:ITP
ARABTEC CONSTRUCTION (L.L.C)
Procedure
Block Works Rev. No. :0
SAADIYAT BEACH RESORT Date
2.0 Materials
MARs. Test
certificates, Supplier
2.1 Materials approvals and conformity of delivered materials Review Arc.,Spec., Vol.1,Sec.1.01-5 R Test R
documents, Delivery
notes
C-
Str. Spec., Vol.,Sec.
VA-CV-MDS-00004)
Visual Approved method The wall in any direction shall be true to
3.4 Lines & levels P - S Checklist
Survey statement (P088-ATC-VA- place with intolerances in MS
CV-MDS-00004)
Inspection of first block course layout to proceed work Str. Spec., Vol.,Sec.
Visual & Approved method
3.10 Approved method statement H - H Checklist & WIR
Survey statement (P088-ATC-VA-
Inspection of block work to proceed plastering CV-MDS-00004)
LEGEND : H-Hold point, W-Witness Point, R- Review Documents only, ARABTEC - Arabtec Construction (L.L.C)
S-Surveillance Inspection, P-Progressive Inspection ITA (P088-ATC-VA-CV-MDS-00004)
- Independent Testing Agency
WIR - Work Inspection Request
P088
Block Works
ITP / 0
Document No.:00
Arabtec Construction (LLC) Rev.:00
Inspection & Test Plan Date:
Block Works Page:2 of 3
Revision
revision No. Date Prepared By Reviewed By Approved By
Description
0 For Approval