BOQ SUMMARY

Project Name: BGH WH Chavuan_3F-4F ramp beam 1

Element :  Beam

No. Material Unit Quantity Rate $ Cost $


1 Concrete C20 (cum) 0.59 10500.00 6195
Sub Total 0.59 6,195

2 Rebar #10 (Fy420) (kg) 63.85 60.00 3831


3 Rebar #16 (Fy420) (kg) 104.74 60.00 6284
Sub Total 168.59 10,115

4 Shuttering (sqm) 4.89 600.00 2934


Sub Total 2,934

Grand Total 19,244

Design Metrics
1 Consumption : Reinforcement/Concrete ratio = 285.75 kg/cum
2 Consumption : Reinforcement/Planarea = 56.20 kg/sqm
3 Consumption : Concrete/Planarea = 0.20 cum/sqm
4 Concrete % C20 = 100.00 % 
5 Shuttering  = 8.29 sqm/cum