You are on page 1of 2

TT04-BM22

HÌNH TRUÏ HOÁ KHOAN (BORING LOG)


Coâng trình (Project) : KHU NHAØ ÔÛ THÖÔNG MAÏI BÌNH HOØA
Ñòa ñieåm (Location) : PHÖÔØNG BÌNH HOØA, XAÕ THUAÄN AN, T. BÌNH DÖÔNG
Hoá khoan (Bore hole) : HK1 Tyû leä (Scale) : 1/100
Cao ñoä (Elevation) : +0.000m (Giaû ñònh / Dummy elevation) Ngaøy khoan (Boring date) : 12/07/2016
Möïc nöôùc tónh (Ground water level) : -11.2m Toå tröôûng (Team leader) : ÑAÄU TOÁ ANH
Ñoä saâu hoá khoan (Total depth of hole) : 20.0m Giaùm saùt beân A(Supervisor) : TRAÀN NGOÏC SINH
Phöông phaùp khoan xoay söû duïng bentonite (Rotary drilling method) Maùy khoan(Driller) : XY-1
THÍ NGHIEÄM XUYEÂN TIEÂU CHUAÅN
Teân lôùp(Stratum No)

B-daøy lôùp(Thickness)

TRUÏ Soá hieäu


Cao ñoä(Elevation)
Tyû leä(Scale) (m)

(STANDARD PENETRATION TEST)


Ñoä saâu lôùp (m)

(Sampling and
CAÉT Soá buùa öùng
(Depth) (m)

vaø ñoä saâu

ñoä saâu SPT

depth SPT)
Soá hieäu vaø
MOÂ TAÛ vôùi 15cm
Bieåu ñoà SPT
(GRAPHIC

maãu (Blows pereach


LOG)

(DESCRIPTION OF SOIL) 15cm)


(CHART SPT)
(Sample No-

15cm
15cm
15cm
N
10 20 30 40 50
Samp. depth)

0.0 0.00 0.00

A 1.5 Ñaát ñaù, xaø baàn san laáp


1.0
-1.50 1.50
HK1-1 AÙ seùt, xaùm traéng - ñoám naâu ñoû
2.0 1 1.0 1.8 ÷ 2.0 1 1 2 3 3 SPT1-1
Traïng thaùi deûo cöùng 2.0 ÷ 2.45
-2.50 2.50
3.0

HK1-2
4.0 3.8 ÷ 4.0 3 5 6 11 11 SPT1-2
4.0 ÷ 4.45

2 4.5 Seùt, xaùm traéng - naâu ñoû, traïng thaùi deûo cöùng
5.0

HK1-3
6.0 5.8 ÷ 6.0 4 6 7 13 13 SPT1-3
6.0 ÷ 6.45

7.0 -7.00 7.00

HK1-4
8.0 7.8 ÷ 8.0 3 4 5 9 9 SPT1-4
8.0 ÷ 8.45

9.0
3 4.5 AÙ seùt, xaùm traéng, traïng thaùi deûo cöùng
HK1-5
10.0 9.8 ÷ 10.0 2 3 4 7 7 SPT1-5
10.0 ÷ 10.45

11.0
-11.50 11.50
HK1-6
12.0 11.8 ÷ 12.0 3 3 4 7 7 SPT1-6
12.0 ÷ 12.45

13.0

HK1-7
14.0 13.8 ÷ 14.0 3 4 6 10 10 SPT1-7
14.0 ÷ 14.45

15.0

4 8.5 HK1-8 AÙ caùt, vaøng naâu, traïng thaùi deûo SPT1-8


16.0 15.8 ÷ 16.0 3 5 6 11 11 16.0 ÷ 16.45

17.0

HK1-9
18.0 17.8 ÷ 18.0 4 6 7 13 13 SPT1-9
18.0 ÷ 18.45

19.0

HK1-10
20.0 -20.00 20.00 19.8 ÷ 20.0 4 7 9 16 16 SPT1-10
20.0 ÷ 20.45
TT04-BM22

HÌNH TRUÏ HOÁ KHOAN (BORING LOG)


Coâng trình (Project) : KHU NHAØ ÔÛ THÖÔNG MAÏI BÌNH HOØA
Ñòa ñieåm (Location) : PHÖÔØNG BÌNH HOØA, XAÕ THUAÄN AN, T. BÌNH DÖÔNG
Hoá khoan (Bore hole) : HK2 Tyû leä (Scale) : 1/100
Cao ñoä (Elevation) : +0.000m (Giaû ñònh / Dummy elevation) Ngaøy khoan (Boring date) : 03/12/2016
Möïc nöôùc tónh (Ground water level) : -10.2m Toå tröôûng (Team leader) :
Ñoä saâu hoá khoan (Total depth of hole) : 20.0m Giaùm saùt beân A(Supervisor) :
Phöông phaùp khoan xoay söû duïng bentonite (Rotary drilling method) Maùy khoan(Driller) : XY-1
THÍ NGHIEÄM XUYEÂN TIEÂU CHUAÅN
Teân lôùp(Stratum No)

B-daøy lôùp(Thickness)

TRUÏ Soá hieäu


Cao ñoä(Elevation)
Tyû leä(Scale) (m)

(STANDARD PENETRATION TEST)


Ñoä saâu lôùp (m)

(Sampling and
CAÉT Soá buùa öùng
(Depth) (m)

vaø ñoä saâu

ñoä saâu SPT

depth SPT)
Soá hieäu vaø
MOÂ TAÛ vôùi 15cm
Bieåu ñoà SPT
(GRAPHIC

maãu (Blows pereach


LOG)

(DESCRIPTION OF SOIL) 15cm)


(CHART SPT)
(Sample No-

15cm
15cm
15cm
N
10 20 30 40 50
Samp. depth)

0.0 0.00 0.00

A 1.2 Ñaát ñaù, xaø baàn san laáp


1.0
-1.20 1.20
HK2-1 AÙ seùt, xaùm traéng - ñoám naâu ñoû
1 1.2
Traïng thaùi deûo cöùng SPT2-1
2.0 1.8 ÷ 2.0 1 2 2 4 4 2.0 ÷ 2.45
-2.40 2.40

3.0

HK2-2
4.0 3.8 ÷ 4.0 3 4 6 10 10 SPT2-2
4.0 ÷ 4.45
2 4.3 Seùt, xaùm traéng - naâu ñoû, traïng thaùi deûo cöùng
5.0

HK2-3
6.0 5.8 ÷ 6.0 4 6 8 14 14 SPT2-3
6.0 ÷ 6.45

-6.70 6.70
7.0

HK2-4
8.0 7.8 ÷ 8.0 3 4 5 9 9 SPT2-4
8.0 ÷ 8.45
3 3.8 AÙ seùt, xaùm traéng, traïng thaùi deûo cöùng
9.0

HK2-5
10.0 9.8 ÷ 10.0 2 3 3 6 6 SPT2-5
10.0 ÷ 10.45
-10.50 10.50
11.0

HK2-6
12.0 11.8 ÷ 12.0 2 3 4 7 7 SPT2-6
12.0 ÷ 12.45

13.0

HK2-7
14.0 13.8 ÷ 14.0 3 4 5 9 9 SPT2-7
14.0 ÷ 14.45

15.0 AÙ caùt, vaøng naâu, traïng thaùi deûo


4 9.5
HK2-8
16.0 15.8 ÷ 16.0 4 4 6 10 10 SPT2-8
16.0 ÷ 16.45

17.0

HK2-9
18.0 17.8 ÷ 18.0 4 5 8 13 13 SPT2-9
18.0 ÷ 18.45

19.0

HK2-10
20.0 -20.00 20.00 19.8 ÷ 20.0 5 7 10 17 17 SPT2-10