1. Installation of FOC.
2. Installation of ODF Switch.
3. Site Cleanup.
2 Permits & Risk Confirm Work Permit & Risk Assessments are in place and has been reviewed and
Assessments, and TBT approved by required authorized personnel.
Confirm Toolbox talk/Method Statement Briefing has been conducted and all
personnel are fully aware of the sequence of operations and their individual
responsibilities.
Before commencement of work confirm worksite is free from debris and any slip, trip
and fall hazards.
Comments:
…………………………………………………………………………………………………………………………………………….
...
……………………………………………………………………………………………………………………………………………
…
……………………………………………………………………………………………………………………………………………
…
……………………………………………………………………………………………………………………………………………
…
……………………………………………………………………………………………………………………………………………
…
Sequence of Events
No Job Steps Description
1 Fiber Optic 20 M of fiber optic cable will be cut and prepared for the connection.
Cables and The cable will be dressed from ODF1 to ODF2 in an existing cable duct inside the control
HDPE Pipe room.
Installation FOC will be connected to ODF1 from one end and to ODF2 from the other end.
Patch Cord will be installed and connected from ODF-1 to Switch-1
Patch Cord will be installed and connected from ODF-2 to Switch-2
Only hand tools will be used for all activities.
All works will be undertaken in coordination with DNO Maintenance and Systems Engineer.
2 Site Supervisor to ensure the work areas are clean and tidied, prior to leaving the CPF. Return &
Cleanup Sign Off Permit to Work to Permit Office, and Control Room
Position: Position:
Date: Date:
Signature: Signature: