II. UPDATES AND STATUS OF THE N1 SEGMENT CP01, CP02 AND CP05
- Mr. Jay Calagos, DOTr Team Lead of N1 Segment presented the following:
DHSUD Building, Kalayaan Avenue corner Mayaman Street, Diliman, Quezon City
Tel. no. (02) 8424-4070 | 0961-137-0196 | 0916-674-14431
revised to toy library as amenities
inside the Disiplina Village
CP02 MOA with LGU 9 ISFs Php 4,674,996.00
Guiguinto
CP05 MOA with NHA (On Going for 847 ISF) 1, 106, 605,598.87
(for final approval)
3. RELOCATION STATUS:
- In terms of Relocation, Contract Package 01 and Contract Package 02 is 100%
completed. While in terms of Structure, they have remaining structure for actual
obstruction.
- In Manila, of the total 157 affected Informal Settlers Families (ISF), 57 were
relocated to Camarin Residences. (2 ISFs from Barangay 199, 46 ISFs from
Barangay 184 and 9 ISFs from Barangay 186). In terms of structures, a total of
54 structures were demolished (24 Structures from Barangay 199, 7 structures
from Barangay 200, 19 structures from Barangay 184, and 4 structures from
Barangay 186. There are 7 remaining erected structures subject to demolition
and 2 newly erected structures in the alignment already cleared by DOTr.
4. TIMELINE:
5. ENTITLEMENTS:
- For the Entitlements of DOTr, 57 ISFs in Manila received a full entitlement breakdown
as follows:
Entitlement Amount
Food Assistance Php. 2,250.00
Inconvenience Allowance Php. 10,000.00
Transportation Allowance of the Php. 15,000.00
- 6 Head of the Family ISFS
Transportation Allowance of the Php. 5,000.00
Member of the Family
TOTAL Php. 32, 250.00
Disqualified but provided inconvenience allowance amounting to Php 10, 000.
6. LIVELIHOOD:
- As of May 2023, A total of 238 ISFs beneficiaries with 46 PAPs have been provided
with livelihood training.
- Pending Livelihood implementation of National Housing Authority and will conduct the
livelihood program on 3rd Quarter of 2023.
-
7. ASSISTANCE REQUESTED FROM MUSO:
1. PROJECT OVERVIEW:
- As of
January 2023
Activity Timeline
Detailed Design Phase 2018-2019
4. PROJECT ENTITLEMENTS:
- Compensation and Entitlements
Cash Compensation for Loss of Land
Cash Compensation for Structure (Explored as Subsidy to the Socialized
Housing)
Reconnection of Utilities
Transportation to Relocation
Food Allowance during Relocation
Socialized Housing of Public Rental Facility
Participation in the LRIP
Rental Subsidy for Temporary Shelter
Cash Compensation for Crops and Trees
Allowance for Costs Associated with Moving Aquaculture Stock
Inconvenience Allowance
5. ASSISTANCE REQUESTED FROM MUSO
- According to the initial discussion between NHMFC and DOTr, NHMFC owns only
the structure, while the lot is owned by PNR. The beneficiaries have a Lease Contract
Agreement with both NHMFC and PNR. However, concerning the housing project of
NHMFC, the beneficiaries’ lease contract agreement expired in 2021. NHMFC
believes that DOTr should have consulted with them regarding the compensation and
entitlements for the structure. However, DOTr requires clarification on how to
approach beneficiaries who have fully paid and those who are not yet fully paid.
IV. Updates and Status of the Line 2 West Extension (L2WE) Project:
- Line 2 West Extension Project is a 3.01 km (South Bound Alignment) with three (3)
additional stations (Tutuban, Divisoria and Pier 4).
- In
2020,
it
was identified that the L2 West Ext. project will have an interface issue with the two
(2) TRB-DPWH Projects namely (a) Harbor Link Extension (HLE); and (b) Metro
Manila Skyway Stage 3 Extension Project (MMSS3 Project). Consequently, the L2
West Extension Project was realigned to the Southbound Side of Mel Lopez Blvd,
thus encroaching the Philippine Ports Authority (PPA) Property.
- To date, the Project Interface issue was resolved last May 2023 consequently, the
DOTr and LRTA-PMO is ongoing with the finalization of the conceptual alignment
prior to the Design and Build (DB) Procurement.
- In Barangay 20, ISFs located near the PPA Zaragoza Gate, for identification (upon
finalization of alignment)
- In Barangay 12, ISFs located near the Delpan St., corner Recto Avenue, for
identification (upon finalization of alignment)
- DOTr to prepare Letter of Commitments with timeline to the NHA to prioritize the
relocation of 47 PAFs from Barangays 159, 155 & 164, which is included in the Meralco
Utility Corridor.
- MUSO committed to expediting the approval of the E.O. for the creation of Unified LIAC
for all DOTr projects in Manila.
- Atty. De Guzman, MUSO Head will appoint an Area Coordinator to handle the
coordination efforts with all DOTr projects.
- DHSUD-RIC-PMO will invite PNR & MUSO for a coordination meeting with regards to the
concerns in Dagupan Extension (PNR Property) EO 48.
- DOTr will invite DHSUD RIC- PMO for the next meeting with NHMFC with regards to the
issue on BLISS property.
- LRTA asked for assistance from Manila LGU on the Ground Marking Activity on June
2023 for LRT Line 2 West Extension Project (if the approval of alignment will pursue.
- DHSUD-RIC-PMO will send a soft copy of EO to MUSO.
Prepared by:
MA. JOCELYN B. ELPIDES
Project Monitoring and Evaluation Officer II
Reviewed by:
Approved by:
PHOTO DOCUMENTATION: