CHECK LIST FOR GAS CUTTING SET

MONTH OF CHECK: CONTRACTOR NAME: DOC. NO:

CHECK LIST
SL NO DESCRIPTION 1st week 2nd Week 3rd Week 4th Week 5th Week Remarks
Protective valve cap firmly fixed
1 for both Cylinder (Check for
damage/crack in the valve cap.
Pressure gauges two for each
cylinder(inlet & out)are in
2 working condition(both Oxygen
& Acetylene gas)
Flash back arrestor (FBAs) is
3 provided for acetylene
& oxygen cylinders
Non return valves (NRVs) is
4 provided for both acetylene &
oxygen cylinders.
Tight Crimping of hoses with
5
jubilee clamps.
Hose free from damage (cut and
6
cracks)
Cylinder secured by chain to the
7
trolley.
Trolley tiry shall be free from
8
damages.
Availability of industrial type
9 lighter (no match box
/Commercial lighters).
Cutting area should be barricaded
10 and warning boards to be
displayed
Cutting area shall be free from
11 debris and flammable materials.

Availability of PPE (Cutting


12 Goggles, Leather gloves Etc.)

Fire extinguisher and fire bucket


13
with sand availability
Checked by Project Engineer

Verified by Safety Officer

Approved by Projects Manager

DOC #: ABS-REC-EHS Rev / Dt: