BOQ SUMMARY

Project Name: BGH WH Chavuan_4F Beam

Element :  Beam

No. Material Unit Quantity Rate $ Cost $


1 Concrete C20 (cum) 46.34 10500.00 486570
Sub Total 46.34 4,86,570

2 Rebar #10 (Fy420) (kg) 2473.22 60.00 148393


3 Rebar #13 (Fy420) (kg) 662.73 60.00 39764
4 Rebar #16 (Fy420) (kg) 3263.51 60.00 195811
5 Rebar #19 (Fy420) (kg) 2149.93 60.00 128996
6 Rebar #22 (Fy420) (kg) 2414.03 60.00 144842
Sub Total 10963.42 6,57,805

7 Shuttering (sqm) 342.12 600.00 205272


Sub Total 2,05,272

Grand Total 13,49,647

Design Metrics
1 Consumption : Reinforcement/Concrete ratio = 236.59 kg/cum
2 Consumption : Reinforcement/Planarea = 19.13 kg/sqm
3 Consumption : Concrete/Planarea = 0.08 cum/sqm
4 Concrete % C20 = 100.00 % 
5 Shuttering  = 7.38 sqm/cum