You are on page 1of 7

MONITORING OF SD PROJECTS BY AM/L&A-STATUS AS ON -----------

A Zonal Railway
No of Stations -Work in Progress
B
with Name
No of Stations-Under Master
C
Planning with Name
No of Stations identified under
D
ABSS Scheme (Phase-I)
Budget Outlay Under PH-53 &
Expenditure till Date.
E
Additional Fund Required, if
any(FY wise)
Railway Stations -Work in Progress[To be filled for Each Station]
S. No. Item/Task / Obligation Remarks/Status/Other details
1. LoA Date and Name of Contractor
2. Appointed Date
Status of approval of Environment Management
3. Plan, Quality Control Mechanism, QAP, MTP and
MS
Status of Appointment of Proof Consultant, Safety
4.
Consultant & Design Director
Status of General Arrangement Drawings of Air
Concourse, Station Buildings, Preliminary Design
5.
Report /Design Basis Report, Architectural &
Structural Drawings
6. Status of Implementation of BIM Framework
Status of Works at Site
7.
(Physical Progress& Financial Progrees)
Details of Milestones lagging behind Contract
8.
Schedule along-with Action Plan and TDC
A Zonal Railway
No of Stations -Work in Progress
B
with Name
No of Stations-Under Master
C
Planning with Name
No of Stations identified under
D
ABSS Scheme (Phase-I)
Budget Outlay Under PH-53 &
Expenditure till Date.
E
Additional Fund Required, if
any(FY wise)
Railway Stations -Work in Progress[To be filled for Each Station]
S. No. Item/Task / Obligation Remarks/Status/Other details
Key Hurdles in Project:
9. Description of Assistance Required with
references made to Authority

Bar Chart for the Project with Major Key Milestones -To be attached
Note: Different colour legends shall be used to show timeline with respect to planned activity, work in progress, completed activity and
activities progressing in delay with planned activities.

Details of Obligations of Authority envisaged in the EPC Contract like Shifting of Utilities, relocation of structures, etc along with their
Status.
S.No. Name of Activity Scope of Work Status Tentative Date of Remarks
Completion
Site Photographs with Brief description and Watermark
a. Existing View of the Station (3 or more)
b. During Construction- View of the Station (3 or more)
c. Envisaged View of the Station
Note: - The photographs shall be taken preferably from good vantage points and similar angles for easy comparison during any stage of
project execution.

Railway Stations -Under Master Planning


S. No. Item/Task / Obligation Remarks/Status/Other details
No & Name of Stations whose Concept Plan
1.
under KD-3 stage approved by Railway Board
Status of Preparation of Master Plans & DPR and
Target Dates for Invitation of EPC Tender
No and Name of Stations whose Concept Plan
2. under preparation with Target Dates of
Presentation to Railway Board (KD-3)
No & Name of Stations whose Tender for
3.
Technical Consultant yet to be invited
Railway Stations -Identified under ABSS (Phase-I)
S. No. Item/Task / Obligation Remarks/Status/Other details
1. Total No & Name of Stations Identified
No & Name of Stations where Consultant
2
Appointed
No & Name of Stations where Consultant yet to
2.
be appointed with Action Plan
No & Name of Stations where Consultant Not
3.
Required
4. Stations where Works Contract Awarded
Stations where Tender for Works Contract to be
5.
invited with Action Plan

Status of Works at Railway Stations -Identified under Adarsh Station Scheme


S. No. Item/Task / Obligation Remarks/Status/Other details
Total No & Name of Stations Identified-
1.
Division-Wise
2 No & Name of Stations where work Completed
No & Name of Stations where work yet to be
2.
done
Details of Works Planned
S.No. Name of Station TDC
with Action Plan
3. Station-wise Work Planned with Action Plan
Status of Works at Railway Stations -Identified under Adarsh Station Scheme
S. No. Item/Task / Obligation Remarks/Status/Other details
No & Name of Stations where work yet to be
1.
Completed
Name of Details of Works Planned/Balance with Target Date of
S.No.
Station Action Plan Completion
2. Station-wise Work Planned with Action Plan 1.
2.
3.

Status of Works pertaining to Divyangjan (MEA) at Railway Stations


SNo Unit Total Scope Works Works Works TDC
Item/Task / and Station- Sanctioned Completed Targeted in
Obligation wise breakup 2022-23

1 FOB Nos.
2 HL PF Nos.
3 Ramp Nos.
4 Double height handrails One station
at ramps fully compliant
for Divyangjan
to be counted
as one unit
5 Tactile guiding blocks at One station
ramps, FOBs, Subways, fully compliant
Platforms for Divyangjan
to be counted
as one unit
6 Parking for Divyangjan One station
fully compliant
for Divyangjan
to be counted
as one unit
7 Braille signages One station
fully compliant
for Divyangjan
to be counted
as one unit
8 Low height ticket and One station
inquiry counters fully compliant
for Divyangjan
to be counted
as one unit
9 Toilet for Divyangjan One station
fully compliant
for Divyangjan
to be counted
as one unit
10 Drinking water booth for One station
Divyangjan fully compliant
for Divyangjan
to be counted
as one unit

Settlement Status of SFMA


All five stations handed over to respective Zonal Railways w. e. f. 01.04.22. Final settlement of dues with Railways in
progress. Railway has in-principle agreed for compensation vide letter No. 2017/LMB/WCS/22/01/22 dated
03.08.2022. Reconciliation is in progress.
SNo Station Name:- Status alongwith TDC

1. Secunderabad
2. Bangalore
3. Anand Vihar Terminal
4. Chandigarh
5. Pune