Site HSE Inspection Report: Document
Site HSE Inspection Report: Document
Document 21-08-2020
Site HSE Inspection Report Sub-Contractor
HPCC
Project Name: 700MW CSP= 250MW PV Hybrid IPP-DEWA Phase IV
Report Number: 01 Reported by: CARLO Location: MEB /HFCC
Responsible
Observation Location Corrective Action Status
Person
1. No available general MEB Immediately coordinate to HPCC Safety Closed
work PTW for chipping subcontractor HSE officer and Charles
work manual handling HPCC supervisor to provide HPCC Engineer
general work PTW. Yang
3. Improper installations of MEB Ground Immediately coordinate to site Site Safety Closed
earthing without floor HPCC engineer and site safety to Charles
earthing clamp provide earthing clamp and Site Engineer
installed properly the earthing Yang
4. Electrical connection on MEB Immediately coordinate to HPCC Engineer Open
distribution panel subcontractor HPCC engineer and Yang
without proper glanding site safety in charge to provide Site Safety
and protection cover proper protection and glanding to Charles
exposed the cable to the cable of distribution panel.
damage.
5. Synthetic web sling used HFCC Immediately notify site safety and HPCC Engineer Open
without available third HPCC engineer to provide third HPCC Site
party certificate and not party certificate of synthetic web Safety Charles
color code the shackle sling and shackle and color coded
and synthetic web sling. the lifting gear
6. Poor cable management MEB Immediately coordinate to HPCC Closed
on workplace. Electrical subcontractor HPCC safety and Supervisor
Room supervisor to arrange the cable Site Safety
properly and provide cable stand Charles