Professional Documents
Culture Documents
ENGINEERING
Reason for Issue: Supersedes 3DG-E21E-00002, Rev. 001 and supersedes part of 3DG-E34E-
00001, Rev. 001 (Sections 2.0 Format, 3.0 Design Procedures, and 4.1 Power System Studies
(except 4.1.5 Harmonic Analysis Studies)
TABLE OF CONTENTS
1.0 PURPOSE
2.0 GENERAL
2.1 Scope
2.2 Codes and Standards
2.3 Format
5.0 CALCULATIONS
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be used,
disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 1 OF 49
APPENDICES
ATTACHMENTS
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be used,
disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 2 OF 49
1.0 PURPOSE
2.0 GENERAL
2.1 Scope
This Design Guide does not cover the following Power System Calculations:
e) Harmonics Calculation – to be covered in a future revision of this Design
Guide
f) Relay Coordination – to be covered in a separate Design Guide.
This design guide shall be used in conjunction with the applicable sections of the
latest edition of the following codes and standards. However, major clients usually
have their own standards and project requirements. These requirements are often
more stringent than the industry standards. Any special client requirements should
also be considered while conducting power system calculations.
2.2.1 ANSI/IEEE
IEEE 141 IEEE Recommended Practice for Electric Power Distribution for
Industrial Plants
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 3 OF 49
IEEE C37.06 AC High Voltage Circuit Breakers Rated on a Symmetrical
Current Basis – Preferred Ratings and Related Required
Capabilities
2.2.2 IEC
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 4 OF 49
IEC 60781: Application guide for calculation of short-circuit currents in
low-voltage radial systems
2.3 Format
The use of other equivalent programs is not covered in the scope of this
document.
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 5 OF 49
1.0 DESIGN PROCEDURES
Power System calculations shall establish that the complete electrical system will
operate under the specified design criteria, and retain stability under normal and
specified abnormal operating conditions.
Power System calculations are conducted for the overall electrical system design
at two stages i.e., (i) during the conceptual design (Preliminary Calculation) and
(ii) after detailed design (Confirmed Calculation).
The Preliminary Calculation is done based on estimated load data. Typical data
is used for the equipment where actual data is not available and can be obtained
from the ETAP library or from applicable standards. The configuration of the
electrical network has been determined and a one-line diagram prepared during
the basic design phase.
The Confirmed Calculation should be performed after all the vendor data for
motors, transformers, generators & switchgear is received and the project single
line diagram has been issued for construction. The Confirmed Calculation
should involve:
a) Performing definitive power system calculations
b) Calculations to confirm equipment sizing/rating
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 6 OF 49
c) System stability during normal, abnormal and transient operating
conditions.
d) Confirming that fault levels are within switchgear capabilities.
e) Finalizing transformer tap settings based on motor starting calculations.
f) Confirming that voltage levels & power flows are acceptable and meet
design criteria requirements.
5.0 CALCULATIONS
5.1.1 Purpose
The results should illustrate the effects of any of these changes on the overall
system prior to implementing the change.
The problem of analyzing the power flow (or “the load flow”) even in a modest
size system ultimately involves the determination of the bus voltages. Whereas
the electrical loads are known, they often represent a nonlinear function of the
applied voltages. In order to find the bus voltages, one has to resort to a cut-
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 7 OF 49
and-try iterative method. The computer is an effective tool for this method
because it can complete the set of calculations much faster and more accurately
than if done by hand.
The PowerStation Load Flow Analysis program calculates the bus voltages,
branch power factors, currents, and power flows throughout the entire electrical
system. The program allows for swing, voltage regulated, and unregulated
power sources with multiple utility and generator connections.
1.2.1 Objectives
The load flow calculations can also be used for practical engineering purposes,
such as verifying voltage drops in long cable lines and voltage level available on
the terminals of a remote load.
The following data is required to carry out load flow calculations in ETAP
PowerStation:
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 8 OF 49
b.) Cable and transmission line, length, and unit
c.) Transformer rated kV and kVA/MVA, tap, and LTC settings
d.) Impedance base kV and base kVA/MVA
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 9 OF 49
d) Equipment cable ID
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 10 OF 49
h) Update (for bus voltages and transformer LTCs using load flow
result)
The study case related data is entered into the Load Flow Study Case
Editor.
The PowerStation load flow program allows for three load flow calculation
methods selected from the Info Page of the Study Case Editor:
a) Newton-Raphson
b) Fast-Decoupled
c) Accelerated Gauss-Seidel.
5.1.5.1 Identify the base analytical cases to represent the different operating
modes of the system or plant. The operating modes should include
the system at a maximum operating load, as well as under light/no
load conditions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 11 OF 49
change made to engineering properties of an element in one
presentation gets automatically reflected in all other presentations.
b) The choice of various system configurations should take advantage
of the PowerStation Status Configuration feature that allows for each
configuration to be independent from the others. Therefore, the
status of elements (e.g., circuit breakers can have open or closed
status, loads and motors may be operating continuously,
intermittently, or be spare, etc.) can be set independently for each
configuration.
c) The primary application of Revision Data is to enable “What if”
calculations where one can readily vary the engineering data of the
system components and compare the results with the Base Data.
Another application of this feature is for assessing the future growth
of the system. Note that the Base Data must include all the
components, even those that will be added in the future (as such,
they would need to be flagged “Out of Service” in the Base Data).
5.1.5.3 Model the system in the PowerStation Edit mode and enter the input
data in the individual component editors.
A general rule of thumb for the preliminary load flow calculation is that all
you need to obtain in advance are the system voltages and power
transformer rating. When using typical US standard equipment the
remaining data may either be obtained from the PowerStation libraries or
entered as “typical data” readily available from the component editors.
Where equipment is non-US standard it is necessary to enter typical
data which should be readily available.
5.1.5.4 Select from the Study Case Editor, Info Page, one of the three
methods described in the “Calculation Methods” above to converge
the algorithm after checking that the network had been modeled
correctly.
5.1.5.5 Based on the project Design Criteria, select from the Study Case
Editor, Alert Page, the critical and marginal values for the Simulation
Alerts that are provided to notify the user of an abnormal loading
condition based on certain predetermined percent values.
5.1.5.6 Select from the Load Flow Toolbar the Display Options that in your
opinion are best suited for your presentation.
5.1.5.8 Depending on your selection from the Display Options screen, Results
Page, PowerStation will calculate:
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 12 OF 49
b) the magnitude of real and reactive power supplied by each source
(utility and onsite generators) and flowing through the branches,
i.e., transformers, feeders and buses, or
c) the apparent power flow, or
d) the current flow,
e) as well as percent or actual voltage levels and phase angles at
each bus.
Note that you can select from the Display Options screen, Results
Page, that the apparent power flow and current flow (but not real
power flow) be accompanied by PowerStation computing percent
power factor in each branch.
5.1.5.10 Run the "What if" calculations using a Revision Control mode where
you can readily vary the engineering data of the network’s components
and compare the results with the Base Data or other Revisions.
5.1.5.11 Review the results of the system load flow calculation to
check/determine:
a) The required continuous power ratings of generators, transformers,
feeders, buses, and circuit breakers.
b) The extent of loading of generators, transformers, and feeders
during the most demanding and emergency (abnormal) operating
conditions.
c) The requirement for load shedding facilities.
d) The need for power factor correction capacitors.
e) Conservative equipment specification parameters to minimize risk
of long-lead procurement, such as the power transformer and
generators’ rating and impedances, transformer LTC requirements,
switchgear nominal bus rating, etc.
5.1.5.12 Make corrective actions as necessary to bring the marginal and critical
values annunciated in the Alert Window within the parameters
allowable by the project design criteria (make sure to check the Auto
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 13 OF 49
Display box in the Alert Page of the Study Case Editor). See Section
below for Corrective Actions.
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 14 OF 49
1.2.5 Corrective Actions
5.1.6.4 Any changes must be checked to see their effect on other operating
conditions and clearly documented.
The following sample Load Flow Calculation is attached to this design guide:
a.) Attachment A, Sample Load Flow Calculation
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 15 OF 49
5.2 Short Circuit Calculation
1.2.7 Purpose
The purpose for short circuit calculations is primarily to ensure that system
components exposed to high fault currents are adequately rated. In a short
circuit calculation, fault levels are calculated throughout the system to confirm
that components will be able to withstand both electro-mechanical and thermal
effects of the maximum possible fault currents prior to clearing, and that the
interrupting devices can successfully interrupt these currents. This calculation
analyzes the effect of three-phase, line-to-ground, line-to-line and line-to-line-to-
ground faults on the electrical distribution system, as required, and computes the
maximum short circuit currents for comparison with the device short circuit
ratings. A three-phase short circuit is frequently the only fault considered since it
generally (but not in every instance) results in the maximum short circuit current.
Short circuit calculations should be conducted:
a) Before finalizing the design of a new electrical system
b) When major electrical additions occur to an existing system
c) Prior to ordering electrical equipment for the system
d) Whenever large motors or a large number of small motors are added to or
removed from the system.
e) When the system electrical source is modified.
The preliminary calculations shall be based upon maximum future plant electrical
equipment operating in order to determine:
a) Three-phase making duty for a fault at each bus bar.
b) Three-phase breaking duty for a fault at each bus bar.
c) Single-phase to ground fault on each bus bar under normal load, peak load,
and emergency system (peak load) conditions.
The preliminary calculations to determine maximum fault currents shall not take
into account the impedance of short lengths of cabling between equipment such
as generators, transformers, and switchgear.
For viable system design short-circuit levels must be within the short-circuit
rating of available switchgear. Values above the switchgear rating are
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 16 OF 49
unacceptable. Values close to ratings should be reviewed against assumptions
and tolerance margins built into the input data. Ideally, a 10% margin between
calculated and plant ratings should be kept but the amount of any margin should
be consistent with the uncertainty in the design at the time of calculation.
Calculations shall also be based upon the minimum anticipated plant electrical
equipment operating to determine the minimum short circuits levels likely to
occur at each bus bar. The results of the calculations shall be used during the
protective relay co-ordination calculation.
Some combined cycle plants have LCIs (Load Commutated Inverters) as starting
devices and manufacturers may specify a minimum system short circuit level for
satisfactory operation of their equipment. This is to ensure that the system is
robust enough not to be adversely impacted by the harmonics generated during
LCI operation. A short circuit calculation undertaken for this purpose should
calculate the minimum available short circuit level at the LCI power supply bus.
This is done by considering the smallest load that is required to be operational
prior to starting the LCI and using the maximum positive tolerances on
transformer impedances (for preliminary data).
It should be underscored here that the loads and tolerances required for
obtaining conservative results can be different for the same type of calculation
depending on the objective, as is true for the above cases.
The results of the short circuit calculation should be used to check/determine the
following:
a) MCC bus bracing Ratings
b) Switchgear bus bracing Ratings
c) Cable Ratings
d) Reactor Ratings
e) Is Limiter Requirements
f) Need for high impedance grounding of Generators and Transformers
g) Bus-duct Ratings
h) Transformer Impedances
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 17 OF 49
i) Protective device momentary & interrupting Ratings
The results of the short circuit calculation also provide information in order to co-
ordinate protective devices in the system. Two values are generally required for
protection design firstly the maximum value to determine effective selectivity
(discrimination) and secondly a minimum value to confirm effective protection
operation. When determining the minimum value a credible minimum plant
operating option should be selected and used in conjunction with positive
tolerances on impedance. Dependant upon the protection settings it is possible
that the thermal rating of some conductors may be determined by the minimum
fault level condition.
The Confirmed short circuit calculation is performed when the project single line
diagram is issued for construction and all relevant ‘As-built’ data is available for
vendor-supplied equipment like transformers, generators, MV motors, etc. At
this stage, impedance tolerances can be removed since actual values are
available. The Confirmed calculation should confirm that all the equipment
purchased is suitable for the required short circuit duties.
The following inputs are required to perform a short circuit calculation in ETAP:
5.2.1.1 Bus Data
a.) Nominal kV (when the prefault voltage option is set to use nominal
kV)
b.) %V and Angle (when the prefault voltage option is set to use bus
voltage)
c.) Type, such as MCC, switchgear, etc. and continuous and bracing
ratings
5.2.1.2 Branch Data
Branch data is entered into the Branch Editors, i.e. 3-Winding
Transformer, 2-Winding Transformer, Transmission Line, Cable,
Reactor, and Impedance Editors of ETAP.
a) Branch Z, R, X, or X/R values and units, tolerance and
temperature, if applicable
b) Cable and transmission line, length, and unit
c) Transformer rated kV and kVA/MVA
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 18 OF 49
e) Transformer winding connections, grounding types, and grounding
parameters
5.2.1.3 Utility/source data:
a) Nominal kV
b) %V and Angle
c) Maximum & minimum 3-phase short circuit values (MVAsc) and X/R
ratio. If a higher short circuit contribution is expected from the utility
in the future, that value should be used, depending on the objective
of the calculation.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 19 OF 49
e) X0 (Zero Sequence Impedance)
f) X2 (Negative Sequence Impedance)
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 20 OF 49
5.2.2.11 Cable Data for major equipment
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 21 OF 49
c) Prefault voltage
d) Report format
e) Machine X/R (machine X/R modeling method)
f) Faulted buses
g) Cable / OL heater (to include cable and overload heater elements)
Short circuit calculations for ANSI systems are performed based on IEEE C37
standards. In ANSI/IEEE short circuit calculations, an equivalent voltage source at
the fault location, which equals the prefault voltage at the location, replaces all
external voltage sources and machine internal voltage sources. All machines are
represented by their internal impedances. Line capacitances and static loads are
neglected. It is assumed that the fault is bolted and therefore, arc resistances are
not considered. System impedances are assumed to be balanced three-phase
and the method of symmetrical components is used for unbalanced fault
calculations.
a) ½ Cycle network
This is the network used to calculate momentary short circuit current levels for
the system under study. The ½ cycle network is also referred to as the
subtransient network because all rotating machines are represented by their
subtransient reactances. The closing & latching capabilities of HV circuit
breakers, interrupting capabilities of fuses & LV circuit breakers and switchgear
bus bracing ratings are compared with the calculated momentary short circuit
currents to confirm that the equipment is adequately rated.
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 22 OF 49
b) 1.5-4 Cycle network
This network is used to calculate interrupting short-circuit current levels for the
system under study and determine adequacy of HV circuit breaker interrupting
capabilities. In this network generators are represented by their subtransient
reactances whereas motors are represented by their transient reactances.
c) 30 Cycle network
This network is used to calculate the steady state short circuit currents that are
present 30 cycles after the fault. Induction machines, synchronous motors and
condensers are not considered in the 30-cycle fault calculation. Generators are
represented by their steady state reactances.
Care should be taken while specifying the pre-fault voltage for short circuit
calculations in ETAP. A number of options are available and the program
literature should be consulted and engineering judgment used when selecting an
option for the calculation at hand.
A calculation shall also be performed based upon the minimum anticipated plant
electrical equipment operating to determine the minimum short circuits levels
likely to occur at each bus.
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 23 OF 49
Short circuit calculations for an IEC system are based on IEC 60909 part 0. An
alternate standard: IEC 61363 Electrical installations of ships and mobile and
fixed offshore units —Part 1: Procedures for calculating short-circuit currents in
three-phase a.c. is also available. ETAP includes an option for calculation to the
IEC 61363 standard, which calculates a full waveform for the fault.
In IEC 60909 short circuit calculations, an equivalent voltage source at the fault
location replaces all voltage sources. A voltage factor c is applied to adjust the
value of the equivalent source for minimum and maximum current calculations
IEC 60909 calculations are not suitable for instances where there is a possibility
of a delayed current zero (i.e. no current zero in the first cycle of the fault
current). This delayed current zero can occur in instances where the sub
transient time constant for the connected generators is comparable with or
longer than the system time constant.
IEC 60909 uses the following definitions, which are relevant for the scope of this
document:
NOTE: IEC 60909 recommends three methods (METHOD A, B, C), for the
calculation of the peak short circuit current in meshed networks. However,
method 'C' is applied in low voltage and high voltage networks if it is
necessary to find a good approximation for 'i p' considering the viewpoints of
both safety and economy.
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 24 OF 49
ETAP calculates 'ip' to all the three methods. However, it is recommended
that method 'C' results should be used.
Note: IEC 60909 suggests that the decay of motor contribution should
only be considered if the motors are connected to the bus where fault is
being considered. For the motors connected 'far' from the fault, i.e. on a
different bus, the a. c. component of the contribution (from the motors)
remains constant (i.e. Ib = I"k) unless the contribution is higher than 5% of
the initial symmetrical short circuit current (I" k) without those motors.
However, it also suggests that as conservative approach, above condition of
5% should not be applied.
'ETAP' calculates 'Ib' in line with IEC 60909's requirements. It also calculates
'Ib' with no decay from the 'far' connected motors, which results in calculating
slightly higher values of 'I b'.
Note: The time tmin is the sum of the shortest possible operating time of
an instantaneous relay and the shortest opening time of a circuit breaker. It
does not take into account adjustable time delays of tripping devices.
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 25 OF 49
Especially for Low Voltage circuit breakers for which contact separation can
occur in less than 1/2 cycle the circuit breaker manufacturer should be consulted
with regard to rating. The circuit breaker’s rated short-circuit breaking capacity
shall be guaranteed at a voltage no less than the nominal system voltage at its
point of installation on the system, and at a power factor not greater than the
calculated power factor of the prospective short-circuit breaking current.
The following sample short circuit calculation cases are attached to this design
guide:
a) Attachment B, Sample Short Circuit Calculation (ANSI)
b) Attachment C, Sample Short Circuit Calculation (IEC)
1.2.12 Purpose
Large induction motors and industrial synchronous motors draw, typically, six or
seven times their full load current from their power supply under starting
conditions, which may last up to several seconds. One of the resulting effects of
this current surge is a voltage drop in the network which may disturb the normal
operation of other loads, dimming of lights, contactors dropping out and voltage-
sensitive equipment malfunctioning.
The purpose of motor starting calculations is to ensure that the voltage profile of
the electrical network remains within the specified limits and that the motor can
be accelerated to its rated speed.
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 26 OF 49
A motor starting calculation should consist of two stages:
The following minimum data is required to carry out voltage drop calculations in
ETAP PowerStation:
a) Motor rating (kW), power factor and efficiency values
1.2.14 Method
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 27 OF 49
b) The ratio of motor connected bus short-circuit kVA to motor-starting kVA
is eight or less
c) The driven load has high inertia
d) Restrictions exist on utility line voltage drop
The above criteria give general guidelines only. Special conditions may exist
such as starting a motor under load where high starting torque is needed which
would require a dynamic motor starting calculation even if none of the above
criteria were met.
If the Preliminary calculations are completed before motor details are available,
especially at the early stages of a project, typical torque versus speed and motor
starting current characteristics should be used. Confirmed calculations should
be carried out following receipt of actual (as-tested) equipment parameters.
In the case of existing systems a motor starting calculation may not always be
necessary. If for example a 55kW motor is being added to a motor control
center that already has, say, a 110kW motor of similar load characteristics,
which already starts and accelerates without problems, it is safe to assume that
the smaller motor will start and accelerate satisfactorily and that a calculation is
not necessary.
Motor starting calculations can be carried out by ETAP using two methods:
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 28 OF 49
Due to the difference in modeling motors, the static motor starting method may
be preferred for its relative simplicity when the effect on network voltage profile is
required. Alternatively, where there is concern about the acceleration time of the
motor or whether the motor can be successfully accelerated to full speed, then
the dynamic motor starting method should be the preferred option.
The following sample motor starting calculation is attached to this design guide:
a) Attachment –D, Sample Motor Starting Calculation
1.2.16 Purpose
Transient Stability calculations require all of the input data provided for a Load
Flow calculation plus the machine dynamic model data, load dynamic model
data, and any control units, such as exciter and governor data. Specifically, the
additional required data includes:
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 29 OF 49
c) Status
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 30 OF 49
5.4.2.6 Synchronous Motor Data
a) Model type (None, Equivalent, Transient, or Subtransient)
b) Machine type (Round-Rotor or Salient-Pole)
c) Xd”, Xd’, Xd, Xq, Xl, X/R, Tdo’ for Equivalent model
d) Xd”, Xd’ Xd, Xq’, Xq, Xl, X/R, Tdo’, for Transient model Round-Rotor
machine type
e) Xd”, Xd’ Xd, Xq”, Xq’, Xq, Xl, X/R, Tdo”, Tdo’, Tqo”, Tqo’ for Subtransient
model Round-Rotor machine type
f) Xd”, Xd’ Xd, Xq’ (=Xq), Xq, Xl, X/R, Tdo’ for Transient model Salient-
Pole machine type
g) Xd”, Xd’ Xd, Xq”, Xq’ (=Xq), Xq, Xl, X/R, Tdo”, Tdo’, Tqo for Subtransient
model Salient-Pole machine type
h) S100, S120, H and Damping
i) Exciter Type and all associated parameters or fixed excitation
j) H
k) Load model
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 31 OF 49
g) Rated Torque
h) Hammer Blow & Micro Switch Flags
i) Locked Rotor (LR), No Load (NL), Normal, & Rated Torque (Rated
T) Time Duration
j) Loading Category ID & %Loading
k) Equipment Cable Data
l) % Voltage Limit
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 32 OF 49
5.4.2.9 Static Load Data
a) Quantity
b) Status & Associated Demand Factor
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 33 OF 49
5.4.2.16 Charger Data
a) Status & Demand Factor
b) AC Ratings
The transient stability calculation determines the machine power angles and
speed deviations, system electrical frequency, real and reactive power flows of
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 34 OF 49
the machines, power flows of lines and transformers, and voltage levels of the
system buses. These conditions provide the indications for the system’s
stability.
During and after system disturbances the machines’ rotor angles will oscillate
which causes power flow oscillations in the system. If these oscillations are
severe it can destroy the electromechanical equilibrium and instability can occur.
The two machine equations used in stability calculations are:
a) Torque Equation:
P 2
T air Fr sin
8
where,
T = mechanical shaft toque
P = number of poles
air = air gap flux
Fr = rotor field MMF
= power (rotor) angle
The torque equation defines the relationship between mechanical shaft torque,
stator voltage, the excitation system, and rotor angle. Changes in any of these
will cause the rotor angle to readjust to a new position.
b) Swing Equation:
d 2 d
M 2
D Pmech Pelec
dt dt
where,
= power (rotor) angle
t = time
M = inertia constant
D = damping constant
Pmech = input mechanical power
Pelec = output electrical power
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 35 OF 49
The swing equation shows that the rotor angle is a function of balance between
the mechanical power and the electrical power. Any system change that breaks
this balance causes the rotor to undergo a transient and reach a new position via
oscillation. This oscillation is called the rotor swing.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 36 OF 49
that occur depending on system dynamic responses or relay settings can be
specified by entering a relay-controlled event. The location, sensor data, and
settings of the protective device are entered for these actions. Examples are a
current relay that trips a circuit breaker when the current exceeds a preset value
or a voltage relay that opens or closes a circuit breaker when compared to upper
or lower settings.
Stability calculations need only be performed on power systems with two or more
synchronous machines tied together electrically (e.g. two or more AC generators
or a large synchronous motor powered by a large AC generator(s)).
The following cases should be included in the calculation. The system should be
at maximum loading.
a) Short-circuits or faults at major buses
b) Fault removal
c) Loss of an in-plant generator
d) Loss of a utility tie
e) Starting the largest motor on each bus
f) Impact loading (motors and static loads)
g) Sudden large step change of load or generation
The output report of the transient stability calculation is presented in tables, one-
lines, and plots. It should include the following information:
a) Rotor angles, torques and speeds of synchronous machines
b) Real and reactive power flow throughout the system
c) Voltage and phase angles at all buses
d) System frequency
e) Torques and slips of induction machines
f) Maximum tolerable fault clearance time to maintain system frequency
g) Load limitation for each calculation condition to maintain system stability
and whether load shedding is required to maintain system stability
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 37 OF 49
if the swing curves come back into step after the initial disturbance, or if they
diverge, indicating instability for the particular transient under consideration
The results should establish if the proposed system is stable and if the system
motor starting capability and the voltage regulation caused by motor starting is
adequate. The initial calculations may indicate that starting certain motors cause
stability problems for the remainder of the system, which may require changing
of the parameters or protection of the motors and carrying out further
calculations.
The cases should be run for a sufficient length of time to determine whether or
not stability is maintained. The criteria used in deciding system stability should
be stated in the report.
Care must be taken while determining the inertia and damping factor (in the
absence of actual data supplied by the Vendor) as these have significant effect
on the results.
All machines and control devices should be modeled using actual data supplied
by the manufacturer. Where manufacturer's models are not compatible with
standard models available in ETAP, OTI can produce a custom model for the
specific device.
The following sample transient stability calculation is attached to this design guide:
a) Attachment E, Sample Transient Stability Calculation
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 38 OF 49
APPENDIX – A
If a network is fed from a utility supply in which only the initial symmetrical short
circuit apparent power (S"k in MVA) is known, then it should be substituted in the
field for short circuit MVA rating of supply in ETAP. If the initial symmetrical
short-circuit current (I"k in KA) at the feeder connection in known, then the
equivalent short circuit apparent power (S"k = Ö3 Un I"k) should be calculated
and entered in ETAP. 'Un' in the equation for S"k being the nominal system
voltage (in kV) at the supply feeder connection point.
X/R Ratio
In case of high voltage feeders with nominal voltages above 35 kV fed by
overhead lines, the equivalent impedance 'Z' may be considered as reactance
only.
For example Z = 0 + j X
In other cases, if no accurate value is known for 'R' of the utility feeders, then
use X/R = 10, where X = 0. 995Z.
2.0 TRANSFORMERS
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 39 OF 49
TABLE 1
For Power station generator transformers with or without tap changers, the
following values (as given in IEC 909-2) may be used:
Where 'SrT' is the rated power in MVA and 'ukr' is the rated short circuit voltage
(impedance).
Tolerance on impedance for two winding transformers is +15% per IEC 76.
These values are used for the preliminary calculation. ETAP uses negative
Impedance Tolerance values for short circuit calculation. Use the actual (tested)
values for Confirmed calculation.
For short circuit calculations, the tap changers of the transformers are assumed
to be in main position per IEC 909.
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 40 OF 49
2.3 Transformer X/R Ratio
The X/R ratio generally increases with transformer size. For large transformers,
the impedance may be assumed to consist only of reactance. Actual values
supplied by the manufacturers should be used.
The zero sequence short circuit impedance's Z(0) = R(0) + j X(0) of transformers
should be obtained from the manufacturers.
Typically, the ratio of X(0)/X(1) for two and three winding network transformers
(where X(0) is zero sequence reactance and X (1) is positive sequence
reactance) is as follows:
Note: Factor 'K' is used to calculate the impedance of the machine (Zm) using
the equation:
X "
Z m d
All machine reactances to be the saturated (full load) values to give conservative
results.
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 41 OF 49
For short circuit calculation purposes, the synchronous motors and synchronous
compensators are treated in the same way as synchronous generators.
For short circuit calculations, the initial symmetrical short circuit current (I" k)
changes in a few seconds to the steady state short circuit current (I k) with Ik <
I"k. The decay depends upon the method of excitation and voltage regulation
and to a high degree on the saturation and highest possible excitation voltage.
Therefore, calculation of Ik is less accurate than that of initial symmetrical current
'I"k'.
In order to have a sufficient estimate of steady state short circuit current, correct
excitation method from the following list should be selected along with the
saturated direct axis reactance (xd (sat)) in % (which is reciprocal of the short
circuit ratio) of the generator.
NOTE: Maximum excitation voltage levels mentioned in the above list are
at rated load and power factor for the generators.
At very initial stage of the calculation, when the actual type of excitation system
is not known, the option (e) above list could be selected to give conservative
values of Ik for a given xd(sat).
Typical values of xdsat lie between 120% and 220% for turbine generators and
between 60% and 200 % for salient pole machines.
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 42 OF 49
The value Ik is inversely proportional to the saturated reactance of xd(sat).
In the absence of actual data for induction machines, the following table, (which
gives recommended values extracted from IEC 909's in section 11.5.3.5) should
be used for the parameters required to carry out short circuit calculation.
£1 - 2.38 0.922
Where 'm' factor is the rated active power of motors (MW) per pair of poles.
(pu)
1
Z " m
LR C
Induction machines for a given bus bar. (e.g. 5 x 37kW 2 pole motors and 5 x 75
kW 4 pole motors can be with same 'm' factor (rated active power (MW) per pair
of poles) can be "lumped " together represented as 560 kW motor having same
characteristics).
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 43 OF 49
For high voltage motors, actual locked rotor current should be used. Typical
values in ETAP's library data should be used in the absence of actual value
suggested by the manufacturer.
Low voltage motors are usually connected to bus bar by cables with different
lengths and cross-sections. For simplification of the calculation of short-circuits
fault currents, as recommended by IEC909 (section 13.2.1), for the lumped
motors including their connection cables, following may be used:
For medium voltage motors, as per IEC 909-II (section 2. 6), the ratio of I LR/Ir =
5.5 may be used.
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 44 OF 49
APPENDIX – B
If a power system is fed from a utility supply in which only the symmetrical short
circuit current (ISC in kA) at the feeder connection in known, then the equivalent
short circuit power (MVASC = Ö3 V ISC) should be calculated and entered in
ETAP. 'V' in this equation is the nominal system voltage (in kV) at the supply
feeder connection point.
X/R Ratio
For example Z = 0 + j X
In other cases, if no accurate value is known for 'R' of the utility feeders, then
use X/R = 15, where X = 0.9375*Z.
2.0 TRANSFORMERS
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 45 OF 49
TABLE 1
Table 2 gives typical transformer X/R ratios per American National Standard
C57.12.10.
TABLE 2
RATING X/R
MVA < 1 5.790
1 < MVA < 2 7.098
2 < MVA < 3 10.67
3 < MVA < 4 11.41
4 < MVA < 5 12.14
5 < MVA < 6 12.85
6 < MVA < 7 13.55
7 < MVA < 8 14.23
8 < MVA < 10 15.50
10 < MVA < 20 18.60
20 < MVA < 30 23.70
30 < MVA < 40 27.30
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 46 OF 49
RATING X/R
40 < MVA < 50 29.50
50 < MVA < 100 34.10
100 < MVA < 200 42.00
200 < MVA < 1000 50.00
TABLE 3
For short circuit calculations, the tap changers of the transformers are assumed
to be in their rated voltage position.
The zero sequence short circuit impedance Z(0) = R(0) + j X(0) of transformers
should be obtained from the manufacturer. If not available use the same value
as the positive sequence reactance.
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 47 OF 49
TABLE 4
Synchronous motors
Typical values in ETAP's library should be used in the absence of actual values
suggested by the manufacturer.
For short circuit calculations, the initial symmetrical short circuit current (I" SC)
changes in a few seconds to the steady state short circuit current (I SC) with ISC <
I"SC. The decay depends upon the method of excitation and voltage regulation
and to a high degree on the saturation and highest possible excitation voltage.
Therefore, calculation of ISC is less accurate than that of initial symmetrical
current I"SC.
Typical values of Xdsat lie between 120% and 220% for turbine generators and
between 60% and 200 % for salient pole machines.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 48 OF 49
Values of sub-transient reactance (X d") and transient reactance (X d') should be
obtained from the manufacturer.
4.1 Typical values in ETAP's library should be used in the absence of actual value
suggested by the manufacturer.
Induction machines for a given bus (e.g. 5 x 50hp 2 pole motors and 5 x 100 hp
4 pole motors) can be "lumped " together and represented as one 750 hp motor
having the same characteristics.
Electronic documents, once printed, are uncontrolled and may become outdated.
Refer to the electronic documents in BecRef for current revisions.
Bechtel Confidential
© Bechtel Corporation 2003. Contains confidential and/or proprietary information to Bechtel and its affiliated companies which shall not be
used, disclosed or reproduced in any format by any non-Bechtel party without Bechtel's prior written permission. All rights reserved.
3DG-E210-00001, REV. 000 PAGE 49 OF 49