Implementation Plan
Validation Activity
Zapote III - 338 (Team A & B) May 6-10, 2024
Talaba II - 335 (Team C& D)
Niyog - 4 (do)
Call Back May 11-12, 2024
Posting of Names per Barangay and Correction May 13-17, 2024
Data Management and Endorsement to BSAAC May 20-22, 2024
LIAC Meeting - Result of Validation and Socio Eco
Profile - Invite General Trias May 23, 2024
BSAAC Deliberation 4th week
Endorsement of Qualified beneficiaries to NHA
for pre-Qualification
Walkthrough
Zapote III - 338 (Team A & B)
Talaba II - 335 (Team C& D)
Niyog - 4 (do) April 23, 2024
Relocation
Letter to DOTr May-04
JUNE JULY AUG SEPT OCT
1st week
2nd week
2nd week
3rd week
1st Batch - 60 HHs
2nd Batch - 60 HHs
4th week
3rd Batch - 60 HHs
4th Batch - 60 HHs
NOV DEC
IMPLEMENTATION PLAN FOR THE RELOCATION AND RESETTLEMENT OF QUALIFIED INFORMAL SETTLERS
FAMILIES AFFECTED BY LRT LINE 1 SOUTH (CAVITE) EXTENSION (L1CE) PROJECT
Validation Activity
Zapote III - 338 (Team A & B) May 6-10, 2024
Talaba II - 335 (Team C& D)
Niyog - 4 (do)
Call Back May 11-12, 2024
Posting of Names per Barangay and Correction May 13-17, 2024
Data Management and Endorsement to BSAAC May 20-22, 2024
LIAC Meeting
- Result of Validation and Socio Eco Profile (Invite the receiving LGU) May 23, 2024
Php. 19,250.00
Financial Assistance:
240 (HHs) X Php. 18,000 (financial assistance)
= Php. 4, 320,000.00
= Php. 54,000.00
AUGUST
Grocery Package:
60 (HHs) X 4 (Batches) = 240 (HH)
240 (HHs) X php. 2,000 ( worth of grocery package)
= Php. 480,000.00
Financial Assistance:
240 (HHs) X Php. 18,000 (financial assistance)
1st week = Php. 4, 320,000.00
1st Batch - 60 HHs
2nd Batch - 60 HHs Transportation:
Relocation
3rd week Truck and Vans
3rd Batch - 60 HHs 33 Vans = Php. 6,600,000.00
4th Batch - 60 HHs 27 Buses = Php. 4,050.000.00
= Php. 10,650,000.00
= Php. 54,000.00
SEPTEMBER
Grocery Package:
66 (HHs) X 3 (Batches) = 198 (HH)
198 (HHs) X php. 2,000 ( worth of grocery package)
= Php. 396,000.00
Financial Assistance:
198 (HHs) X Php. 18,000 (financial assistance)
= Php. 3, 564,000.00
1st week:
1st Batch - 60 HHs
2nd Batch - 60 HHs Transportation:
Relocation
3rd week : Truck and Vans
3rd Batch - 60 HHs 30 Vans = Php. 6,600,000.00
4th Batch - 60 HHs 27 Buses = Php. 4,050.000.00
= Php. 10,650,000.00
= Php. 54,000.00
ACTIVITIES DATE
APRIL
Validation Activity
Zapote III - 338 (Team A & B) May 6-10, 2024
Talaba II - 335 (Team C& D)
Niyog - 4 (do)
Call Back May 11-12, 2024
Posting of Names per Barangay and Correction May 13-17, 2024
Data Management and Endorsement to BSAAC May 20-22, 2024
LIAC Meeting
- Result of Validation and Socio Eco Profile (Invite the receiving LGU) May 23, 2024
3rd week:
1st Batch - 60 HHs
2nd Batch - 60 HHs
Relocation
4th week :
3rd Batch - 60 HHs
4th Batch - 60 HHs
AUGUST
1st week
1st Batch - 60 HHs
2nd Batch - 60 HHs
Relocation
3rd week
3rd Batch - 60 HHs
4th Batch - 60 HHs
SEPTEMBER
1st week:
1st Batch - 60 HHs
2nd Batch - 60 HHs
Relocation
3rd week :
3rd Batch - 60 HHs
4th Batch - 60 HHs
BUDGET
php. 24,000.00
Php. 19,250.00
Php. 19,250.00
Php. 550.00 X 30 pax = Php. 16,500 X 5 (days)
= Php. 82, 500.00
Grocery Package:
60 (HHs) X 4 (Batches) = 240 (HH)
240 (HHs) X php. 2,000 ( worth of grocery package)
= Php. 480,000.00
Financial Assistance:
240 (HHs) X Php. 18,000 (financial assistance)
= Php. 4, 320,000.00
Transportation:
Truck and Vans
33 Vans = Php. 6,600,000.00
27 Buses = Php. 4,050.000.00
= Php. 10,650,000.00
= Php. 54,000.00
Grocery Package:
60 (HHs) X 4 (Batches) = 240 (HH)
240 (HHs) X php. 2,000 ( worth of grocery package)
= Php. 480,000.00
Financial Assistance:
240 (HHs) X Php. 18,000 (financial assistance)
= Php. 4, 320,000.00
Transportation:
Truck and Vans
33 Vans = Php. 6,600,000.00
27 Buses = Php. 4,050.000.00
= Php. 10,650,000.00
= Php. 54,000.00
Grocery Package:
66 (HHs) X 3 (Batches) = 198 (HH)
198 (HHs) X php. 2,000 ( worth of grocery package)
= Php. 396,000.00
Financial Assistance:
198 (HHs) X Php. 18,000 (financial assistance)
= Php. 3, 564,000.00
Transportation:
Truck and Vans
30 Vans = Php. 6,600,000.00
27 Buses = Php. 4,050.000.00
= Php. 10,650,000.00