Concreting of Brgy. Poblacion Ilaya to Brgy. Project should have been completed last
Malagab-I FMR, Brgy. Poblacion Ilaya and August 31, 2023. Request for CTE1 is
Brgy. Malagab-i, Cuartero, Capiz still being processed. If approved,
23GP0069
expiry is on October 20, 2023. Project
accomplishment is 59.70% as of this
day.
Project should have been completed last
August 14, 2023. Revised expiry due to
Concreting of Mapulang Bato FMR, Brgy. CTE1 is last October 3, 2023. Project
Capiz 2nd DEO 23GP0070 accomplishment is 92.06% as of this
Mapulang Bato, Dao, Capiz
day. Project can be completed this year.