Professional Documents
Culture Documents
5 Early Work For Construction Commence Construction July 2023 – 1st week
Re-injection line construction completion and tie 2 weeks after completion drilling
6 Construction Oct 2023 – 1st week
in within WEX02 well pad WEX2 / 1 week after rig out
Re-injection line construction tie in within
7 Construction Aug 2023 – 4th week
Hotspot 02 or IP2X injection pad
Re-injection line construction from WEX02 to
8 Construction Aug 2023 – 4th week
Hotspot 02 complete
Re-injection line construction completion and tie 2 weeks after completion drilling
9 Construction Nov 2023 – 4th week
in within Central well pad Central / 1 week after rig out
Re-injection line construction completion and tie 2 weeks after completion drilling
10 Construction Jan 2024 – 1st week
in within Hotspot well pad Central / 1 week after rig out
STM-CN23-050
EPCM Water Injection Line