QUTATION OF BUILDING CONSTRUCTION WITH MATERIAL

OWNER: -----------

PROJECT: RESIDENCE

LOCATION: GOMTINAGAR,LUCKNOW

BUILDER A&D CONSTRUCTION ARCHITECTURAL


D-114 VIBHUTI KHAND GOMTI NAGAR
LUCKNOW-226010
RATE 1500/SQ.FT.

RESPECTED SIR,

As per discussion for the construction quotation of your apartment. We will provide you
full finished building with below description of items-

1. MATERIAL SPECIFICATION:-
➢ CIVIL WORK-
• CEMENT- ACC/BIRLA/MYCEM/PRISM
• STEEL BAR - RHL/TATA TISCON
• BRICK - 1st CLASS
• STONE BALLAST - 1 st class
• COURSE SAND - 1 st class
• GRANITE /KOTA - 1 st class(ORDINARY RANGE)

2. FLOORING –
• VITRIFIED FLOOR TILES(2'X2') – KAJARIA/ASIAN/SOMANY(up to 55 rs./sq.ft. above this
will be charged extra)
• WALL TILES(1'X1'-6") – KAJARIA/ASIAN/SOMANY (up to 55 rs./sq.ft. above this will be
charged extra)

email id:-a.dconstructionarch@gmail.com
ADD.:-2/124, VISHWAS KHAND
GOMTI NAGAR LUCKNOW
MOB.-+91-9506913481
• MARBLE - WHITE MARBLE ( up to 60 rs./sq.ft. above this will be charged extra)
• GRANITE - STAIRECASE AND KITCHEN (ordinary range)

3. WOOD WORK-
• DOOR - PLYWOOD DOOR ( MALASIYA SAKU CHAUKHAT)
• WINDOW - TEAK WOOD WINDOW( MALASIYA SAKU CHAUKHAT)

4. PLUMBING WORK –
• WATER-PIPELINE – PVC PIPE (ASTRAL/JINDAL)
• PIPE LINE – PVC-6” (TIRUPATI/ASTRAL)
• RAINWATER PIPE – PVC-4” (TIRUPATI/ASTRAL)

5. SANITRY FITTING: –
• BATHROOM FITTINGS/ACCESSORIS –HINDWARE OR EQUIVALENT(ORDINARY RANGE)
• TOILET SHEETS (INDIAN/WESTERN) -HINDWARE OR EQUIVALENT(UP TO 8000/PER
SHEET)

6. PAINTING WORK:-
• WALLS / CEILING PAINT – ASIAN / NEROLAC
• TWO COAT WALL PUTTY WITH TWO COAT PAINT
• POLISHING WORK - DOOR / WINDOW FLUSHES

7. ELECTRIFICATION WORK-
• ALL PIPES (CONCEILED) – SEIKO/ ANCHOR
• ALL TYPE WIRINGS/SWITCHES – ANCHOR / HAVELLS (MODULAR)
• MCBs - HAVELLS

email id:-a.dconstructionarch@gmail.com
ADD.:-2/124, VISHWAS KHAND
GOMTI NAGAR LUCKNOW
MOB.-+91-9058913568
8. STEEL/GRILL WORK-
• GRILLS FOR WINDOW CHAUKHAT

• RAILING FOR STAIRCASE & FRONT PARAPET (SS WORKS)

9.TERMS AND CONDITION:-


• Covered area will be applicable for 11’ ht. Extra height will be rated extra
@ 3% per feet.

• Boring and electric connection will be separate from the rates .

• Main gate will be charged separate(Actual).

• All material used will be ISI marked.

• Lift charge will be paid 4% for each floor after 2nd floor slab.

10.PAYMENT SHEDULE:-
• GROUND FLOOR :-
Advance :- 15%
After footing :- 10%
After plinth :- 10%
Before shuttering for slab :- 20%

Before brick work & plaster :- 15%


Before sanitary work :- 10%

Before electrical work :- 10%


Before painting work :- 5%

After completion :- 5%

email id:-a.dconstructionarch@gmail.com
ADD.:-2/124, VISHWAS KHAND
GOMTI NAGAR LUCKNOW
MOB.- +91-9058913568

• FIRST FLOOR AND ABOVE ALL FLOOR :-

Before column :- 15%


After column :- 15%

Before shuttering for slab :- 30%


Before brick work & plaster :- 15%

Before sanitary work :- 10%


Before electrical work :- 10%

Before painting work :- 5%

DATE:-15/11/2017

CLIENT SINCERELY

(SIGNATURE) FOR A&D CONSTRUCTION ARCHITECTURAL