The West Bengal Power Development Corporation Limited

[Ph. – III, (1x660 MW, U#5) SGPROJ03]


MINUTES OF WEEKLY PROJECT REVIEW MEETING (WPRM- 88) – at SgTPP on 08.04.2023.

U #5 BOILER LIT-UP TARGET DATE: 28.01.2024.


Sl. Area Resolution on 01.04.23 BHEL Reply 07.04.2023
No.
1. Safety 1. Proper support in track hopper #1 to arrest any material Regular vigilance to be taken for following Safety
Aspect work stated in Twin tippler working zone. Continuous points:
supervision required by BHEL and WBPDCL.
2. In boiler working area two layers of safety net have to be 1 Proper support in track hopper #1 to arrest any
fixed immediately. material work stated in Twin tippler working zone.
3. In boiler cavity area man movement must be restricted. Continuous supervision required by BHEL and
4. All scaffolding should be green tagged other than any job WBPDCL
will be permitted. 2 In boiler working area two layers of safety net have to
5. Except chimney area further improvement of illumination be fixed immediately. Continuous process same are
level is required. Illumination level must be increased being fixed on regular basis and as suggested by
immediately specially at Boiler & ESP area by PCP. same WBPDCL.
is being complied on regular basis. 3 In boiler cavity area man movement must be
6. 100% safety PPE not given to workers(Mainly M/s PCP). restricted.
WBPDCL requested to provide PPE to all. 4 All scaffolding should be green tagged other than any
7. A joint visit already done regarding safety net in Tippler, job will be permitted
TP and Conv. erection site. WBPDCL requested BHEL to 5 Except chimney area further improvement of
provide sufficient safety net to the above area at the illumination level is required. Illumination level must
earliest. be increased immediately specially at Boiler & ESP
8. Rod welded ladder will not be allowed for ladder. Partial area by PCP.
work done and action taken report shall be submitted by 6 100% safety PPE not given to workers (Mainly M/s
05.04.2023. PCP). WBPDCL requested to provide PPE to all.
9. Proper walk way boiler to pent house construction should 7 A joint visit already done regarding safety net in
be started by 31.03.23. Work under progress. Tippler, TP and Conv. erection site. WBPDCL
10. BHEL assure that PCC for all 11KV substation foundation requested BHEL to provide sufficient safety net to the
base of construction power shall be done sequentially above area at the earliest.
without affecting construction works from April’23. -----ALL ABOVE POINTS ARE NOTED AND BEING
FOLLOWED.
8 Rod welded ladder will not be allowed for ladder.
Boiler Area marked ladder are modified with hand
railing. Issue closed.
9 Proper walk way in boiler to pent house (roof area )
completed . issue closed.
10 BHEL assure that PCC for all 11KV substation
foundation base of construction power shall be done
sequentially without affecting construction works
from April’23.
SAFETY COMMITTEE RECOMMENDATIONS:
11. All unsafe area is to be hard barricaded properly and
cautionary board should be displayed in working
area.
12. Fact finding committee found low illumination in
boiler area. BHEL said that after recommendation
they fixed new lights. GM’s sir advised that a joint
visit with WBPDCL, BHEL and PCP will be done
regarding illumination level improvement on
10.04.2023.
13. Fact finding committee found very bad house kipping
in different area. BHEL assured that excess materials
from drain area cleaning will be start from 10.04.23
and cleaning already started at boiler cavity area.
14. Regarding the safety nets in boiler cavity area plant
GM advice to explore in boiler cavity area.
15. As advice by fact finding committee BHEL already
cleaned the plastic materials in working area and
assured that it will be continued in regular basis.
16. Fact finding committee found various load
equipments are in hanging condition for a long
period. BHEL said that a new gang started fixing the

Page 1 of 7
[Ph. – III,(1x660 MW, U#5) SGPROJ03]

MINUTES OF WEEKLY PROJECT REVIEW MEETING (WPRM- 88) – at SgTPP on 08.04.2023.

headers and all headers will fixed by end of April23


and permanent support is to be incorporated for
ceiling.
17. During visit at different area gratings found without
proper welding. BHEL assured that those will be
solved by 10.04.23.
18. During the visit committee found that lifting work
was going on without barricading and safety
personnel. Plant GMs instructed to maintain strictly.
19. 100% green/red tagging will be completed by
21.04.23.
20. 100% guide rope will be used for anchoring the fall
arrestor.
21. Use of all types of mobile phone in height job and
critical job area is strictly restricted. BHEL requested
to strictly follow the rules; after caution advise to
panelized the responsible person and WBPDCL
advice BHEL to implantation of caution poster of
penalization for use of mobile phone.
DIR.(PROJECT) RECOMMANDATION :

22. Area wise allocation of safety stewards and


responsibility to be done immediately and it should
be displayed in their allocated zone. A joint safety
team WBPDCL and BHEL along with safety steward
will visit site regularly. A weekly safety meet will be
arranged with BHEL and WBPDCL. In this meeting
next week schedule will be fixed. All the above will
be implemented within end of April23.
23. In existing safety what’s app group WBPDCL official
should be includes.
24. Total list of safety officers/stewards and their phone
number and their responsible zone will be submitted
to WBPDCL immediately.

MECHANICAL- BOILER & AUX.


2. Manp Area Erectable Avg. Additional Erectable
BHEL Avg. Additional BHEL reply BHEL reply B
ower available workers Workers available
reply workers Workers BHEL reply
(MT) working reqd. (No.) working reqd.
for (No.) (No.) (No.)
boiler PG 34 150 17 17
and
PG 35 30 35 35
ESP
erecti PG 36 2850 128 128 04 nos. G.P.
on 10.02.23. in process.
PG 48/39 60 32 32

Separat 20 14 15
or &
downwa
rd
89 30 15 nos. G.P.
1st pass 800 81 40 10 GP U/P in process.
2nd pass 200 53 30 10 GP U/P 76 20 By 15th of
Apr’23
30 APH area
Mill/ 80 30 05
Work on hold
Rotary Since Mar’23
ESP 1500 156 156 ESP I/L NO
Front avl.,
ESP O/L par.
Front. Avl.
Due to Chi-
mney work.

Page 2 of 7
The West Bengal Power Development Corporation Limited

[Ph. – III, (1x660 MW, U#5) SGPROJ03]


MINUTES OF WEEKLY PROJECT REVIEW MEETING (WPRM- 88) – at SgTPP on 08.04.2023.

U #5 BOILER LIT-UP TARGET DATE: 28.01.2024.


MANPOWER: Now avg. 546 nos. present. MANPOWER: Now avg. 578 nos. present.
Job target in next week: 1. Bunker Column LHS: Feeder floor main beam erection
1. Bunker Column LHS: Feeder floor main beam erection completed by PCP. KEPL Structural Welding of feeder
completed. Welding under progress, expected hand over to floor under progress, expected hand over to civil casting
civil casting by 03.04.2023. (Initial date: 30.01.23). by 10.04.2023. (Initial date: 30.01.23).
2. Clearance for feeder floor casting will be available by 2. Clearance for feeder floor casting will be available by
05.04.2023. (Initial date: 20.01.23). 10.04.2023. (Initial date: 20.01.23).
3. New 250T crane will reach at site by 15.04.23 (Initial date: 3. New 250T crane will reach at site by 10.04.23 (Initial
Feb’23 from Haldia. PCP will share the un-priced PO & date: Feb’23 from Haldia. PCP shared the un-priced PO
contact no. of the co-ordinator for 250 MT crane to & contact no. of the co-ordinator for 250 MT crane to
WBPDCL. WBPDCL.
4. SR capacity will be increased from 120 nos. to 150 nos on 4. SR capacity now increased from 120 nos. to 150 nos /per
daily basis. daily basis.
5. Sequential plan for civil and erection plan of duct, AHP, CHP 5. Sequential plan for civil and erection plan of duct, AHP,
etc. between boiler and Chimney inlet need to be submit. CHP etc. between boiler and Chimney inlet need to be
6. Platen SH joints will be started from April’23 1 st week. submit.
7. Additional 10 no. fitter gangs & additional 15 nos. 6. Platen SH joints will be started from April’23 1 st week.
attachment welders will be available by 10.04.23. Total 13 7. By 15.04.23- IBR welders: additional 07 nos. will be
nos. IBR welder will be available by 10.04.23. increased. (Total no. Will be -15).
8. Manpower increased to 546 as on date. Fitter gang: Additional 06 nos. will join (total no will be
9. WBPDCL advised to recruit a project management engineer 18 nos.) At preset total fitter gang is 12 nos.
in M/s PCP for utilization of manpower and material and for 8. Manpower increased to 578 as on date.
proper planning. 9. Experienced planning engineer already available in PCP.
10. BHEL assured that work at ESP outlet side duct will start Organisation chart may be referred.
from 01.06.23. 10. BHEL assured that work at ESP outlet side duct will start
11. BHEL stated that work at FGD will start only after from 01.06.23 after chimney shell casting.
completion of chimney shell work due to safety reasons. 11. BHEL stated that work at FGD will start only after
completion of chimney shell casting work due to safety
reasons.
12. Gang engaged. Complete shifting to permanent hanger
by May end23 for present headers as erected.
13. Not understood...
14. Day wise micro plan not possible. Monthly & weekly
plan already submitted. day wise activity regularly
discussed in daily site meeting.
15. Day wise micro plan not possible. Monthly & weekly
plan already submitted. day wise activity regularly
discussed in daily site meeting.
16. Day wise micro plan not possible. Monthly & weekly
plan already submitted. day wise activity regularly
discussed in daily site meeting.
17. Given in DPR.
18. It was already discussed several times that After 350T
crane work completion in LHS side as expected by July
23
19. BHEL assured that no additional 75T crane mobilisation
envisaged and not required. 3 nos already available. Due
to this no work will be hampered.
20. Clearance date of bunker column erection? -Upto third
tier erected. Further erection after erection of bunker
shell
21. Clearance date of civl work RHS feeder floor? -RHS
feeder floor handed over to KEPL for further civil work .

Page 3 of 7
[Ph. – III,(1x660 MW, U#5) SGPROJ03]

MINUTES OF WEEKLY PROJECT REVIEW MEETING (WPRM- 88) – at SgTPP on 08.04.2023.

3. Add. T&P Av. Add. BHEL reply


T&P for Reqd. T&P Av. Add. BHEL reply
pr. Reqd.
Welding m/c 98 0 Welding m/c for 98 0
Parts
for boiler boiler
erectio
n. Winch m/c- 08 0 Winch m/c- pr. 08 0
Requir pr. Parts Parts
ement Winch m/c- 02 0 Winch m/c- PG- 02 0
&availa PG-36 36
bility. PMI 1 0 PMI 1 0
Hardness tester 1 0 Portable machine
Hardness 1 0 Portable machine available. UCI
tester available. UCI machine machine reqd.
reqd. Reached at site by
20.04.23.
Boroscope 1 0 Boroscope 1 0
Ind. HEATING 4 04 nos reached at
Ind. HeatING 4 Induction heating MACHINE site middle of
MACHINE machine av. Checking Dewatering 2 0 May23.
Dewatering 2 0 u/p. pump
pump Comp. 1 1
Comp. 1 1 paut M/c Agency finalization by
10.04.23.

4. Total tube joints completed as on Date (30.03.2023): Total tube joints completed as on Date (07.04.2023): 4840
3784 nos. (Excluding defective). no.
Per day Joint target 200 nos. RT will be done consequently
done.
5 CRITICAL PIPING CRITICAL PIPING
1. 250KVA P91 set available by 2nd week of April23. 1. 250KVA P91 set available by 15.05.23.
2. 02 nos. induction heating m/c available, PCP will supply another 02 nos. 2. 02 nos.induction heating m/c available, PCP will supply
by April 2nd week, another 02 nos. will be available by May’23. BHEL will another 02 nos. by April 2nd week, another 02 nos. will
provide another 02 nos. by April’23. be available by May’23. BHEL will provide another 02
3. Job started from 27.03.23. (Initial date: 18.03.23). Separate gang will be nos. by April’23.
arranged based on front and material availability. 3. Job started from 27.03.23. (Initial date: 18.03.23).
4. UT/RT will be arranged in time as per FQP. Separate gang will be arranged based on front and
5. All erection drawings need to be finalized. Issue to be taken up with BHEL material availability.
Trichy and WBPDCL /HQ/DCPL. 4. UT/RT will be arranged in time as per FQP. issue closed.
6.Critical piping job already started. Additional 10 nos. manpower 5. All erection drawings need to be finalized. Issue to be
mobilization by 07.04.23. Work will resume from 10.04.23. taken up with BHEL Trichy and WBPDCL /HQ/DCPL.
6. Critical piping job already started. Additional 10 nos.
manpower mobilization by 10.04.23. Work will resume
from 10.04.23.
7. Critical piping additional 02 nos. gang will joined by
15.04.23. 01 no. engineer already joined.
MECHANICAL- TG & AUX
6 TG- 1. Handover of Power House from Civil to Mechanical: ALL POINTS RELATED TO CIVIL & STRL . TAKEN UP IN
Mechanical Further floor 17mtr Handed over & 0 mtr in progress. CIVIL & STRL POINTS
2. TG deck side cladding: Detail drawing approved for A and B * 1. Handover of Power House from Civil to Mechanical:
row and submitted for C Row. Erection will start by 1st week Further floor 17mtr Handed over & 0 mtr in progress.
of April’23. Side runner fabrication will be started. All side 2. TG deck side cladding: Detail drawing approved for A
runners may be erected except between A1 & B1 and and B row and submitted for C Row. Erection will start by
between Col. #7 & Col. #8. 1st week of April’23. Side runner fabrication will be
3. TG Hall Permanent Lift: Permanent lift will reach site in end started. All side runners may be erected except between
of April’23 and will be erected by june’23. Also floor A1 & B1 and between Col. #7 & Col. #8.
connection from U-4 will be done. 3. TG Hall Permanent Lift: Permanent lift will reach site in
end of April’23 and will be erected by june’23. Also floor
connection from U-4 will be done.
Page 4 of 7
The West Bengal Power Development Corporation Limited

[Ph. – III, (1x660 MW, U#5) SGPROJ03]


MINUTES OF WEEKLY PROJECT REVIEW MEETING (WPRM- 88) – at SgTPP on 08.04.2023.

U #5 BOILER LIT-UP TARGET DATE: 28.01.2024.


4. 2nd TG hall EOT crane: In manufacturing stage.
5.TD BFP: EOT crane will reached at site by April end.
7 LP Piping 1. Front availability of CW pipe laying near Cooling Tower 1. Front availability of CW pipe laying near Cooling
2. Erection Plan required for LP piping Tower- Excavation shall start from 20.04.2023 after
placement of 3rd & 4th CW pipe pc as per plan .
2. Erection Plan required for LP piping – Plan submitted
vide email dated 05.04.2023
7 Critical 1. 250KVA P91 set available by 2nd week of April23. ALL POINTS RELATED TO BOILER . TAKEN UP IN BOILER
piping 2. 02 nos. induction heating m/c available, PCP will supply POINTS
another 02 nos. by April 2nd week, another 02 nos. will be
available by May’23. BHEL will provide another 02 nos. by 1. 250KVA P91 set available by 2nd week of April23.
April’23. 2. 02 nos. induction heating m/c available, PCP will supply
4. Job started from 27.03.23. (Initial date: 18.03.23). Separate another 02 nos. by April 2nd week, another 02 nos. will be
gang will be arranged based on front and material availability. available by May’23. BHEL will provide another 02 nos. by
5. UT/RT will be arranged in time as per FQP. April’23.
6. All erection drawings need to be finalized. Issue to be taken 4. Job started from 27.03.23. (Initial date: 18.03.23).
up with BHEL Trichy and WBPDCL /HQ/DCPL. Separate gang will be arranged based on front and
7. Critical piping job already started. Additional 10 nos. material availability.
manpower mobilization by 07.04.23. Work will resume from 5. UT/RT will be arranged in time as per FQP. Noted and
10.04.23. issue closed.
6. All erection drawings need to be finalized. Issue to be
taken up with BHEL Trichy and WBPDCL /HQ/DCPL.
7. Critical piping job already started. Additional 10 nos.
manpower mobilization by 10.04.23. Work will resume
from 10.04.23.
CIVIL & STRUCTURAL
CHIMNEY WORK
8 Civil Chimney: Chimney:
works 1. RCC -6150/9500cum completed. Height: 134.85mtr as on 1. RCC -6330/9500cum completed. Height: 140.00mtr
/Chimney 30.03.2023. as on 07.04.2023.
2. 161.34 MT cement available as on 30.03.2023 at site. 2. 58 MT cement available as on 08.04.2023 at site.
3. Fabrication work for flue started from 20.03.23. (Initial 3. Fabrication work for flue started from 20.03.23.
date: 13.03.23). 17/620MT Completed as on (Initial date: 13.03.23). 34MT/620MT Completed as
30.03.2023. on 07.04.2023.
4. 2nd Bending machine will be available at site by 15.04.23. 4. 2nd Bending machine will be available at site by
This machine will be barrow by BHEL in risk and cost of 12.04.23.
KEPL. 5. Lifting method of flue can mast be submitted by
5. Weekly Target: Shell casting 15 Mtr .Structural 13.04.23.
fabrication 40 MT. Weekly Target: Shell casting 15 Mtr(Height 144.7 Mtr).
Structural fabrication 40 MT.
Main Plant and BOP PKG
9. Civil Works Power House: Power House:
Main Plant Control room: All control room related beams and materials Control room: All control room related beams and
& BOP to be shifted before 07.04.23. materials to be shifted before 15.04.23.
AB Bay EL (+) 17.00M Floor: Structural erection and handover *AB Bay EL (+) 17.00M Floor: Structural erection and
at grid 6-7 will complete by 15.04.2023. (Initial date: handover at grid 6-7 will complete by 15.04.2023. (Initial
16.03.23). Starting from 01.04.2023. date: 16.03.23). Starting from 10.04.2023.
Deaerator Floor: will be completed by April ‘23 end. Deaerator Floor: will be completed by April ‘23 end.
DECK SHEET WORK: completed for grid 2 to 13 and PH Roof DECK SHEET WORK: completed for grid 2 to 13 and PH
slab casting will start from 03 April 2023. Roof slab casting will start from 10 April 2023.Completed
STAIR CASE WORK: SC – 05 (BC bay 1-2 grid) - Erection started by 30.04.23.
from 22.02.2023 and completed. Welding and Hand railing STAIR CASE WORK: SC – 05 (BC bay 1-2 grid) - Erection
works under progress. started from 22.02.2023 and completed. Welding and
25.00m BC bay (Grid 1-2) Floor slab casting complete by Hand railing works under progress.
15.04.2023. (Initial date: 18.03.23). Roof casting start after 25.00m BC bay (Grid 1-2) Floor slab casting complete by
completion of roof access. (Initial date: 25.03.23). Access to 15.04.2023. (Initial date: 18.03.23).
roof will complete by 07.04.2023. BC bay (grid 2-4) handover PH ROOF: Roof casting start after completion of roof
and protocol under progress. (Initial date: 13.03.23). access. (Initial date: 25.03.23). Access to roof will
0.00mtr Floor: Next week target ABC bay (3-4) casting by complete by 10.04.2023. BC bay (grid 2-4) handover and
10.04.2023 and A-Aa bay (9-11) casting by 05.04.2023. (Initial protocol under progress. (Initial date: 13.03.23).

Page 5 of 7
[Ph. – III,(1x660 MW, U#5) SGPROJ03]

MINUTES OF WEEKLY PROJECT REVIEW MEETING (WPRM- 88) – at SgTPP on 08.04.2023.

date: 20.03.23). Next week target TDBFP oil pit, Lift pit at grid 0.00mtr Floor: Next week target ABC bay (3-4) casting by
13-15. 10.04.2023 and A-Aa bay (9-11) casting by 08.04.2023.
8.5mtr Floor: BC bay (9-11) casting completed. (Initial date: 20.03.23). Next week target TDBFP oil pit, Lift
Feeder Floor:- LHS feeder floor structural handover for casting pit at grid 13-15.
by 05.04.2023 and fllor casting complete by 21.04.2023. Next 8.5mtr Floor: BC bay (9-11) casting completed. Issue
week target is deck sheeting at 03 spans and reinforcement closed
fixing at one span. Feeder Floor:- LHS feeder floor structural handover for
Transformer Yard: Rail track upto SAT will completed by casting by 08.04.2023 and floor casting complete by
15.04.2023. (Initial date: 31.01.23). 21.04.2023. Next week target is deck sheeting at 03 spans
ESP Control Room: 3.7mtr floor casted on 27.03.2023 (80%). and reinforcement fixing at one span.
0.0mtr grade slab casting completed (90%). Total Ground floor Transformer Yard: Rail track up to SAT will completed by
slab and 3.70m floor slab casting will complete by 15.04.2023 15.04.2023. (Initial date: 31.01.23).
(Initial date: 31.01.23). Lintel casting will start from 10.04.23. UAT Foundation: WBPDCL requested BHEL to finalised
CW channel & Feed Pool: 4th stage mechanical clearance for UAT foundation immediately.
reinforcement work by 07.04.23 and casting date will given in ESP Control Room: 3.7mtr floor casted on 27.03.2023
the next WPRM. (80%). 0.0mtr grade slab casting completed (90%). Total
Next week 02 nos. CW encasing will be done. Ground floor slab and 3.70m floor slab casting will
Fire pump side grade slab casting will start by 10.04.23. complete by 15.04.2023 (Initial date: 31.01.23). Lintel
CWTP: plinth beam completed First lift column casting done. casting will start from 10.04.23.
(Initial date: 18.03.23). ESP inlet side ID duct foundation (A, B CW channel & Feed Pool: 4th stage mechanical clearance
& C pass): for reinforcement work by 07.04.23 and casting by
Raft casting completed for A, B and C pass. Final bolt lift in 20.04.2023
progress and will completed. CW piping: 1st pipe encasing foundation completed .Next
FAE Tower: FAE 1& 2 foundation completed and pedestal week 01 nos. CW encasing will be done.
under progress. BHEL committed that FAE tower 1, 2, 3 & 4 Fire pump side grade slab casting will start by 10.04.23.
will complete by March’ 23 end in all respect. 04 nos. CW pipes will be fitted by 15.04.23.
FD Fan – A & B: Beam work completed and VIS spring fixing by CWTP: plinth beam completed First lift column casting
03.04.2023 Deck casting in April’23. done. (Initial date: 18.03.23).
ESP inlet side ID duct foundation (A, B & C pass):
Raft casting completed for A, B and C pass. Final bolt lift
completed . issue closed.
FAE Tower: FAE 1& 2 foundation completed. BHEL
committed that FAE tower 3 & 4 will complete by April’ 23
end in all respect.
FD Fan – A & B: Beam work completed and VIS spring
fixing by 11.04.2023 Deck casting in April’23.
10. ENCASING Encasing at Boiler: 17/26 nos. completed. Encasing at Boiler: 17/26 nos. completed.
WORK Balance 09 nos. column encasing boiler area as per front Balance 09 nos. column encasing boiler area as per front
availability. availability.
Encasing APH area: 21/38 nos. completed, balance to be Encasing APH area: 21/38 nos. completed, balance to be
completed by 15.04.2023. (Initial date: 25.01.2023). completed by 15.04.2023. (Initial date: 25.01.2023).
11 Structural As on date approved fabrication drawings available at site: As on date approved fabrication drawings available at
Works/ Main Power House: Drawing: - 8831/9700 MT (Excluding Bunker site: Power House: Drawing: - 8831/9700 MT (Excluding
Plant & BOP bay), Mill & Bunker approved fabrication drawing 1198/1636 Bunker bay), Mill & Bunker approved fabrication drawing
MT, Fabrication: 8251/8831MT, Erection: 7408/8141.59 MT. 1198/1636 MT, Fabrication: 8321/8831MT, Erection:
Bending machine issue resolved for ring beam. 7468/8141.59 MT.
RHS feeder floor beam clearance by April’23 First week. Bending machine issue resolved for ring beam.
RHS feeder floor beam clearance received on 1.04.2023
CHP/AHP
12. Structural/ As on date approved fabrication drawings available at site: As on date approved fabrication drawings available at
Civil/Works/ CHP-10000/11962 MT. site: CHP-10000/11962 MT.
AHP/CHP Fabricated 6056.67MT/10000. Available drawing for further Fabricated 6218MT/10000. Available drawing for further
fabrication is 3943.33 MT. fabrication is 3782MT.
Target for Mar ’2023 at CHP area: Target for April ’2023 at CHP area:
Fabrication – 983.912 MT, Erection –779.00 MT. Fabrication – 938.37 MT, Erection –752.518 MT.

TP-20: Fab. Completed 663.27/752 MT, erection 336.911 TP-20: Erection work is in progress. (337/752MT).
/752MT. TP-20A: Erection work is in progress. (269/1171MT).
TP-20A: Erection work is in progress. (267.41/1171MT). TP-21: Erection work is in progress. (298/826MT).
TP-21: Erection work is in progress. (297.54/826MT). TP-22: Erection work is in progress. (364/656MT).
TP-22: Erection work is in progress. (364.33/656MT). TP-23: Erection work is in progress (102/291MT).
TP-23: Erection work is in progress (102.00/291MT). BCN-23 A/B: Erection work is in progress 500/862MT.
BCN-23 A/B: Erection work is in progress 495.64/862MT. Gallery fabrication in progress & erection will be complete
Gallery fabrication in progress & erection will be complete by by 15.04.2023.

Page 6 of 7
The West Bengal Power Development Corporation Limited

[Ph. – III, (1x660 MW, U#5) SGPROJ03]


MINUTES OF WEEKLY PROJECT REVIEW MEETING (WPRM- 88) – at SgTPP on 08.04.2023.

U #5 BOILER LIT-UP TARGET DATE: 28.01.2024.


15.04.2023. BCN-25 & 27 A/B: Erection front will be available after
BCN-25 & 27 A/B: Erection front will be available after APH APH erection. BCN 25 Fabrication completed. BCN 27:
erection. BCN 25 Fabrication completed. BCN 27: 172.77MT 174.00MT fab completed.
fab completed. Crusher House: Fabrication started from 20.11.22. Till
Crusher House: Fabrication started from 20.11.22. Till date date completed- March: 588/1900 MT. Erection:
completed- March: 560.94/1900 MT. Erection: 263.20/1900 277/1900 MT.
MT. BHEL committed that Erection of TP – 20A, TP – 21 & TP –
BHEL committed that Erection of TP – 20A, TP – 21 & TP – 22 22 will complete by June’23 end in all respect.
will complete by June’23 end in all respect. WBPDCL instructed to increase Alignment and Erection
WBPDCL instructed to increase Alignment and Erection welding gang to meet monthly targets. Same is being
welding gang to meet monthly targets. Same is being increased sequentially – Noted and being complied.
increased sequentially
13 Civil Works BCN-30 A/B: Mechanical erected 143.91/648MT BCN-30 A/B: Mechanical erected 152/648MT
AHP/CHP BCN-36 A/B: TR-7 work will be executed by April’23 as per BCN-36 A/B: TR-7 work will be executed by April’23 as
work permit issued. Erection completed 121.84/522MT. per work permit issued. Erection completed 130/522MT.
WT: 1st lift wall casting completed. Recovery plan for WT WT: 1st lift wall casting completed. Recovery plan for WT
balance work will be submitted on 25.03.23. (Initial date: balance work submitted on 25.03.23. (Initial date:
14.03.23). 14.03.23). Before monsoon target reach slab casting -
CHP-MCC-1: Work is in progress. Columns lift completed. 70% 10mtr.
Grade slab completed. Ground floor slab casting completed by CHP-MCC-1: Work is in progress. Columns lift completed.
15.04.23. Staging started on 10.03.23. 70% Grade slab completed. Ground floor slab casting
CHP-MCC-2: 4.60mtr Slab casting (60%) completed and completed by 15.04.23. Staging started on 10.03.23.
balances by April’23. (Initial date: Mar’23). CHP-MCC-2: 4.60mtr Slab casting (60%) completed and
Silo: 2nd tier slab casting completed. Shell will start in April’23 balances by April’23. (Initial date: Mar’23).
end. (Initial date: Mar’23). Silo: 2nd tier slab casting completed. Shell will start in
TP-25: Final bolt lift completed and back filing under progress. April’23 end. (Initial date: Mar’23).
Ready for Mechanical erection by 10.04.2023 TP-25: Final bolt lift completed and back filing under
TP-26: Temporary structure erection completed. progress. Ready for Mechanical erection by 10.04.2023
TP-26: Temporary structure erection completed.
14 Switch yard 1. BCR-1, BCR-2 and LT SWGR building slab casting 1. BCR-1, BCR-2 and LT SWGR building slab casting
Battery completed. Battery room column casting under progress. completed. Battery room column casting under
Room Civil Entire earth mat work completed and cable trenches progress. Entire earth mat work completed and cable
work work under progress expected completion by April’23. trenches work under progress expected completion
(Initial date: 31.03.23). by April’23. (Initial date: 31.03.23).
2. Equipment Erection status 2. Equipment Erection status
CB: 00/12 nos. CB: 00/12 nos.
CT: 15/18 nos. CT: 18/18 nos.
LA: 00/06 sets. LA: 00/06 sets.
CVT: 00/03 sets. CVT: 00/03 sets.
Isolator: 04/12 sets Isolator: 05/12 sets
BPI: 00/53. Sets BPI: 00/53. Sets
Stringing: 06/09 span Stringing: 08/09 span
15. Construction 2nd construction source will be charged by 09.04.23 2nd
2nd source half in presence of safety personnel.
16. Road & Drain Work of Drain No 7/8/26/41/444 under Progress Work of Drain No 7/8/26/41/44 under Progress
Culvert BC-6 and 7 Completed. Culvert BC-6 and 7 Completed.

BHEL WBPDCL

Page 7 of 7