Work Method

PT. LANCANG
KUNING SUKSES Statement
(System to Work Safely)
Company/Department : PT. Lancang Kuning Sukses WMS No:
Address : 2020-F-LKS-HSE-NO.18
Work Location / Area : PT CATERPILLAR _Body Building Bay 1 - Expansion

DESCRIPTION & SCOPE OF WORK

PENJELASAN SINGKAT DAN LINGKUP PEKERJAAN

Instalation Roof Panel Body Building Bay 1 - EXPANSION


NAME OF CONTRACTOR SUPERVISOR AND SUPERVISOR JOB DESCRIPTION

NAMA PENGAWAS, ENGINEER & HSE KONTRAKTOR PELAKSANA DAN APA SAJA TUGAS TUGASNYA
1. Diaz P and Agus Supriyono as Site Supervisor
2. Mahesa and Angga as Engineer
3. Wigik, Fidiyansah, Norman and Amril Al Riza as HSE officer
Job Description
1. Site Supervisor
a. Inspecting construction sites regularly to identify and eliminate potential safety hazards.
b. Supervising and instructing the construction team as well as subcontractors.
c. Educating site workers on construction safety regulations and accident protocol.
d. Enforcing site safety rules to minimize work-related accidents and injuries.
e. Handling site accidents in accordance with established accident protocol.
f. Maintaining an accurate record of construction employee attendance.
g. Evaluating the performance of construction employees and instituting disciplinary measures as needed.
h. Analyzing blueprints to ensure that construction projects meet design, safety, and budget specifications.
i. Recommending changes to construction operations or procedures to increase efficiency.
2. Engineering
a. Managing parts of construction projects
b. Overseeing erection work
c. Undertaking surveys
d. Setting out sites 
e. Checking technical designs and drawings to ensure that they are followed correctly
f. Supervising contracted staff
g. Ensuring project packages meet agreed specifications, budgets and/or timescales
h. Liaising with clients, subcontractors and other professional staff, especially quantity surveyors and the overall project manager
i. Providing technical advice and solving problems on site
j. Preparing site reports and filling in other paperwork
k. Ensuring that health and safety and sustainability policies and legislation are adhered to.
3. HSE Officer
a. Advise and instruct on various safety-related topics (noise levels, use of machinery etc.)
b. Conduct risk assessment and enforce preventative measures
c. Review existing policies and measures and update according to legislation
d. Initiate and organize Safety Briefing of worker
e. Inspect premises and the work of personnel to identify issues or non-conformity (e.g., not using protective equipment)
f. Oversee installations, disposal of substances etc.
g. Stop any unsafe acts or processes that seem dangerous or unhealthy
h. Record and investigate incidents to determine causes.

IMPLEMENTATION PLAN (Start Date and End) And the Hour Start and Finish Every Day
RENCANA WAKTU PELAKSANAAN (Tanggal Mulai dan Selesai) Dan Jam Mulai dan Selesai Setiap Hari

Start Date 15 Mei 2022

Start Time 08.00 s/d 16.00

SEQUENCE OF WORK

URUTAN PELAKSANAAN PEKERJAAN

Work: Pemasangan Metal Sidding Body Building Bay 1 - EXPANSION

1. Preparation
1.1. Document preparation for work purpose (RA & PTW)
1.2. Safety briefing and TBM before proceed work activity
1.3. The Project In-charge will confirm area and method are ready to execute
1.4. Identify special safety equipment to be used
1.5. Coordinate with client to ensure suitable access will be available at all times.
1.6. Organize work group to perform the works. If necessary, organize with client suitable laydown
area close to work place.
1.7. Ensure all Access area are not difficult, dangerous and safe
1.8. Ensure All Supporting Document and Procedure and Permit in placed and has been read
1.9. All tools, equipment and worker has been prepared
1.10. All Suporting Document and Tooling has been prepared and ready
1.11. Barricade tape,protection has been prepared and install

2. Roll Forming, Lifting and Installation Procedure of Roof Panel


2.1. Prepare the working area level and compacted to store rolled panels
2.2. Assemble the Spreader Bar made ready for lifting of panels
2.3. Rolling of Panels to 27.000 mm long
2.4. Moving the rolled panel to Storage area
2.5. File of rolled panels
2.6. Preparation of panels for one secured lift
2.7. Lifting the Panels from Grid line 36 with the spreader bar, by using 1 cranes.
2.8. Team on the roof ready to receive the panels.
2.9. Trolley conveyor on the purlins. Trolley is used to distribute the panels on every bay
2.10. Placing the panels onto the trolley conveyor
2.11. Distributing the panels with the use of trolley
2.12. Distributed bundles of panels on the roof
2.13. Offloading the panels from trolley
2.14. Moving the Trolley to the lifting point
2.15. Fixing the Rake Angle and Rake Support
2.16. Laying of insulation
2.17. Laying of Panels
2.18. Moving the Panels to position
2.19. Instaled multiple panel runs
2.20. Panel is lifted to place in position
2.21. Fixing the end of the panel ath thr eave line
2.22. Cheking the width of the panel run
2.23. Fixing the Inside closure and tri-bead sealer
2.24. The articulating clip is placed in position and fastened with two screws
2.25. Fix of the minor rib tape to completely seal the eave assembly
2.26. Laying of succeeding insulation
2.27. Back up plate in position to maintain the module of the panel
2.28. Seaming of successive panes runs

3. Finishing
3.1. Cleaning the panels after installation. It is the standard operating procedure of cleaning
the roof panel every end of the day and after finishing the roof installation.
3.2. Finished roof panel installation

4. Drawing Life Line


Administrative Control of Risk
(Risk Assessment, Environmental Aspect Impact, MSDS, etc)

 Risk assessment
 Mitigation Plan W.A.H
 Drawing engineering Lifeline
 Pre-checklist W.A.H
 Inspection checklist.
Employee/Worker List
(list all employees/workers involved in work process)
No Name Position Department Competence/License/Certificate Remarks

1 Prastiwo Anggoro Project Manager Project

2 Sudomo Hse Manager Project

3 Fauzan Project Engineer Project

4 Cahyo Budi N SF Manager Project

5 Suranto Head Engineer Project

6 Diaz SPV Civil Project

7 Agus Supriyono Lead Project

8 Mahesa Engineer Project

9 Refki Engineer Project

10 Angga Engineer Project

11 Amril Al Riza HSE Officer Project

12 Wigik Febriyanto HSE Officer Project

13 Fidiyansah HSE Officer Project

14 Norman HSE Officer Project

15 Rizki Agustian Rigger Project

16 Deo Putra Rigger Project

17 Kurniawan Rigger Project

18 Decky Arisandi OP Mobile Crane Project

19 Zainal OP Crane Kato Project

20 Dwi Sitiyoso OP Boom Lift 1 Project

21 Abdullah OP Boom Lift 2 Project

22 Sandi W.A.H Project

23 Okta W.A.H Project

24 Effendi W.A.H Project

25 Egi W.A.H Project

Tools & Equipment


(List all)

Result direct checks


Kind of equipment & Tools Brand
Condition & Function Safe - Unsafe

Crane 45 T Houlotte Good Safe

Trolley 7 unit Houlotte Good Safe

Roof Panel Machine TBA Good Safe

Webing Sling 6 x 8 ton TBA Good Safe

Spreader bar 3 unit TBA Good Safe

Shackle 6.5 ton TBA Good Safe


Baricade TBA Good Safe

Personal Protective Equipment (PPE ) Required TBA

(List all)

Mandatory:

1. Full Body Harnes


2. Safety Helmet
3. Safety Glass
4. Safety Shoes
5. Hand Gloves
6. Ear Plug,
7. Mask

Additional:

1. Fall Protection Limiter


2. Lifeline
3. Head Lamp
4. Fire Blanket

Emergency Response at Site Project


Prepared by, Checked by, Approved by,
Project In charge QHSE Department (Project Leader)

Name: Nur Angga Name : Sudomo Name : Ir. Prastiwo


Tittle : Engineer Tittle : HSE Manager Tittle : Project
Date : 6 Mei 2022 Date : 18 August 21 Manager Date : 18
August 21