You are on page 1of 2

#Actionable points on TBM Commissioning and Excavation Dated: 28.07.

2023
TBM-1 (SHAKTI) Progress Beyond RTB Chainage 48180
A1 Shield Chainage 50040.35 Total excavtion by TBM-1 (in RM) 1861.50
Face Chainage 50041.50 in terms of Rings 1095 Inverts installed 1083
TBM-2 (SHIV) Progress Beyond RTB Chainage 878
A2 Shield Chainage 1833.95 Total excavtion by TBM-2 (in RM) 957.10
Face Chainage 1835.10 in terms of Rings 563 Inverts installed 551
243
Conveyor belts: Commisioning Date Remarks
B TBM-1 (SHAKTI) 22.04.2023
15 rolls of 1m width belts, 500m each available at Portal 1 store for both TBMs
TBM-2 (SHIV) 08.06.2023

MSVs: Commisioning Date Remarks


MSV-1 17.01.2023
C MSV-2 15.01.2023
MSV-1 to 4 operational at site
MSV-3 20.04.2023
MSV-4 24.04.2023

Casting of Ring segments/Invert segment (Availability of parts for initial start-up of casting activities)
S.No. Item Scope Available Remarks
In % Date
Availability of Mould Sets 12 12 100%
1 Available 100% i.e. 12 sets recived
INVERT 12 12 100%
Total Required Total rings casted Total rings installed in tunnel Stock Available
Gasket for 2523 ring along with 13.65 ton
D 2 Supply of gaskets enough for 2523
12,224 Rings 2933 1658 adhesive is available at site.
rings

Segment rings casted FTW FTM Cumulative Available 2933 Ring casted & 2650 Invert Casted.
3 Factory-1 60 178 1989
Tentative target- 2978 rings by Jul 2023
Factory-2 64 188 944 2933
(450 Rings for July 2023)
Invert 126 522 2650

Page 1 of 2
#Actionable points on TBM Commissioning and Excavation Dated: 28.07.2023

Availability of spares - Target


Remarks
S.No. % Date
E 1 As per desired list of items 100% Jan-23-W-4
These are through SLA with HK.
2 Disc Cutters (Total No. reqd:) TBM 1
1 set Received at Site
3 Disc Cutters (Total No. reqd:) TBM 2

Stacking of aggregates/raw materials vis-à-vis Total required


S.No. Material Required Available (Tons) Remarks
1 Aggregates 21920
2 Cement (at Portal 1) 755
F 3 Grout- 1 component (BENTONITE) 42.00
4 Grout- 2 component (SODIUM SILICATE) 86
5 Microfine cement 9.75
6 Collidal Silica 4.30
7 PU grout 1.6

G Availability of TBM consumable as per OEM List. Target Date = Dec-22 (Available for initial drive), remaining will be delivered at site as per consumption.

Page 2 of 2

You might also like