F-Delay Analysis Gangapath 15.04.2024
F-Delay Analysis Gangapath 15.04.2024
Sl. No. Description Apr-23 May-23 Jun-23 Jul-23 Aug-23 Sep-23 Oct-23 Nov-23 Dec-23 Jan-24 Feb-24 Mar-24 Apr-24 May-24 Jun-24 Jul-24 Aug-24
NOC from patna encumbrance due to Temple,Majar,patna university examination building & pump
1 Actual handing over land
university . house.Encrumbance continues upto the Month of March,24.
Handing over of land and relocation of utilities at Km 8+450 Delay in Poviding ROW
1 6/1/2023 3/31/2024 304
connectivity (Pier- P5)
Construction of Ganga path from Digha to Didarganj (21.50 Km) at Patna in the state of Bihar on EPC Mode
ORIGINAL SCOPE 1 2 3 4 5 6 7
Stage 1: Clearing & Grubbing of land, Removal of Soil and Disposal as per
drawing (Varies from 1.00 m to 3.00 m) & Ground improvement including laying Stage 11.44 117025208 11.44 115554064 0
of Mactex & Paralink and Embankment Filling & filling upto OGL
Stage 2: Embankment Filling upto Height of 2 M from OGL Stage 11.44 511985198 11.44 505548941 0
Stage 3: Embankment Filling from OGL+2m Upto HFL Berm Level Stage 11.44 511985287 11.44 505549028 0
Stage 4: Embankment Filling from HFL Berm upto Sub-Grade Top Level
Stage 11.44 321819323 11.44 317773675 0
( Subgrade CBR Value - 10)
Stage 1: River Side Slope Protection Work - Upto HFL berm level Stage 11.44 175537813 11.44 173331095 0
Stage 2: River Side Launching Apron Stage 11.44 234050417 11.44 231108127 0
Stage 3: River Side Slope Protection Work - Berm Level to FRL Stage 11.44 58512604 10.62 57777032 0.82 897039 0.82
Stage 4: City Side Toe Drain & City Side Slope Protection Work OGL to FRL Stage 11.44 117025296 10.04 115554150 1.40 1053829 1.40
WMM & Shoulders - 250 mm Thick Stage 11.44 190165964 11.44 187512151 0 16622899
Digha @-0+580 to 0+000 and MG Setu +12+000 to 12+200 Grade Separators 2 547430422 1.55 373721190 0.45 386736695 0.052 0.013 0.178 0.137 0.069
A Culverts Nos
B Grade separated structures (a) Underpasses and Junction improvement Nos 3 71094860 2 47396574
Total Turnover for Embankment 3239291525 2976762602 224.20 50.53 688.52 530.60 265.30 0.00 0.00
a Foundation
Piling Nos 907 907 0 0 0 0 0 0 0 0
Piles 1900 mm dia - MCW Nos 727 2879341830 727 2876427516 0
Piles 1000 mm dia - MCW
Piles - EVUP & RL Nos 180 180 0
Pile Cap Nos 232 223 9 8 1 0 0 0 0 0
Pile Cap for 1900 dia piles - MCW Nos 180 863802549 179 862928255 1 0 1 0 0 0 0 0
Pile Cap for 1000 dia piles - MCW 0 0 0
Pile Cap - EVUP & RL Nos 52 44 8 8 0 0 0 0 0 0
b Substructure Nos
Pier Nos 232 216 16 8 8 0 0 0 0 0
Pier Cap Nos 232 216 16 0 8 8 0 0 0 0 0
Pier & Pier cap 2500 mm dia- MCW Nos 180 2879341830 179 2866713138 1 0 1 0 0 0 0 0
Pier & Pier cap 1500 mm dia- MCW 1 0 0
Pier & Pier cap - EVUP & RL Nos 52 37 15 8 7 0 0 0 0 0
c Superstructure Nos
Segment Casting Nos 2431 1895566705 2431 1895566705 0 0 0 0 0 0 0 0
Segment Erection Nos 143 646628507 135 614583200 8 4005663 4 4 0 0 0 0 0
Casting PSC Girder(24.62m) Spans Nos 19 49212435 19 49212435 0 0 0 0
d Crash Barriers & Railings Nos 162 287934183 141 250166500 21 1798461 8 8 5
SuperStructure of EVUP including Rails Nos 47 4 43 4 4 8 7 5 5 10
Total Turnover for Elevated Structure 9501828039 9415597749 304.10 304.10 89.92 0.00 0.00 0.00 0.00
3 Other Works
a Toll Plaza Nos 1.00 26660573 0
Road Side Drains Stage 11.80 36212346 11.19 34343380 0.61 3068843 0.61
Protection work at elevated structure portion of 7600m length Stage 10.00 748628887 6.84 512219757 3.16 74884108 2.00 1.16
c Road Signs, Marking KM 13.50 20088431 7.54 11219761 5.96 1488032 2.5 3.460000008
d Project Facilities 0
a) Bus Bays Nos 1.00 39990859 0.38 23994515
b) Truck Lay bays Nos 0.00 0 0 0
c) Rest Areas Nos 2.00 12187690 0
d) Others Nos 1.00 10664229 0.7 7330844
e Road Side Plantation 4.24 9053086 4.24 9754876 0.00
f Safety & Traffic Management Nos 5.02 13392288 5 13330286 0.02 3100067 0.02
Total Turnover for Other Works 916878389 612193419 1534.88 937.20 0.00 0.00 0.00 0.00 0.00
Total Turnover for Km.0+000 to Km 13+500 136580 130046 2063 1292 778 531 265
Page 3 of 4
Ganga Path Project
Turnover ( in Lacs)
Sl.No Structure Feb-24 Mar-24 Apr-24 May-24 Jun-24 Jul-24 Aug-24 Total
Total Completed Balance
1 OS-MCW- Km:0+000 to Km:13+500 136580 130046 4929 2,063 1,292 778 531 265 - - 4929
Total 151907.42 145023.94 4962.31 2096.12 1291.84 778.44 530.60 265.30 0.00 0.00 4962
Percentage of Completion
42.24% 26.03% 15.69% 10.69% 5.35% 0.00% 0.00%
w.r.t Balance works
Percentage of Completion
95.47% 1.38% 0.85% 0.51% 0.35% 0.17% 0.00% 0.00% 3.27%
w.r.t Total Scope