Peter’s College
No. 042 Sabayle Street, Iligan City
College of Engineering
Electrical Engineering Department
2. Karding and you laughed. He was talking and said he led constructing a temporary office 4' by 8' by 3'. Then the work was done on lighting and outlets. He spent
more than Php 100,00.00 for 7 days. He brought 3 electricians with him. He doesn't know that you are an electrical works estimator. Verify the schedule of loads, his
estimates on electrical works, cost estimation and explain what you can suggest for his costing. Total length for 3.5mm 2 is 100m. The contract is only Php 100,00.00.
Explain your answer.
Demand Breaker
Description Current (A) Wire and Conduit Size
Load (VA) Size
Lighting
2,000 8.696 15 A 2-3.5 mm2 , 20mm PVC
Outlet
2-3.5 mm2 & 1-
10-Outlet 3,600 15.652 30 A
3.5mm2, 20mm PVC
2-3.5 mm2 &
3- Outlet 1080 4.696 15 A
1-3.5mm2, 20mm PVC
Spare 1500 6.522 15 A
Spare 1500 6.522 15 A
Spare 1500 6.522 15 A
Total 48.610
Main Breaker Size: 60AT, 100AF Feeder Size: 2-8.00 mm2 & 1-5.5mm2, 20mm PVC
Description Quantity Unit Material Cost Amount Labor Cost Amount Direct Cost
Mobilization 1 lot 15,000.00 15,000.00 5,000.00 5,000.00 20,000.00
Temporary facilities 1 lot 15,000.00 15,000.00 5,000.00 5,000.00 20,000.00
Requirement
Description Quantity Unit Material Cost Amount Labor Cost Amount Direct Cost
Mobilization 1 lot
Temporary facilities 1 lot
Requirement
Switches 8 pcs
Outlets 13 pcs
Lights 10 pcs
Miscellaneous 1 lot
Total
3.Cite an example where your estimate on electrical works and actual electrical works are different.