Certified Test, Adjust and Balance Report

Date of Issue: 12 December 2021 Name of Issuer Maged Mamdouh


System Name: Chilled Watter Reading By: Maged Mamdouh
Project Name: GIS
Project Location: ‫ﺍﻟﻌﺎﺻﻤﺔ ﺍﻹﺩﺍﺭﻳﺔ‬ Pages 3 of 5 Revision A
Date of Measure: 11 December 2021 System Served Area Basement 1
Form No. : QP-13-TB-03-F-01/1 Project No.: TAB -4166
Engineering Report

1- Balance device is installed inversely.


2- Fillter should be washed .
3- Balance device is not working it should be changed .

Reviewed By
For Engineer Main Contractor HVAC Contractor TAB
Name
Date

Signature