Owner’s Engineer
Project Title
Contractors
Replaces Derived from Project Document Code
- - JAW/00/D/A-----EP60/EI/561
Responsible dept. Created by Checked by Approved by Format
EM Satria P. Agustiono B.K. Teuku Akbar A4
Originator Document Type Document Status
Method Statement For Construction
GE POWER Title, Subtitle Originator Document No.
Grid Solutions 500kV GIS Cibatu Baru 2 / Sukatani & Cilamaya PI038-COM-500-SHV-6561-ER-S2280
Substation Method of Work GIS CB Installation Rev. Date Lang. Sheet
Indonesia
1 10 Apr 2020 En 1 of 16
CLASS II – Non-Critical
© COPYRIGHT 2018 General Electric Company (USA)
All rights reserved. The information herein is Proprietary and Technically Exclusive content that is solely owned by General Electric Company and/or
its affiliates. Thus, it is being provided with the explicit expectation of restricted and privileged use. All persons or legal entities receiving this
information shall be deemed by the act of its receipt have contractually agreed to make no duplications, reproductions of any nature by any means,
modifications, disclosures, or use any portion of this material; except as is expressly authorized in writing by the General Electric Company, and/or its
legitimate affiliates.
Project Name: Doc. Name: Rev. Date Lang. Sheet
JAWA-1 COMBINED 500kV GIS Cibatu Baru 2 / Sukatani & 1 10 April 2020 En 2 of 16
CYCLE Cilamaya Method of Work GIS CB
GAS TURBINE Installation
POWER PLANT Doc. Number:
(1760MW) JAW/00/D/A-----EP60/EI/561
CONTENTS
GENERAL ............................................................................................................................................................................................... 5
SCOPE OF WORK ............................................................................................................................................................................... 5
DEFINITION AND ABBREVIATIONS ............................................................................................................................................. 5
RESOURCE ............................................................................................................................................................................................ 5
4.1 Equipment & Tools ............................................................................................................................................................................ 5
4.2 Materials................................................................................................................................................................................................ 5
4.3 Personals ............................................................................................................................................................................................... 6
PERSONAL PROTECTIVE EQUIPMENT (PPE) ........................................................................................................................... 6
SUPPORTING DOCUMENT.............................................................................................................................................................. 6
WORKING METHOD AND SEQUENCE ....................................................................................................................................... 7
7.1 INSPECTION OF CIVIL WORKS ...................................................................................................................................................... 7
7.2 SAFETY INSTRUCTIONS ................................................................................................................................................................... 8
Main risks detected....................................................................................................................................................................... 8
Secondary risks .............................................................................................................................................................................. 9
7.3 IMPLEMENTATION OF THE WORKS ............................................................................................................................................ 9
Installation and preparation ..................................................................................................................................................... 9
Conditions of starting ............................................................................................................................................................... 10
7.4 INSTALLATION OF CIRCUIT-BREAKERS ................................................................................................................................. 10
Installation of the first pole circuit-breaker ..................................................................................................................... 10
INSPECTION AND TEST................................................................................................................................................................. 15
RISK ASSESSEMENT (RA) ............................................................................................................................................................. 15
Project Name: Doc. Name: Rev. Date Lang. Sheet
JAWA-1 COMBINED 500kV GIS Cibatu Baru 2 / Sukatani & 1 10 April 2020 En 3 of 16
CYCLE Cilamaya Method of Work GIS CB
GAS TURBINE Installation
POWER PLANT Doc. Number:
(1760MW) JAW/00/D/A-----EP60/EI/561
REVISION SUMMARY
GENERAL
SCOPE OF WORK
This work procedure covers general requirement for GIS Installation Work in Jawa Satu Power
Combined Cycle Power Plant 1 x 1760 MW specifically for 500kV Gas Insulated Substation model
T155-2 for Project site Cibatu Baru 2 / Sukatani & Cilamaya. GIS CB in Cibatu is consist of 30 units in
4 diameters and GIS CB in Cilamaya consist of 18 units in 2 diameters.
RESOURCE
4.2 Materials
500kV GIS Cibatu 500kV GIS Cilamaya
GIS CB: 30 unit GIS CB: 18 unit
Project Name: Doc. Name: Rev. Date Lang. Sheet
JAWA-1 COMBINED 500kV GIS Cibatu Baru 2 / Sukatani & 1 10 April 2020 En 6 of 16
CYCLE Cilamaya Method of Work GIS CB
GAS TURBINE Installation
POWER PLANT Doc. Number:
(1760MW) JAW/00/D/A-----EP60/EI/561
4.3 Personals
SUPPORTING DOCUMENT
Reference Document
JAW/00/D/A-----EP60/ES/200 R0 500kV GIS CIBATU BARU 2 / SUKATANI SUBSTATION TECHNICAL
SPECIFICATIONS OUTDOOR GIS
JAW/00/D/A-----EP60/EA/202 R0 500kV GIS CIBATU BARU 2 / SUKATANI SUBSTATION LAYOUT & SECTION
GIS
S3010 JAW/00/D/A-----EP/SD/203 RC 500kV GIS CIBATU BARU 2 / SUKATANI SUBSTATION SINGLE LINE
DIAGRAM GIS
JAW/00/D/A-----EP60/CG/204 500kV GIS CIBATU BARU 2 / SUKATANI SUBSTATION CIVIL WORK
GUIDE/LOAD & FOUNDATION DETAILS
JAW/00/D/A-----EN/ES/700 R0 500kV GIS CILAMAYA SUBSTATION TECHNICAL SPECIFICATIONS OUTDOOR
GIS
JAW/00/D/A-----EN/EA/702 R0 500kV GIS CILAMAYA SUBSTATION LAYOUT & SECTION GIS
JAW/00/D/A-----EN/SD/703 RC 500kV GIS CILAMAYA SUBSTATION SINGLE LINE DIAGRAM GIS
JAW/00/D/A-----EN/CG/704 500kV GIS CILAMAYA SUBSTATION CIVIL WORK GUIDE/LOAD & FOUNDATION
DETAILS
Project Name: Doc. Name: Rev. Date Lang. Sheet
JAWA-1 COMBINED 500kV GIS Cibatu Baru 2 / Sukatani & 1 10 April 2020 En 7 of 16
CYCLE Cilamaya Method of Work GIS CB
GAS TURBINE Installation
POWER PLANT Doc. Number:
(1760MW) JAW/00/D/A-----EP60/EI/561
General tolerance value is referring to CIVIL WORK GUIDE DRAWING on section LOAD &
FOUNDATION DETAILS - JAW/00/D/A-----EP60/CG/204 for Cibatu and JAW/00/D/A-----EN/CG/704
for Cilamaya in page 1 .
a) Unless specified, all dimensions are in millimeters.
b) The difference between the actual level and the theoretical level of the outdoor foundation must
not exceed +/- 20mm
Project Name: Doc. Name: Rev. Date Lang. Sheet
JAWA-1 COMBINED 500kV GIS Cibatu Baru 2 / Sukatani & 1 10 April 2020 En 8 of 16
CYCLE Cilamaya Method of Work GIS CB
GAS TURBINE Installation
POWER PLANT Doc. Number:
(1760MW) JAW/00/D/A-----EP60/EI/561
Source of danger
Risks Compulsory protective means
Fall of tools,
Safety helmet must be
Access to an area of parts
worn on site and substation
gas- insulated Shock with the
in service
substation head
Secondary risks
Conditions of starting
The conditions required for the implementation and realization of the site works shall
conform with to SITE CONDITIONS PRIOR TO START SITE ACTIVITY document leaflet
FAQ 011 which will be available at the work site during inspection
A certain number of dangerous works are prohibited to isolated workers and require
the presence of a supervisor:
o Site works or work in height with:
Use of belt or safety shoulder belt
Maneuvering of vehicles, apparatuses and site works equipment
Maneuvering of lifting equipment
Works which require the use of a hoist.
Marking of axes on the GIS foundation is referring to civil work guide drawing drawings
JAW/00/D/A-----EP60/CG/204 for Cibatu and JAW/00/D/A-----EN/CG/704 for Cilamaya
in page 3.
Fix the metallic structure to the ground with bolts M16 according to the indications
mentioned in the civil works guide drawing JAW/00/D/A-----EP60/CG/204 for Cibatu
and JAW/00/D/A-----EN/CG/704 for Cilamaya in page 3 and 6 with bolts installation
figure as below. The bolt will be tightening after all CB are connected. Torque value for
bolt tightening referring to below bolt torque table.
Project Name: Doc. Name: Rev. Date Lang. Sheet
JAWA-1 COMBINED 500kV GIS Cibatu Baru 2 / Sukatani & 1 10 April 2020 En 12 of 16
CYCLE Cilamaya Method of Work GIS CB
GAS TURBINE Installation
POWER PLANT Doc. Number:
(1760MW) JAW/00/D/A-----EP60/EI/561
Unpacking
Move CB packing unit from storage area to near installation location
They must also comply with all handling rules indicated in:
-- Box labels (pictograms: center of gravity, sling handles, stacking rules, etc.).
-- Equipment assembly instructions.
Unpack the equipment on the place of installation, on a firm and level base.
To open the boxes, use a nail-remover.
Remove the plastic film from the units.
Ensure N2 positive pressure inside circuit breaker compartment via filling port.
Take off and dispose of the fixing plates and bolts as these will not be needed.
Handling and lifting of the equipment are carried out by means of mobile crane with
minimum capacity of 5 tons SWL with appropriate lifting plan with consideration of the
weight load to be lift, working range and safe working load. Lifting plan will be provided as
attachment to PTW application.
Use 2 round sling or protected steel cables with hooks at each end with 3 tons SWL or
above.
Installing
Following sequence of installation work are applicable for the rest of Circuit-Breakers
with installation order from each single phase to complete phase of 3 unit in one set or
bay. The installation work continues with other remaining sets for the whole substation
with following breakdown.
Project Name: Doc. Name: Rev. Date Lang. Sheet
JAWA-1 COMBINED 500kV GIS Cibatu Baru 2 / Sukatani & 1 10 April 2020 En 15 of 16
CYCLE Cilamaya Method of Work GIS CB
GAS TURBINE Installation
POWER PLANT Doc. Number:
(1760MW) JAW/00/D/A-----EP60/EI/561
Risk Assessor
Construction
EHS Department
Management