Initial JDL

Week No. 26
DAILY ACTIVITY REPORT Date Cut-In 26-Jun-23

WEEK 26 - 2023 Date Cut-Off 2-Jul-23


Date Prepared 30-Jun-23
ENGINEERING DEPARTMENT JHUN MICHAEL D. LOCUS Checked by ASS
CAVITE PHILIPPINES OFFICE PROJECT ENGINEER Submitted To RDE
Date Project Specific Job Worked Time Notes & Remarks

26-Jun-23 22024 PM4 Equipment Stock Prep Equipment Layout reposition of equipments 8:00 AM - 5:00 PM Start

Change on Equipment layouts- Sedimex, Sieb contaminex, & Refiner Draft Done

Reference Plan for Location of HDC Rack Finished

27-Jun-23 22024 Reference plan layout for HDC 8:00 AM - 5:00 PM Start

Reference data for reject handling Finished

Proposed Reposition of Equipments with rejects Finished

28-Jun-23 22024 Piping hole for reject and suction 8:00 AM - 5:00 PM Start

Change on Equipment Layout- Drum sorter & Turbo separator Draft Done

Checking of proposed layout & repositioning of equipments Draft Done

29-Jun-23 22024 PM4 Stock prep equipment, junkomat and junk trap reference 8:00 AM - 5:00 PM Start

proposed junkomat and sedimex position Draft Done

consideration of piping line for mixed waste line Draft Done

30-Jun-23 22024 Determining the suction position for Pulper Line 3 and 4 8:00 AM - 5:00 PM Start

Reject handling equipment- Rake Classifier reference - Draft Done

Confimation of location of pumps for Pulper Line 3 & 4 Finished

1-Jul-23 - Holiday

2-Jul-23 - Rest Day

Prepared By: Jhun Michael D. Locus Submitted To: PPI Office


Date: June 30, 2023 Date: June 30, 2023
Evaluation and Remarks:
Checked By: Arnold S. Sapanta 1-
Date: June 30, 2023 2-

Week 26-2023 JDL Activity Report Page 1 of 1