Name of Project Date Relocation Relocation Amount Amount for % of Completion Remarks
Started Cost Agreement Released Funding of Relocation of
Poles
Off-Carriageway 5/10/2018 P 376,434.00 None None P 100% Project
Improvement: Should 376,434.00 Completed.
Paving/Construction Implemented
along Tagbilaran City- by DPWH –
Corella-Sikatuna-Loboc Bohol 3rd
Rd – K022 + (-175) – DEO.
K0025 + 380 – Road Included in
Widening – Brgy. “Annex A” of
Tambis-oy, Loboc JC3. For
request for
funding.
JICA-Assisted Road 4/16/2018 P 832,743.88 None None P 100% Project is on-
Upgrading/Improvement 832,743.88 going.
Component of the Road Implemented
Upgrading & by DPWH –
Preservation Project RMC1 UPMO.
(RUPP) Included in
Reconstruction/Repair “Annex A” of
of Bridges Damaged by JC3. For
the 2013 Earthquake, request for
Province of Bohol, funding.
Contract Package III
Reconstruction of Clarin
Bridge
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CEBU 4TH DISTRICT ENGINEERING OFFICE
Regional Office No. VII
Name of Project Date Relocation Relocation Amount Amount for % of Completion Remarks
Started Cost Agreement Released Funding of Relocation of
Poles
Off-Carriageway 5/10/20 P 376,434.00 None None P 100% Project
Improvement: Shoulder 18 376,434.00 Completed.
Paving/Construction along Implemented
Tagbilaran City-Corella- by DPWH –
Sikatuna-Loboc Rd – K022 Bohol 3rd
+ (-175) – K0025 + 380 – DEO.
Road Widening – Brgy. Included in
Tambis-oy, Loboc “Annex A” of
JC3. For
request for
funding.
Road Widening – 4/16/20 P 832,743.88 None None P 100% Project is on-
Villalimpia (Clarin Bridge), 18 832,743.88 going.
Loay, Bohol Implemented
by DPWH –
RMC1 UPMO.
Included in
“Annex A” of
JC3. For
request for
funding.
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Bohol 1st DISTRICT ENGINEERING OFFICE
Regional Office No. VII
Name of Project Date Relocation Relocation Amount Amount for % of Completion Remarks
Started Cost Agreement Released Funding of Relocation of
Poles
Off-Carriageway 5/10/2018 P 376,434.00 None None P 100% Project
Improvement: Should 376,434.00 Completed.
Paving/Construction Implemented
along Tagbilaran City- by DPWH –
Corella-Sikatuna-Loboc Bohol 3rd
Rd – K022 + (-175) – DEO.
K0025 + 380 – Road Included in
Widening – Brgy. “Annex A” of
Tambis-oy, Loboc JC3. For
request for
funding.
JICA-Assisted Road 4/16/2018 P 832,743.88 None None P 100% Project is on-
Upgrading/Improvement 832,743.88 going.
Component of the Road Implemented
Upgrading & by DPWH –
Preservation Project RMC1 UPMO.
(RUPP) Included in
Reconstruction/Repair “Annex A” of
of Bridges Damaged by JC3. For
the 2013 Earthquake, request for
Province of Bohol, funding.
Contract Package III
Reconstruction of Clarin
Bridge