METHOD STATEMENT

Ref No. KU-TWK-10-EL-PLP-0002 Produced by Narrson Emanuel


Project: FSK IT and FOC Project Position Operations Coordinator
Project No. FSK-1019 Date 05/01/20
Location FSK
Area/Process Control Room

Description:
1. Installation of FOC.
2. Installation of ODF Switch.
3. Site Cleanup.

Personnel Involved in the Operations Equipment to Be Used


Name Duties 1- Hand Tools.
Warren Mills Project Manager 2- Testing Equipment.
Qutaiba Ahmed CCTV System Team Supervisor
Saif Ali CCTV Engineer
Muthana Abd CCTV Technician
Mohamed Sabeeh CCTV Technician
Khosro Karim QAQC

Preparations Before Commencement


N
Job Steps Description
o
1 General Safety  Each worker will have completed the mandatory HSE Induction (DNO) prior to work
commencing.
 Each Worker is required at all times to wear PPE.

2 Permits & Risk  Confirm Work Permit & Risk Assessments are in place and has been reviewed and
Assessments, and TBT approved by required authorized personnel.
 Confirm Toolbox talk/Method Statement Briefing has been conducted and all
personnel are fully aware of the sequence of operations and their individual
responsibilities.
 Before commencement of work confirm worksite is free from debris and any slip, trip
and fall hazards.

Comments:
…………………………………………………………………………………………………………………………………………….
...
……………………………………………………………………………………………………………………………………………

……………………………………………………………………………………………………………………………………………

……………………………………………………………………………………………………………………………………………

……………………………………………………………………………………………………………………………………………

Sequence of Events
No Job Steps Description
1 Fiber Optic  20 M of fiber optic cable will be cut and prepared for the connection.
Cables and  The cable will be dressed from ODF1 to ODF2 in an existing cable duct inside the control
HDPE Pipe room.
Installation  FOC will be connected to ODF1 from one end and to ODF2 from the other end.
 Patch Cord will be installed and connected from ODF-1 to Switch-1
 Patch Cord will be installed and connected from ODF-2 to Switch-2
 Only hand tools will be used for all activities.
 All works will be undertaken in coordination with DNO Maintenance and Systems Engineer.

2 Site  Supervisor to ensure the work areas are clean and tidied, prior to leaving the CPF. Return &
Cleanup Sign Off Permit to Work to Permit Office, and Control Room

Approved by (Talia): Approved by (DNO):

Position: Position:

Date: Date:

Signature: Signature: