Agreement Basic Data
Country Ethiopia
Project Title Hawassa – Ageremariam
Executing Agency Ethiopian Roads Administration
Project ID No P-Z1-DB0-070
Loan Number 2100150025545
Loan Amount UA 105,000,000
Signing Date 3-Febu-2012
Closing Date 31- Dec-2017
Revised Closing Date Dec 31, 2020.
Length 198km
Chuko – Yirgachaffe Rehabilitation Project; Contract II

Table 2 Chuko – Yirgachaffe Basic Contract Data

Civil Work
Project Name : Chuko – Yirgachefe
Project Length : 60 km
Construction type : Asphalt Concrete
Contractor : China Railway no 3 Engineering Group
Funded by : ADB and GOE
Proportion of Payment
Date of contract signature : March 13,2017
Commencement Date : April 24, 2017
Original Completion Date : Feb 22,2019
Extension of time (EOT) : 331 Calendar days
Revised Completion Date : Jan 08, 2020 Rev. Jan 11,2021
Actual Completion Date Jun 1,2021, (EOT request to September)
Original Total Contract Sum : ETB 889,003,033.32
Estimated/Revised Final : ETB 885,169,608.41 (15% ETB and 85% USD) with all
Contract Sum Variation orders
Exchange Rate
Supervision Contract
Consultant : LEA International Ltd. In JV with LEA Associates South
Asia Pvt. Ltd. In association with Net Consultant Consulting
Engineers and Architects PLC
Contract Signing Date : Oct. 24,2012
Commencement Date : Dec 28,2012
Original Completion date : Dec 28,2015
Revised Completion date : Oct. 27,2012 REV Dec.2020 Rev. March 31,2021, (March
2022, EOT Request)
Original Contract Price : USD 1,170,500.00 and ETB 7,084,500.00
Revised Contract Price : USD 2,153,228.75 and ETB 10,306,414.29
Proportion of Payment

Status of the project


 The project has been substantially completed, i.e., 95% of the physical work. After, the
loan agreement was closed at December 31, 2021 the government of Ethiopia is now
financing the project to complete the remaining works.