Professional Documents
Culture Documents
BILL OF QUANTITIES
ACCESS ROAD FROM M6.1 TO WF MESIHOVINA
B. EARTHWORKS
4. 21 232 Mechanical excavation of the upper soil layer
d=30 cm (50 or 100cm) in the part of widening
new clearance of the road, as indicated by the
cross sections in the design. Excavated soil need
to be loaded and transported to the landfill
provided by the contr
m3 24,925.20 4.00 99,700.80
Note: For additional description of the items in accordance with the listed codes, please see
1/11
the Guidelines for the design, construction, maintenance and supervision of roads, 2005.
WFM-LOT2-MD-1
Note: For additional description of the items in accordance with the listed codes, please see
2/11
the Guidelines for the design, construction, maintenance and supervision of roads, 2005.
WFM-LOT2-MD-1
C. DRAINAGE:
Note: For additional description of the items in accordance with the listed codes, please see
3/11
the Guidelines for the design, construction, maintenance and supervision of roads, 2005.
WFM-LOT2-MD-1
D. PAVEMENT STRUCTURE:
E. OTHER
18. Preparation of as built geodetic survey with
as built design, delivery on paper at a scale
1:1000, verified in two copies and
lump
electronically in DWG/DXF format on DVD sum 1 3000 3,000.00
Note: For additional description of the items in accordance with the listed codes, please see
4/11
the Guidelines for the design, construction, maintenance and supervision of roads, 2005.
WFM-LOT2-MD-1
RECAPITULATION
B. EARTHWORKS KM 728,439.28
C. DRAINAGE KM 109,430.86
E. OTHER KM 6,000.00
Note: For additional description of the items in accordance with the listed codes, please see
5/11
the Guidelines for the design, construction, maintenance and supervision of roads, 2005.
WFM-LOT2-MD-1
ACCOUNTING
ACCESS ROAD FROM M6.1 TO WF MESIHOVINA
B. EARTHWORKS
4. 21 232 Mechanical excavation of the upper soil layer
d=30 cm (50 or 100cm) in the part of widening
new clearance of the road, as indicated by the
cross sections in the design. Excavated soil need
to be loaded and transported to the landfill
provided by the contractor, with the previously
received permission of the local government.
Disposal of material is to be done in accordance
with the Construction Waste Management Plan.
Calculation per m3 naturally compacted material.
The price include the transport of materials.
Medium transportation distance up to 10 km.
Note: For additional description of the items in accordance with the listed codes, please see
6/11
the Guidelines for the design, construction, maintenance and supervision of roads, 2005.
WFM-LOT2-MD-1
Note: For additional description of the items in accordance with the listed codes, please see
7/11
the Guidelines for the design, construction, maintenance and supervision of roads, 2005.
WFM-LOT2-MD-1
C. DRAINAGE:
Note: For additional description of the items in accordance with the listed codes, please see
8/11
the Guidelines for the design, construction, maintenance and supervision of roads, 2005.
WFM-LOT2-MD-1
Note: For additional description of the items in accordance with the listed codes, please see
9/11
the Guidelines for the design, construction, maintenance and supervision of roads, 2005.
WFM-LOT2-MD-1
D. PAVEMENT STRUCTURE:
E. OTHER
18. Preparation of as built geodetic survey with
as built design, delivery on paper at a scale
1:1000, verified in two copies and
lump
electronically in DWG/DXF format on DVD sum 1 3000 3,000.00
Note: For additional description of the items in accordance with the listed codes, please see
10/11
the Guidelines for the design, construction, maintenance and supervision of roads, 2005.
WFM-LOT2-MD-1
RECAPITULATION
B. EARTHWORKS KM 728,439.28
C. DRAINAGE KM 109,430.86
E. OTHER KM 6,000.00
Note: For additional description of the items in accordance with the listed codes, please see
11/11
the Guidelines for the design, construction, maintenance and supervision of roads, 2005.