Professional Documents
Culture Documents
(Hinshitsu Hozen)
Background – QM Pillar
No structured approach
to analyze defects
Background
No customer
No sustained efforts satisfaction
For defect prevention
High process
Process condition are
variation
not standardized
Why Quality
Survival
Zero Globalization
Defect
Quality
Competition
Customer
Satisfaction Customer
Demand
Aim – QM Pillar
3 In process PPM
Rejection /Scrap
4 In process Rework PPM
QM Master Plan
Prepare QA matrix
Standardise 4M condition.
Revision of standards.
C) To achieve
Data Collection on Warranty Rej.
Warranty
rejection below
Analysis of Warranty phenomena. 2000 < 100
100
( A. Inspection side action ). PPM PPM
PPM.
Started Completed
10 Steps of Quality Maintenance
‘A’ Type defect: During normal production, products are produced with in the
tolerances of Upper Side Limit and Lower Side Limit. But suddenly one defect occurs.
Operator takes action for rectifying the cause of this defect occurred. When he starts
production, the next product is OK. Defects occurring in this situation are called as
A-Type Defect.
‘B’ Type defect: This type of defect also occurs during normal production. But the difference from A
type defect is that the next product is OK . We say that these defects are due to chance causes. These
defects occur and disappear by themselves without any corrective action taken.
This type of defect is dangerous as the we do not get to know the reason for the cause and how to
prevent them from repeating again.
FTA Analysis is the tool which is used to prevent this type of defect from
occurring. At times by looking at the process sequence in detail w.r.t.
defect and changing the sequence could eliminate the defect.
Defect Classification
‘C’ TYPE DEFECT
‘C’ Type defect: Defect occurred initially for some time and found Ok after taking action is called “C”
type defect.
Some defects occur during set up time and changeovers. Trial production and corrective measures are
taken to ensure defect free state so that the regular production begins. This condition arises due to
inadequate set-up procedures and lack of skills in jigs and fixtures positioning and setting
Key Points :
1. One defect phenomenon shall have one or more physical phenomenon.
2. CFT approach to be adopted to eliminate physical phenomenon.
3. Physical Phenomenon’s wise analysis & action to be initiated.
Actions with example
Action Definition Example No 01 Example No 02
Corrective action Actions taken to eliminate the defect Inspection side
Inspection side
• Restoring / modifying 4M1T conditions • Drill Size confirmation freq inspection increased
• Confirmation of spatter free threaded holes by 100%
• Should include cause side and inspection side from twice to 4 times in shift .
inspection of minor diameter by pin gauge.
action. Process side
• Inspection marking near threaded hole
Reactive approach • Drill replacement after 1000 Nos started to
Process side - CO2 Welding parameter change.
address tool wear.
• Current 140~160Amp and Voltage 18~25 V to
80~110Amp and 15~18 V respectively for spatter free
welding
• Masking of threaded hole
Preventive Action taken to Prevent the defect. Inspection Side Inspection Side
action • Defect can not be generated or defective parts
can not pass through the cell. Process side Process side
• Interlock of defect generating stage through • Drill 4.2 mm tool life interlock in drilling machine. • CO2 Welding parameter interlock with machine
control of contributing parameter or fool • Interlocking masking clamp with weld cycle
proof inspection of product (eg. No
declamping, no OK sticker generation, no
engraving etc)
Sustenance Monitor actions taken to prevent defect Inspection Side Inspection Side
generation / arrest defective delivery through fool • Pin OD monitoring
proof inspection. • 3 layer audit
Process side
• Verification of tool life monitoring Pokayoke Process side
• Process parameter monitoring
System side To document Preventive and Sustenance actions • Tool life to be update n IPO.
• CO2 Welding parameter standard up dation.
for preventing defects in similar process / product • Tool life interlock addition in PRBFM/PFMEA
• For welding of parts with threads , holes, studs etc.,
in future • Tool life study to be done before SOP wherever it
establish process for generating minimum spatter.
is CTQ
.
PHENOMENA WISE MONTHLY REJECTION QUANTITY
MATRIX ROTOR ASSEMBLY
Sr. DEFECT PHENOMENON DEFECT
Sept'07 Oct'07 Nov'07 Dec'07 Jan'08 Feb'08 Mar'08 Apr'08 May'08 Jun-08 Jul-08 Aug-08
No. (IN-PROCESS) TYPE
1 Drill hole through during balancing C 27 6 5 0 0 0 0 0 0 0 0 0
2 Rivet head damage A 5 4 0 1 0 2 0 0 0 0 0 0
3 Bolt broken B 25 24 13 0 4 3 0 0 0 0 0 0
4 Double marking A 11 12 0 0 0 0 0 0 0 0 0 0
5 Pip radius oversize (>57.75mm) B 121 140 7 0 3 0 0 0 0 0 0 0
6 Boss thread damage A 0 25 21 12 17 8 26 15 8 21 12 10
7 Magnet case scratch mark A 31 32 1 2 0 0 0 0 0 0 0 0
8 Plate starter clutch damage A 77 67 12 7 2 11 7 0 0 0 0 0
9 Magnet case up B 57 124 11 2 1 8 4 0 0 0 0 0
10 Pip radius undersize (<57.95mm) B 60 80 29 0 0 0 0 0 0 0 0 0
11 Magnet case shift A 31 35 7 3 0 0 1 0 0 0 0 0
12 Taper dent mark B 12 9 7 6 9 12 7 8 3 0 0 0
13 Keyway damage A 25 48 12 8 7 5 12 10 12 6 12 0
14 Pip damage A 11 15 12 9 11 15 12 10 9 12 9 9
15 Magnet case damage B 101 86 57 33 31 62 65 74 67 49 52 33
C. Contact V/s Fixed Value V/s Motion Reading Methods for Poka-
Yoke classification :
These use the principle of physical or energy contact with the product
using sensing devices. They range from guide pins, limit switches,
photo electric beams, etc.
Contact methods often take advantage of parts that are designed
with an uneven shape. We can use guide pins or blocks that don’t
allow the product to be seated in a machines jig in the wrong
position.
Theme: To eliminate PCD shift in K10 rotor boss
Before After
Alarm
BEFORE AFTER
Sustenance Plan :
Action plan in 5W2H,6W2H
Format
Step-5 – Analyze conditions for non defective units
that are not confirmed.
Quality Cost
Conformance Non-Conformance
KK PM ANALYSIS
Quality Maintenance
KAIZENS
Application of
PM Equipment diagnosis CONDITION MANAGEMENT (Follow Strictly)
Technology
Feedback
DM
MP DESIGN Fostering proficiency
of Employee in
Equipment operation
& maintenance
ACCOMPLISH
E&T
ZERO DEFECTS
THANK YOU