Title: Clarification on Lay-up after Hydrotest. Request # 4043558843
Requester Name: Requester Org: Request Date:
Shivputtrayya Manjunath Math (MATHSM) Hook-Up/Tie-in Div ( 30027110)
Current Responsible Employee : Status: Current Step:
Mohammed Faisal Al Subaie (SUBAMF0N) Awaiting Input Implementation Concurrence
Details
Main Information
Field Name Selected Value(s)
Equipment Number OFFSHORE PROJECT DEPARTMENT
ES Department Consulting Services Department
Plant Number OFFSHORE PROJECT DEPARTMENT
Please specify if this is a PMT No
request
Priority High (Division Head#s approval )
Assigned Group Corrosion Engineering
Service Type Materials Engineering
Notes
Justification:
On behalf of Offshore Project Department (OPD) and Hook-up and Tie-in
Division (HTD). I the undersigned hereby submit my write-up to seek
clarification on Lay-up requirement per SAES-A-007 Edition Aug 18, 2019.
Additional Information:
The query is related to Lay-up requirement on following below steel
grades (reference taken from Table 3 of SAES-A-007) below.
Material Category:
Note: Maximum Contact Time Limits = 30 Days (for the above mentioned
material category Sr. No. 1 to 5).
Request Information
Title: Clarification on Lay-up after Hydrotest. Request # 4043558843
Requester Name: Requester Org: Request Date:
Shivputtrayya Manjunath Math (MATHSM) Hook-Up/Tie-in Div ( 30027110)
Current Responsible Employee : Status: Current Step:
Mohammed Faisal Al Subaie (SUBAMF0N) Awaiting Input Implementation Concurrence
Material Category:
Note: Maximum Contact Time Limits = 14 Days (for the above mentioned
material category Sr. No. 1 to 2).
# SAES-A-007 Para 9.2 Assets shall be laid-up per section 9.4 if water
contact time exceeds the limits set in Table 3. This is regardless of
the purpose behind water usage; e.g. flushing, cleaning, etc.
Query:
The Lay-up requirements comes into play, when the water contact exceeds
the limits set in Table 3. In our case, when we perform hydrostatic
pressure testing the test duration is (aforementioned 10 minutes or 30
minutes for Piping spools and 2 hours for Pipeline spools). If we add up
hydrostatic pressure testing preparation time i.e., the time consumed to
fill the water in the spools till pressurization completion time we
never exceed one (1) or two (2) days. Therefore, we don#t see our
testing criteria falls under the boundary of SAES-A-007 Para 9.2 which
leads us to believe we do not have to perform lay-up for the material
Request Information
Title: Clarification on Lay-up after Hydrotest. Request # 4043558843
Requester Name: Requester Org: Request Date:
Shivputtrayya Manjunath Math (MATHSM) Hook-Up/Tie-in Div ( 30027110)
Current Responsible Employee : Status: Current Step:
Mohammed Faisal Al Subaie (SUBAMF0N) Awaiting Input Implementation Concurrence
Regards,
***
Manjunath. Math.
Offshore Projects Department (OPD).
Hook-Up & Tie-In Division (HTD).
DPC-811, Tanajib.
Desk Phone: +966 - 13 - 3789245.
Phone: +966 500979939.
Recommendation:
Dear Manjunath,
Request Information
Title: Clarification on Lay-up after Hydrotest. Request # 4043558843
Requester Name: Requester Org: Request Date:
Shivputtrayya Manjunath Math (MATHSM) Hook-Up/Tie-in Div ( 30027110)
Current Responsible Employee : Status: Current Step:
Mohammed Faisal Al Subaie (SUBAMF0N) Awaiting Input Implementation Concurrence
CRM-ESR request.
Kind regards,
Hendrik J. Debruyn
Engineering Consultant - Corrosion
Vice Chairman - Corrosion Control Standards Committee
CSD
Auto Approvals
Agent Title Agent Name Agent Position Title Status Status Date
Approver Mohammad Abdulrahman Al Acting as - Project Manager Completed 03/09/2021
Suwaiyel