Appendix A/ Lampiran A – Description of Services/ Deskripsi Jasa

Item Description Discipline Week Note

1 Injection Line Design Handover Contract June 2023 – 2nd week

2 Contract Sole Sources Contract June 2023 – 3rd week

Procurement Process based on Jacobs design


2 Procurement July 2023 – 1st week
and material datasheet

Update Forcon Drawing DED – If required based


3 Engineering July 2023 – 2nd week
on Jacobs DED

4 Team Mobilization Start Construction June 2023 – 4th week

5 Early Work For Construction Commence Construction July 2023 – 1st week

Re-injection line construction completion and tie 2 weeks after completion drilling
6 Construction Oct 2023 – 1st week
in within WEX02 well pad WEX2 / 1 week after rig out
Re-injection line construction tie in within
7 Construction Aug 2023 – 4th week
Hotspot 02 or IP2X injection pad
Re-injection line construction from WEX02 to
8 Construction Aug 2023 – 4th week
Hotspot 02 complete
Re-injection line construction completion and tie 2 weeks after completion drilling
9 Construction Nov 2023 – 4th week
in within Central well pad Central / 1 week after rig out
Re-injection line construction completion and tie 2 weeks after completion drilling
10 Construction Jan 2024 – 1st week
in within Hotspot well pad Central / 1 week after rig out

Re-injection line construction from Central –


11 Construction Oct 2023 – 4th week
Hotspot – HS02 and IP2X
Provide commissioning work after
12 Testing, pre commissioning & Commissioning Commissioning
all construction work completed
As built drawing should be
As Built (WEX02, Central, Hotspot, Re-Injection
13 As built dwg Jan 2024 – 2nd week provided 1 week after each
Line)
construction finish &
14 Maintenance Injection Line Complete Maintenance Feb 2024 - 1st week

2 weeks after drilling complete for


15 Relocation of Scale inhibitor within well Construction next location or 2 weeks after
pumping test previous location
Identified location as per advise by
16 Line decommission - complete Decommissioning Mar 2023 - 2nd week
Principal

16 Contract Close out Contract 30 April 2024

STM-CN23-050
EPCM Water Injection Line