Progress

Cut and Fill Work


Progress Until :
22 October 2023
Total land area :
19 Ha
Area of land completed :
2 4
3,23 Ha
Percentage :
17,01%
Working Progress

Already Finished

1 3 Cutting work on progress

Filling work on progress

Area of next filling works