MINUTES OF MEETING -ALTRON

MINUTES OF MEETING – FABRICATION WORKSHOP AND PRIORTIZED


SITE WORKS

Venue: ALTRON FABSHOP CEO MEETING ROOM Prepared by: Palaninadane.R

Date: 29/01/2023 Time: 04:00 PM Sheet No. 1 of 3

MINUTES OF MEETING FOR ONGOING WORKS IN FABRICATION WORKSHOP AND


PRIORITZED SITE WORKS

Minutes of Meeting

SN Attendees Signature
ALTRON
1. Mr. JINYOUNG LEE ALTRON CEO
2. Mr. HITESH RAVISH ALTRON PD
3. Mr. PALANINADANE RAJAKUMAR ALTRON PM
4. Mr. DHARMENDRA RAI ALTRON SUPERINTENDENT
CC
1. Mr. SURESH ROBY ELECTRICAL SUPERVISOR
ALTRON
2. Mr. GEORGE ADMIN MANAGER
ALTRON
3. Mr. VISHALKUMAR OPERATIONAL MANAGER
ALTRON
4. Mr. IDHAYADHULLAH MOHAMED SITE MANAGER
ALTRON
MEERA
5. Mr. MOHAMED AZEEM ABDUL DRAFTSMAN
ALTRON
SAMAD

1 | Page
MINUTES OF MEETING -ALTRON

S.No. Description A
I. Every day internal meeting to be conducted for daily Fabrication work RAI /
orders and Daily target to be fixed and reviewed.

II. Fabrication order form should be maintained properly for all Fabrication RAI /
works.

I. Portable Toilets first 3 Nos should be Transported to Site by Thursday


(02/02/2023).

II. Proper coordination should be done and care should be taken while
2
transporting the Portable toilet to site to avoid paint damage.

III. Transportation should be arranged with proper Escort permit and should
be coordinated in prior with ADMIN. RAI

I. W17 Diesel tank Stairs to be Transported by Thursday (02/02/2023).


3

RAI
II. Transportation should be arranged with proper Escort permit and should
be coordinated in prior with ADMIN.

I. Marker Post Sample should be completed on Priority and in Parallel to


be checked from Other Supplier for QUOTE and Supply. RAI /

II. Remaining 3 Portable Toilet work and Office Cabin works can be FOR
Slowdown.

RAI /
III. Priority should be given for First 3 portable Toilet Delivery, Plastering for
HITES
Accommodation rooms at workshop.

2 | Page
MINUTES OF MEETING -ALTRON

IV. FORKLIFT repair QUOTE to be finalized


CEO

V. Ceiling Change Schedule for MR.LEE room should be Prioritized.


RAI /
PALA
/HITE
VI. Lighting Drawings to be prepared for 10 Locations.
SURE

VII. Cable Pulling to be started on site by 06/02/2023 on Priority, Method of


Statement, JSA, Calibration Certificates for tools and Tackles to be
finalized and submitted. SURE

VIII. Additional Rollers required for Cable Pulling to be Finalized and MIR and
PR to be initiated.
SURE

IX. Battery Station Sunshade Shop Drawing to be coordinated by Gokul with


Mr. Idhay, once finalized Fabrication should be started on Priority
IDHA
GOKU

X. W 10 JDK Stores mini-DB 3 Nos should be incorporated in the Drawing


and Breaker Calculation to be finalized.
SURE
HITES
AZEE

3 | Page