Inspection & Test Plan: Document No.

:ITP
ARABTEC CONSTRUCTION (L.L.C)
Procedure
Block Works Rev. No. :0
SAADIYAT BEACH RESORT Date

Type of Testing Requirement/ Acceptance Inspection Points Verifying / Control


Item No. Inspection Description Reference Document
Inspection Criteria ARABTEC ITA Consultant Data Forms
1.0 Approval of documents

Sh. Drwg. Submittal


1.1 Shop drawings Review Arch.Spec.,Vol.Sec. Approved shop drawings R - R
Sheet
Method statement
1.2 Method Statement Review Arc.,Spec., Vol.1,Sec.1 R - R
submittal Sheet

2.0 Materials

MARs. Test
certificates, Supplier
2.1 Materials approvals and conformity of delivered materials Review Arc.,Spec., Vol.1,Sec.1.01-5 R Test R
documents, Delivery
notes

3.0 Placing of Masonry

Surface of the foundation shall be


Str. Spec., Vol.,Sec.
roughened to receive the first
Approved method
3.1 Surface Preparation of foundation Visual P - S Checklist
statement (P088-ATC-VA-
CV-MDS-00004)
mortar bed
Arc. Spec.,Vol.1,Sec.1.02
Vol1.,Sec.1.02 Proportion of dry mix mortar, as per
3.2 Mortar Dry Mix Visual Arc.Spec., P - S Checklist
Approved method specifications and mix thoroughly
statement (P088-AT
Mixing shall be carried out by means of a
3.3 Mortar Mixing Visual P - S Checklist
mechanical batching mixer

C-
Str. Spec., Vol.,Sec.
VA-CV-MDS-00004)
Visual Approved method The wall in any direction shall be true to
3.4 Lines & levels P - S Checklist
Survey statement (P088-ATC-VA- place with intolerances in MS
CV-MDS-00004)

1 of 5 Form # 17028-Rev 1-Feb 04


Inspection & Test Plan: Document No. :ITP
ARABTEC CONSTRUCTION (L.L.C)
Procedure
Block Works Rev. No. :0
SAADIYAT BEACH RESORT Date

Type of Testing Requirement/ Acceptance Inspection Points Verifying / Control


Item No. Inspection Description Reference Document
Inspection Criteria ARABTEC ITA Consultant Data Forms
Block shall not be soaked before being
used and shall be free of
3.5 Block Preparation Visual P - S Checklist
smears,mortar,stains,cracks and broken
edges.
Approved method
statement (P088-AT The wall shall be kept level at all time.
No part to raise more than 1.2m above
3.6 Block Workmanship Visual another.Max raise height 1.5/day.Angle P - S Checklist
and reveal shall be kept true square and
C- plumb
VA-CV-MDS-00004)
3.7 Horizontal reinforcing Visual Every second course of block masonry P - S Checklist

Joint raked back 12 mm for full thickness


Str. Spec., Vol.,Sec.
of the joint to form key
Approved method
3.8 Joint Finishing Visual P - S Checklist
statement (P088-ATC-VA-
CV-MDS-00004)
for the plaster
Properly cured by sprinkling water on
Str. Spec., Vol.,Sec.,
damp
Str. Hessian
Spec., for a period of not less
Vol.,Sec.
3.9 Curing Visual Approved method P - S Checklist
than 7 days after completion of laying
Statement
course

Inspection of first block course layout to proceed work Str. Spec., Vol.,Sec.
Visual & Approved method
3.10 Approved method statement H - H Checklist & WIR
Survey statement (P088-ATC-VA-
Inspection of block work to proceed plastering CV-MDS-00004)

LEGEND : H-Hold point, W-Witness Point, R- Review Documents only, ARABTEC - Arabtec Construction (L.L.C)
S-Surveillance Inspection, P-Progressive Inspection ITA (P088-ATC-VA-CV-MDS-00004)
- Independent Testing Agency
WIR - Work Inspection Request

2 of 5 Form # 17028-Rev 1-Feb 04


Document No.:00
Arabtec Construction (LLC) Rev.:00
Inspection & Test Plan Date:

Block Works Page:1 of 3

SAADIYAT BEACH RESORT

P088

INSPECTION AND TEST PLAN

Block Works

ITP / 0
Document No.:00
Arabtec Construction (LLC) Rev.:00
Inspection & Test Plan Date:
Block Works Page:2 of 3

Revision
revision No. Date Prepared By Reviewed By Approved By
Description

0 For Approval