Version Control Sheet

Document Name : CM Audit Check List


Document Number : QMS/PE/018
Effective Date : 06.01.2020

Author: Reviewer:

EPG Team Kumar Amit

Signature Signature
Electronic copies valid without signature

Document Revision History


Ver. No Effective date Nature of Modification
1.0 Released Version
Sheet

Issue Number : 1
Version Number: 1.0
Document Version No: 1.0

: Approver:

mit Ratan Sah

Signature
signature

History
Nature of Modification
Released Version
CM Audit Check List

Project Name:

Reviewd By:

Date :

Self Check QA Check


No. Type Check Item Result Result NC#
Plan Baseline
1 Availability of Plan
2 File Naming convention followed
3 Work product is baseline
4 Work product has been reviewed (using review checklist)
5 All identified issues have been incorporated into work product & closed
6 Work product has been approved by approving authority
7 Folder structure in CM tool as per definition in CM plan
8 All work products have been baselined at defined baseline instance
9 Check-in remarks are entered as per defined standards
10 All project members use CM system for their day-to-day work as defined
11 CM system has capability to support organization CM requirement

Requirement Baseline
1 Work product is baseline
2 Work product has been reviewed (using review checklist)
3 Change Control Process
4 All identified issues have been incorporated into work product & closed
5 Work product has been approved by approving authority

Design Baseline
1 Work product is baseline
2 Work product has been reviewed (using review checklist)
3 All identified issues have been incorporated into work product & closed

Document No: QMS/PE/18 | Issue No: 01 | Revision No: 00 | Effective Date: 10 Dec 2016 | Page No: 3
CM Audit Check List

4 Work product has been approved by approving authority


Testing Baseline
1 Work product is baseline
2 Work product has been reviewed (using review checklist)
3 All identified issues have been incorporated into work product & closed
4 All work products have been baselined at defined baseline instance
Closure Baseline
1 Work product is baseline

Document No: QMS/PE/18 | Issue No: 01 | Revision No: 00 | Effective Date: 10 Dec 2016 | Page No: 4