Professional Documents
Culture Documents
Management
1. According to Clause 17 of the FIDIC Red Book 2017, who is responsible for the care
a. Engineer
b. Employer
c. Contractor
d. Subcontractor
e. Architect
2. Under Clause 17, the Contractor is required to protect the works from:
a. Design changes
b. Loss or damage
c. Environmental impact
d. Delays in payment
e. Quality defects
3. The indemnity obligations under Clause 17 cover all of the following parties,
EXCEPT:
a. Employer
b. Engineer
c. Contractor's subcontractors
d. Employer's personnel
e. Consultant's representatives
a. Employer's risks
c. Contractor's negligence
d. Breach of contract
5. What is the purpose of including the Care of the Works and Indemnities clause in
6. The Contractor's liability for loss or damage under Clause 17 may be capped or
a. Environmental impacts
d. Contractor's negligence
a. Contractor only
b. Employer only
8. The Contractor's obligation to care for the works includes compliance with:
9. What does the Contractor's indemnity obligation cover under Clause 17?
10. Who may provide guidance and interpretation of the obligations outlined in Clause
17?
b. The Engineer
12. The Contractor's liability for damage to the works is limited to:
c. Liquidated damages
d. Consequential damages
13. Which party is responsible for maintaining insurance coverage for risks associated
a. Engineer
b. Contractor
c. Employer
d. Subcontractor
e. Project Manager
14. The Contractor's liability for damage to the works extends to which of the following?
15. Who is primarily responsible for the design, construction, workmanship, and safety
of the works?
a. Engineer
b. Contractor
c. Employer
d. Subcontractor
e. Project Manager