Reference No. : Date:

Company Name of Recipient


Address Line 1
Address Line 2
P.O. Box

For the Attention of Mr. ____________________ - “Designation”


Project Name :
Project No. :

Subject : RE: (CONTRACT NAME)


PRIORITY OF DOCUMENTS.

Dear Sir,

Further to the issue of the Engineer’s instruction regarding the clarification of the
ambiguity that existed between the detail shown on the drawing, reference XXXXX
and the detail reflected through the Specification, page XX item XX, we confirm that
this is not consistent with the hierarchy of documents that form part of the Contract
documentation, clause 1.6 and as such constitutes a variation as per clause 20.1 in the
Conditions of Contract.

Once the full ramification has been established we shall provide a fully detailed claim
and trust that the Engineer will approve the time and cost entitlement.

Yours faithfully,

for Urbacon Trading and Contracting

Name of Sender
Position

Enclosure :
Responds to Reference No. of Letter Responded or N/A :
Response Required : Yes or No
Date Required: : State Date if Applicable
 

________________________________________________________________________________________________________________________________
Tel +974 4429 2220 – 4429 2221 | Fax +974 4429 2244 | Email info@urbacon‐intl.com 
PO Box 201184, Doha, Qatar | www.urbacon‐intl.com 
Page 1 of 1                                                                                                                                                                                                                     
UCC‐IMS‐CC‐2001A‐01 Rev 0        Dated: May 11, 2016 

                     

You might also like