You are on page 1of 66

Technical

Publications

sm 2401594--100
Revision 2

Proteus XRe
sm
Service Manual

do not duplicate

CopyrightE 2004 by General Electric Co.


WARNING

THIS EQUIPMENT IS DANGEROUS TO BOTH PATIENT AND OPERATOR


UNLESS MEASURES OF PROTECTION ARE STRICTLY OBSERVED
Though this equipment is built to the highest standards of electrical and mechanical safety, the useful radiation
beam becomes a source of danger in the hands of the unauthorized or unqualified operator. Excessive
exposure to radiation causes damage to human tissue.
Therefore, adequate precautions must be taken to prevent unauthorized or unqualified persons from
operating this equipment or exposing themselves or others to its radiation.
Before operation, persons qualified and authorized to operate this equipment should be familiar with the
Recommendations of the International Commission on Radiological Protection, contained in Annals Number
60 of the ICRP, with applicable National Standards, and should have been trained in use of the equipment.

ENVIRONMENTAL STATEMENT
ON THE LIFE CYCLE OF THE EQUIPMENT OR SYSTEM

This equipment or system contains environmentally dangerous components and materials (such as PCB‘s,
electronic components, used dielectric oil, lead, batteries etc.) which, once the life-cycle of the equipment or
system comes to an end, becomes dangerous and need to be considered as harmful waste according to the
international, domestic and local regulations.
The manufacturer recommends to contact an authorized representative of the manufacturer or an authorized
waste management company once the life-cycle of the equipment or system comes to an end to remove this
equipment or system.

--- MEDICAL EQUIPMENT ---


WITH RESPECT TO ELECTRIC SHOCK,
FIRE AND MECHANICAL HAZARDS
ONLY IN ACCORDANCE WITH
UL 60601---1, CAN/CSA C22.2 NO.601.1
<14NN>
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

REVISION HISTORY

REV DATE REASON FOR CHANGE

1 NOV 23, 2004 First edition.

2 OCT 25, 2005 Updated Schematics.

This Document is the English original version, edited and supplied by the manufacturer.

ADVISORY SYMBOLS

The following advisory symbols will be used throughout this manual.

DANGERS ADVISE OF CONDITIONS OR SITUATIONS THAT


IF NOT HEEDED OR AVOIDED WILL CAUSE SERIOUS
PERSONAL INJURY OR DEATH.

ADVISE OF CONDITIONS OR SITUATIONS THAT IF NOT


HEEDED OR AVOIDED COULD CAUSE SERIOUS PERSONAL
INJURY, OR CATASTROPHIC DAMAGE OF EQUIPMENT OR
DATA.

Advise of conditions or situations that if not heeded or


avoided could cause personal injury or damage to equipment
or data.

Note . Alert readers to pertinent facts and conditions. Notes represent


information that is important to know but which do not necessarily
relate to possible injury or damage to equipment.

3
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

SAFETY SYMBOLS

The following safety symbols will be used in the equipment.

Attention, consult accompanying documents.

Ionizing radiation.

Type B equipment.

Dangerous voltage.

Ground.

This symbol indicates that the waste of electrical and


electronic equipment must not be disposed as unsorted
municipal waste and must be collected separately. Please
contact an authorized representative of the manufacturer or
an authorized waste management company for information
concerning the decommissioning of your equipment.

4
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

TABLE OF CONTENTS

Section Page

1 PRE-INSTALLATION CHECKS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7

2 UNPACKING . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15

3 INSTALLATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17

3.1 Tools . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17

3.2 Installation Tips . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17

3.3 Sliding Column Assembly . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18

3.4 Radiographic Table . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22

3.5 Wall Bucky Stand / Wall Support Stand Assembly . . . . . . . . . . . . . . . . . . . . . . . 23

3.6 Installation of Undertable Generator (option) . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25

3.7 Interconnection Cables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25


3.7.1 Cables from Sliding Column . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
3.7.2 Cables from Radiographic Table . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
3.7.3 Cables from Bucky . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28

4 FINAL INSTALLATION AND CHECKS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29

4.1 Sliding Column . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29

4.2 Cable Fastening and Covers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30

1
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

Section Page

5 ADJUSTMENTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31

5.1 Adjustment Tools . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31

5.2 Alignment of X-ray Beam . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31


5.2.1 Alignment of Light Field with X-ray Field . . . . . . . . . . . . . . . . . . . . . . . . . 34
5.2.2 Perpendicularity Adjustment of X-ray Beam with Image Receptor . . . 36
5.2.3 Centering of X-ray Field and Image Receptor Bucky Assembly . . . . . 39
5.3 Alignment of X-ray field with the Wall Bucky Stand . . . . . . . . . . . . . . . . . . . . . . 40

5.4 Field Size Indicator Test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41

5.5 Collimator Lamp Brightness Test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 42


5.5.1 Collimator Light Field Intensity . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 42
5.5.2 Collimator Light Field Contrast Ratio . . . . . . . . . . . . . . . . . . . . . . . . . . . . 44

6 PERIODIC MAINTENANCE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 47

6.1 Checking of the Radiographic Table . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 47

6.2 Checking of the Floor Mounted Tube-Stand . . . . . . . . . . . . . . . . . . . . . . . . . . . . 48

6.3 Checking of the Vertical Bucky . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 48

7 RENEWAL PARTS OF THE RAD ROOM . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 49

8 SYSTEM INTERCONNECTION MAPS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 53

2
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

SECTION 1 PRE-INSTALLATION CHECKS

Prior to beginning installation, it is recommended to inspect the site and verify


that the X-ray room complies with the following Pre-installation requirements for
the X-ray System.

• High Voltage cables Standard length: 9 meters.

• Optional High Voltage Cables 12 meters and 16 meters.

FLOOR, WALL AND RACEWAYS FOR EQUIPMENT INSTALLATION

• Surface 4 x 2 meters (13 x 6.5 ft).

• Height 2.6 meters (8.5 ft).

POWER LINE REQUIREMENTS

Power Line for System is supplied from the Generator.

• SLIDING COLUMN

Power Line for Collimator Lamp . . . . 24 VAC, 6.5 A


50 / 60 Hz

Power Line for Locks . . . . . . . . . . . . . . 24 VDC, 100 W

• RADIOGRAPHIC TABLE

Power Line for Bucky . . . . . . . . . . . . . 110 -- 230 VAC,


500 VA (minimum input)
50 / 60 Hz

Power Line for Locks . . . . . . . . . . . . . . 24 VDC, 50 W

• WALL BUCKY STAND

Power Line for Bucky . . . . . . . . . . . . . 110 -- 230 VAC,


500 VA (minimum input)
50 / 60 Hz

Power Line for Locks . . . . . . . . . . . . . . 24 VDC, 48 W

• WALL SUPPORT STAND

Power Line for optional Bucky . . . . . . 110 -- 230 VAC,


500 VA (minimum input)
50 / 60 Hz

Power Line for Locks . . . . . . . . . . . . . . Not applicable

7
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

DIMENSIONS AND WEIGHT

• SLIDING COLUMN

Height . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2318 mm
Width . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1090 mm
Length . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2000 mm
Length with additional rail . . . . . . . . . . . . . . . 3000 mm

Weight . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 224 kg

Height from vertical axis of X-Ray Tube


facing the Wall Bucky or Wall Stand
Minimum height . . . . . . . . . . . . . . . . . . 400 mm
Maximum height . . . . . . . . . . . . . . . . . 1900 mm

SID from Horizontal axis of X-Ray Tube


facing the Wall Bucky or Wall Stand
Minimum SID . . . . . . . . . . . . . . . . . . . . 1000 mm
Maximum SID . . . . . . . . . . . . . . . . . . . 2480 mm

Column longitudinal motion . . . . . . . . . . . . . . 1480 m

Telescopic motion of Tube-Collimator Assembly 300 mm

Rotation of Tube-Collimator Assembly with respect


to its transverse axis (Rotation may be limited by cables) ±180o

Rotation of Column with respect to its vertical


axis (Rotation may be limited by cables) . . . . . . . . ±90o

• RADIOGRAPHIC TABLE

Height . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 775 mm
Width . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2000 mm
Length . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 725 mm

Weight . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 80 kg

Dimensions of Floating Table-Top . . . . . . . . 2000 x 725 mm

Table-Top / Film distance . . . . . . . . . . . . . . . 94 mm

Table-Top Attenuation . . . . . . . . . . . . . . . . . . <1.0 mm Al eq.

Longitudinal travel of Table-Top . . . . . . . . . . 600 mm

Transverse travel of Table-Top . . . . . . . . . . . 170 mm

Longitudinal travel of Bucky . . . . . . . . . . . . . 430 mm

Grid . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 40 lines/cm -- 12:1

Cassettes sizes . . . . . . . . . . . . . . . . . . . . . . . from 18 to 43 cm

8
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

• WALL BUCKY STAND / WALL SUPPORT STAND

Height . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2235 mm
Width . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 622 mm
Length . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 345 mm

Weight . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 145 kg

Dimensions of Bucky Assembly . . . . . . . . . . 622 x 577 mm

Table-Top / Film distance . . . . . . . . . . . . . . . . 44 mm

Table-Top Attenuation . . . . . . . . . . . . . . . . . . <0.8 mm Al eq.

Height from horizontal axis of film


Minimum height . . . . . . . . . . . . . . . . . . 400 mm
Maximum height . . . . . . . . . . . . . . . . . 1900 mm

Bucky Vertical Travel .................. 1500 mm

Grid . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 40 lines/cm -- 12:1

Cassettes sizes . . . . . . . . . . . . . . . . . . . . . . . from 18 to 43 cm

• HIGH VOLTAGE CABLES

High Voltage Cables -- Standard length . . . 9m

High Voltage Cables -- Optional length . . . 12 m or 16 m

9
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

Illustration 1
Dimensions for Installation (Non telescopic Arm)

100
1000 Max.

1231
800

10
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

Illustration 2
Dimensions for Installation (Telescopic Arm)

100
1425
800

11
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

Illustration 3
Drilling Template

Rooms with optional Telescopic Arm


Distances in brackets correspond to
(1091)

(1215)

(885)

(942)

12
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

Illustration 4
Cabling and Room Raceways suggestions

For 9 m High Voltage Cables, install a cable hook on the wall and
position the generator as close as possible to the Column base

Cable Hook

Generator Upper
Cable Entrance

GENERATOR
CABINET

13
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

Illustration 4 (cont.)
Cabling and Room Raceways suggestions

SURFACE RACEWAYS SUGGESTION

GENERATOR
CABINET

Table Base

To Console
Surface Cable Raceways

Suggested Raceways dimensions


50

100

UNDERFLOOR RACEWAYS SUGGESTION

GENERATOR
CABINET

Table Base
To Console

Cable Entrance
(All the Table Base Area can be used for Cable Entrance except when the Generator is installed undertable)
Underfloor Cable Raceways

Dimension of suggested Cable Entrances and Underfloor Raceways


100

100

14
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

SECTION 2 UNPACKING

The system is shipped in different crates to facilitate transport and installation.


Upon receipt of the equipments, inspect all shipping crates for signs of damage.
If damage is found, notify carrier or his agent immediately.

1. Place crates close to its final location at room and remove each wood
package part. Do not discard any packing material (envelopes, boxes,
bags) until all parts are identified and listed in the packing list.

AT LEAST TWO/THREE PEOPLE ARE REQUIRED TO


REMOVE ALL HEAVY COMPONENTS FROM THE SHIPPING
PALLET.

2. When the equipment is unpacked, check part numbers and serial


numbers of each component in the identification labels. Inspect all
pieces for visible damages. If any damaged part is found, repair it or
order a replacement to prevent unnecessary delay in installation.

3. Verify that all items on the customer order are present.

4. Leave a free working area around equipment until installation is


complete.

15
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

This page intentionally left blank.

16
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

SECTION 3 INSTALLATION

Note . Follow Installation sequence process as described. At least two or


three people are required for the following tasks.

3.1 TOOLS

Tools required for Installation:

• Standard service engineers tool kit.

• Standard and extended levels (1 meter for Column Base).

• Electric drill motor and assorted bits.

3.2 INSTALLATION TIPS

The following advices are to be taken in a common installation, as every room


has it own characteristics and options, please plan the room distribution before
starting the installation.

• For Column Base positioning, a good reference is 1144 mm distance


from the wall where the Wall Bucky Stand is installed to the first drilling
hole of the Column Base. Otherwise keep in mind the length of the Wall
Spacer or Support to increase the reference distance. (Refer to
Illustration 3 ).

• The minimum distance from the Column Base to its parallel wall is
variable depending on the room size.

• For Wall Bucky/ Wall Support positioning, a good reference is to


install it at 1021 mm from the transverse axis of the Wall Bucky to the
Column Base Back Wall for Non Telescopic Column Arm, (Refer to
Illustration 3) and 1215 mm for Telescopic Column Arm (Refer to
Illustration 3).

• For Table positioning, a good reference is to install it at 748 mm from


the longitudinal Axis of the Table Bucky to the Column Base Back Wall
for Non Telescopic Column Arm, (Refer to Illustration 3) and 942 mm for
Telescopic Column Arm (Refer to Illustration 3).

17
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

3.3 SLIDING COLUMN ASSEMBLY

1. Position the Column Base on the floor according to the RAD Room plan
distribution. Keep in mind the dimensions and final position of each
component in the System (Column, Wall Bucky, Table, etc.).

The Column Base has to be placed with the Brake Track at the rear side
and perpendicular to the wall where the Vertical Bucky will be installed.

2. Mark the position of the ten (10) anchoring holes on the floor. Move the
Base and drill the anchoring holes. Bolts and hardware are field
provided.

3. Check the leveling in different points on the Base and adjust it by using
leveling plates. Anchor slightly the Base to the floor.

4. Remove the Rail Stop from one of the Base laterals. Rail Stops can be
installed in the front or in the rear rails.

Illustration 5
Sliding Column Base

BRAKE TRACK

ANCHORING HOLES
BUCKY - COLUMN BASE LINK
(OPTIONAL)

COLUMN SCREWS COLUMN FOOT


BRAKES

COLUMN CARRIAGE

5. With the Column laid on the floor, remove the Upper Cap and Upper Front
Cover (both are secured with two screws). (Refer to Illustration 6).

6. Stand up the Column in line to the Column Base.

7. In order to ease the Column installation inside the Base, remove or loose
the Column Foot Brakes located at the rear side of the Column Foot.
(Refer to Illustration 5).

8. Slide carefully the Column into the Base.

18
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

Do not remove the Counterweight Safety Bar neither the two


Shipping Safety Screws close to the Vertical Carriage until
specifically instructed in this document.

Make sure that the iron cables are properly routed around the
pulleys before standing up the Column.

9. Re-install the Rail Stop in the lateral of the Base and the Column Foot
Brakes.

10. Level the Column vertically on both laterals and front side. Adjust it by
means of the leveling plates in the Column Base. Anchor tightly the Base
to the floor. (Refer to Illustration 6).

Illustration 6
Sliding Column Base
UPPER CAP

UPPER FRONT COVER

COUNTERWEIGHT SAFETY BAR

LEVELS

SHIPPING SAFETY SCREW

VERTICAL CARRIAGE

COLUMN FOOT
BASE

ANCHORING HOLES

19
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

11. Install the Tube-Collimator Support to the Column Arm (Coupling Plate)
by using the four screws mounted at the rear side of the Support (upper
and lower holes). The two rods will be used to level the Support when all
the components are assembled. Pass both cables (J1 and J2) in the Arm
through the window of the Support.

Illustration 7
Coupling of Tube-Collimator Support -- Rear View

COUPLING SCREWS

TUBE-COLLIMATOR SUPPORT LEVELING RODS

COUPLING PLATE OF COLUMN ARM

12. Install the Column Control Panel by using the two bolts in the rear side
of the Control Panel.

13. Carefully, remove the Collimator Adaptation Ring from the Collimator.
Avoid the ring screws to fall down into the Collimator.

14. Install the X-ray Tube on its Support using the Collimator Adaptation Ring
and its four Security Screws (Allen).

Illustration 8
X-ray Tube, Collimator and Control Panel

X-RAY TUBE CONTROL PANEL

COLLIMATOR

COLLIMATOR ADAPTATION RING

20
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

15. Before installing the Collimator, unscrew the same number of turns the
four Centering Adjustment and Security Screws (Allen) to allow the
Collimator installation in the Collimator Adaptation Ring. Adjust the
Collimator Blades to their widest setting and carefully install the
Collimator centering it with the X-ray Tube window.

Tighten carefully the four Centering Adjustment and Security Screws


(Allen) equally (same number of turns) until Collimator is centered and
held firmly on the Collimator Adaptation Ring (support). (Also, refer to
Collimator Manual).

16. Level horizontally the Tube-Collimator Assembly on the Tube and the
Collimator base. Adjust the level by using the two rods in the rear side
of the Coupling Plate (Arm).

17. Remove the Counterweight Safety Bar (upper front of Column) and the
two Shipping Safety screws close to the Vertical Carriage. The weight
of the Counterweight is equal or slightly greater than the weight of the
Carriage + Arm + Tube + Collimator + Control Panel. It is factory
adjusted.

18. Install the Upper Front Cover and then the Upper Cap (both are secured
with two screws). Install the Foot Cover of the Column pushing it.

Illustration 9
Tube Support Arm Leveling
UPPER CAP

UPPER FRONT COVER


COUNTERWEIGHT SAFETY BAR

SHIPPING SAFETY SCREW LEVEL

LEVELING RODS

VERTICAL CARRIAGE LEVEL

21
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

3.4 RADIOGRAPHIC TABLE

1. Remove the transport screws that secure the Radiographic Table to the
pallet and move away the Table.

2. Remove the front cover screws of the Table in order to access inside the
table.

3. Power ON the Collimator Lamp and align perfectly the Bucky axes with
the Collimator light beam. During alignment, place the Tube-Collimator
Assembly and the Bucky Carriage at different positions to check that it
is correctly aligned.

4. Mark the four anchoring holes on the floor, shift the table and perform the
holes (diam 9).

ANCHORING HOLES

5. Level the Table and anchor the Table to the floor.

6. Connect a line from Generator TS1 +24VDC, --24VDC and Ground to the
Table Terminal as per schematics 54302065.

7. Connect the Table Bucky Cables as per Bucky schematics. The Bucky
ground cable (yellow/green) must be connected to the Generator ground
point.

8. Optional -- Install the Bucky link part to the rear of the Bucky assembly
(6 allen screws).

ALLEN SCREWS

9. Install the four Table-top bumpers provided at four corners of the table.

22
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

10. Install Table-Top, remove first the allen screws located at both sides for
the Table-Top carriage and slide the assembly, then reinstall the removed
screws.

11. Guide cables through table rear outlet and reinstall front cover.

3.5 WALL BUCKY STAND / WALL SUPPORT STAND ASSEMBLY

1. Place the Wall Bucky Stand in Vertical position.

2. Remove the Security Screws of Counterweights and Carriage Rails of


the Column. For this operation it is advisable a person pushes the Bucky
Assembly downwards to ease the screws removing.

Illustration 10
Wall Bucky Stand

ANCHORING HOLES COUNTERWEIGHT SAFETY BAR UPPER CAP

UPPER FRONT COVER


LEVELS

SHIPPING SAFETY SCREW

VERTICAL CARRIAGE

BASE

ANCHORING HOLES

23
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

3. Decide wether installing the wall anchors with the supplied Small
Spacers, Wall Support or nothing to separate the Wall Bucky Stand from
the wall.

4. At least, mark in the wall two of the upper anchoring holes of the Column
and mark the two anchoring holes on the floor.

5. Take away the Column and prepare its anchors.

Illustration 11
Wall Bucky Stand -- Anchoring Holes and Dimensions

FLOOR CABLE ENTRANCE

24
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

6. Position the Column and secure it to the floor and wall. Check that it is
properly leveled in both laterals and front side. Use the leveling plates
provided to raise and level the Column previous to secure it definitively.
(Refer to Illustration 10).

Note . In case that a Spacer or Wall Support are used, separate the
Column from the wall and assemble the Spacer or Wall Support
at the upper part of the column before marking the anchoring holes
in the wall.

7. Install the Upper Front Cover and then the Upper Cap (both are secured
with two screws). Install the Foot Cover of the Column pushing it.

8. Route the cables along the room to the Generator for their later
connection.

Some safety devices such as Safety Switch / Emergency Switch, Warning


Light, and Door Interlock Switch are supplied and installed by the customer.
Verify that safety devices have been properly installed and routed during the
Pre-Installation procedure.

3.6 INSTALLATION OF UNDERTABLE GENERATOR (OPTION)

Follow steps below for Generator installation in Undertable position.

1. Remove the Table front cover. For that unscrew the four cover screws
located at upper and lower front cover.

FRONT COVER SCREWS

2. Disconnect ground cable from front cover and take out the front cover.

3. Disconnect the three faston terminals of the microswitch SW1 located


inside the table base.

25
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

4. Remove 2 + 2 allen screws of the pedal assembly located at both sides


of the table base, and pull out the pedal assembly.

MICROSWITCH SW1

PEDAL ASSEMBLY SCREWS

5. Place the Generator Cabinet (without covers) on its carriage in front of


the table. Usually, this component is freestanding below the table.
Seismic areas and other conditions require to secure the Generator
Cabinet to the floor through the mounting holes on the bottom.

GENERATOR CARRIAGE

Note . Do not slide the Generator under the table until Configuration and
Calibration procedures are completed. Refer to Generator service
Manual.

6. Push the Generator inside the table.

7. Reassemble in reverse order after performing the configuration and


calibration processes of the Generator.

26
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

3.7 INTERCONNECTION CABLES

3.7.1 CABLES FROM SLIDING COLUMN

1. Connect the Lock cables from the Vertical Carriage (J1-J1) and from the
Column Control Panel (J2-J2) located close to the Tube-Collimator
Support (refer to Interconnection Map IM 341).

2. Connect the Collimator Lamp (if it has not been connected before).

3. Route all cables from the Collimator and X-ray Tube along to the Arm and
secure with the metallic Clamp over the Arm.

CABLES CLAMP

4. Ground cables should be connected to the main GND stud in the


Generator.

3.7.2 CABLES FROM RADIOGRAPHIC TABLE

1. Route and connect the Locks cables from the Table to the Terminal Block
TB7 of the Locks Board (on the Top of the Generator).

2. Cable from the Bucky is connected directly to the Terminal Block 3TS1
of the Generator Cabinet. (Refer to Interconnection Map IM 341).

3. Ground cable should be connected to the main GND stud in the


Generator.

27
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

3.7.3 CABLES FROM BUCKY

Cables from the Bucky are connected directly to the Terminal Block 3TS1 of the
Generator Cabinet. (Refer to IM 341 ).

Connect the Bucky as indicated in Section “System Interconnections”, and


check them before connecting the Ion Chambers (if applicable).

Note . To avoid noises which could cause exposure cutting and/or


console blocking, it is recommended to install on the Bucky
terminals the R-Cs supplied with the Generator (a bag with
resistors and capacitors) according to Bucky Interconnections
Maps (note-3).

If “Bucky Start” signal enter to the Bucky through an optocoupler,


do not add the supplied R2--C2 for the Bucky and remove resistors
R36 and R37 in the Interface Board.

28
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

SECTION 4 FINAL INSTALLATION AND CHECKS

4.1 SLIDING COLUMN

Install the Cable Support on the upper right/left side of the Column. Route and
Fasten all the cables to it by using strain reliefs.

TOP OF COLUMN

CABLE SUPPORT CABLE SUPPORT

Position the Sliding Column with the Tube-Collimator Assembly opposite the
Wall Bucky. Measure the SID with the Collimator Metric Tape and determine
the position where the Column has to stop when it reaches the required SID (1
m, 1.8 m, 2 m, etc.) respect to the Wall Bucky. Drill the Base and install the
Centering Plates where the Column has to stop. Adjust the Longitudinal Detent.
on the Column Foot.

Illustration 12
Centering Plate in Base

COLUMN FOOT
CAP OF DETENT

COLUMN BASE

CENTERING PLATE

LONGITUDINAL DETENT

29
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

4.2 CABLE FASTENING AND COVERS

Note . Before re-installing all cabinet covers, perform the rest of the
Calibration procedures if required.

Check that all electrical connections are firm and secure, and all cables are
correctly routed. Remove the ferrite blocks factory clamped to the cables when
it is required to carry out a correct routing, then re-install again the ferrites blocks
at the same place around cables. (Refer to Section 3.7)

In order to avoid signal interferences, it is strongly


recommended to fold and fasten close to Generator Cabinet
the portion of cables not routed (see picture below). Never
wrap in circles.

YES NO

Re-install the Cabinet covers and connect its internal ground wires. Power line,
High Voltage and Interconnections cables must go through the cover cable
outlet.

30
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

SECTION 5 ADJUSTMENTS

5.1 ADJUSTMENT TOOLS

The following special Tools have been used for adjustment of the Proteus XR/e
Plus X-ray System (these tools are not included with the System):

• Collimator Test Tool (Model RMI 161B9).

• Beam Alignment Test Tool (Model RMI 162A).

• SID Test Stand Tool (Inside Case: RMI Model 175).

• Light Meter (Standard).

5.2 ALIGNMENT OF X-RAY BEAM

1. Place the Tube-Collimator Assembly at 1 meter SID of the Horizontal


Bucky. Check with a level correct horizontal position of Tube-Collimator
Assembly and Table-Top.

2. Turn on Collimator light and center the Collimator in relation to the Bucky.
Horizontal and transverse position of the light axes projected by the
Collimator Lamp must be in line with the axes of the horizontal Bucky.

If needed, modify Collimator position by carefully unscrewing and


screwing the four Centering Adjustment and Safety Screws (Allen) of
Collimator.

Illustration 13
Collimator Screws
CENTERING ADJUSTMENT AND SAFETY SCREWS

31
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

3. Position the Collimator Test Tool (RMI model 161B) on the Table-Top.

4. Turn on Collimator light and by means of the Collimator Control Knobs,


center the Collimator Test Tool with the light axes projected by the
Collimator Lamp.

5. Adjust the Light Field of the Collimator Lamp to the rectangle drawn
inside the Collimator Test Tool.

6. Place centered the Beam Alignment Test Tool (RMI model 162A) on the
Collimator Test Tool .

Illustration 14
Alignment Test Tools

BEAM ALIGNMENT TEST TOOL -- RMA MODEL 162A

COLLIMATOR TEST TOOL -- RMA MODEL 161B

7. Load Cassette film Tray with cassette film 24x30 and insert it.

8. Make an exposure at 60 kVp / 5 mAs.

9. Process film and:

a. Check that the X-ray Field falls just within the image of the inner
rectangle of the Collimator Test Tool.

If an edge of the X-ray Field falls out of the inner rectangle means
a misalignment of the Light Field respect to the X-ray Field. The
maximum misalignment allowed is 2 % of SID (for SID 1m = 2 cm
tolerance).

Refer to Section 5.2.1 for alignment of Light Field with X-ray Field.

32
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

b. Check that the X-ray Beam is perpendicular to the plane of the


Image Receptor. If the Image receptor is parallel to the Table-Top,
the perpendicularity of the X-ray Beam can be checked using the
Beam Alignment Test Tool with the Collimator Test Tool.

Based on next illustration, the criteria for SID at 1 meter is:

-- If the image of the two balls overlap (A) the X-ray Beam is
perpendicular to within 0.5o.

-- If the image of the top ball (larger shadow) intercepts the first
circle (B), the X-ray Beam is about 1.5o away from the
perpendicular.

-- If the image of the top ball (larger shadow) intercepts the second
circle (C), the X-ray Beam is about 3o away from the perpendicular.

In cases (A) and (B) perpendicularity is within tolerance for SID at


1 meter (top ball is within or intercepting the first circle). The third
case (C) needs readjustment.

Refer to Section 5.2.2 for perpendicularity adjustment.

A B C

c. Check that the X-ray Beam is properly centered with the Image
Receptor. To determine the center of the Image Receptor, draw
diagonal lines from corner to corner of the X-ray Film. (Alternately,
the film can be folded in half and creased at the center). The two
lines will cross in the center of the Image Receptor (film). Then
draw diagonal lines from the corners of the imaged X-ray Field.

If the center of the X-ray Field and Image Receptor is the same,
the diagonals of both sets of lines should cross at the same point.
The maximum misalignment allowed is 2 % of SID (for SID 1m =
2 cm tolerance).

Refer to Section 5.2.3 for centering of X-ray Field and Image


Receptor.

33
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

5.2.1 ALIGNMENT OF LIGHT FIELD WITH X-RAY FIELD

1. Turn on Collimator light and place the Tube-Collimator Assembly


perfectly centered with the Horizontal Bucky (use the mark at Bucky Tray
Handle as reference for centering). Check with a level correct horizontal
position of Tube-Collimator Assembly and Table-Top.

2. Place SID at 1 meter.

3. Center the Collimator Test Tool (RMI model 161B) on the Table-Top with
the light axes projected by the Collimator Lamp.

COLLIMATOR TEST TOOL

4. Adjust the Light Field of the Collimator Lamp to the rectangle drawn
inside the Collimator Test Tool.

34
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

5. Check on the processed film the adjustment required to meet the Light
Field with the X-ray Field. Identify the deviation on the axes imaged on
the film.

PROCESSED FILM

COLLIMATED LIGHT FIELD

COLLIMATED X-RAY FIELD

LIGHT FIELD MISALIGNMENT

PROCESSED FILM

COLLIMATED LIGHT FIELD = COLLIMATED X-RAY FIELD

GOOD FIELDS ALIGNMENT

35
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

6. Do not remove the Collimator Test Tool from its original position and
adjust the Light Field by moving the Collimator Unit and/or the Collimator
Lamp.

a. Collimator Lamp must be ON during Light Field adjustment.

b. Modify Collimator position by carefully unscrewing and screwing


the four Centering Adjustment and Safety Screws (Allen) until the
Light Field coincides with the axes reference imaged (numbers
and dots) on the processed film.

Illustration 15
Collimator Screws

CENTERING ADJUSTMENT AND SAFETY SCREWS

c. If adjustment is still necessary, modify position of Collimator Lamp


(refer to Collimator Manual).

7. Repeat exposure and procedure until the result is satisfactory. The


maximum misalignment allowed is 2 % of SID (for SID 1m = 2 cm of
tolerance).

36
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

5.2.2 PERPENDICULARITY ADJUSTMENT OF X-RAY BEAM WITH IMAGE RECEPTOR

In case that perpendicularity is out of tolerance (top ball is out of first circle),
adjust perpendicularity as follows:

1. Place the Tube-Collimator Assembly perfectly centered with the


Horizontal Bucky (use the mark at Bucky Tray Handle as reference for
centering). Check with a level correct horizontal position of
Tube-Collimator Assembly and Table-Top.

2. Place SID at 1 meter.

3. Position the Collimator Test Tool (RMI model 161B) on the Table-Top.

4. Turn on Collimator light and by means of the Collimator Control Knobs,


center the Collimator Test Tool with the light axes projected by the
Collimator Lamp.

5. Place centered the Beam Alignment Test Tool (RMI model 162A) on the
Collimator Test Tool (fix the Test Tool with adhesive or another product).
Turn on Collimator light and observe if shadow of the Beam Alignment
Test Tool is projected in equal proportion around it.

6. Check on the processed film the adjustment required to center the top
ball mark. Shadow around the Beam Alignment Test Tool can also help
to make a first correction.

7. Loosen slightly the four Safety Screws (M6) at the rear side of the
Coupling Plate (Tube-Collimator Assembly). Then loosen or tighten the
two rods (Allen M5) to adjust horizontally the Tube-Collimator Assembly
with reference to the Horizontal Bucky. (Refer to Illustration 16).

If horizontal deviation is considerable, loose the two Safety Screws of the


Arm, perform the horizontal adjustment and tighten the two Safety
Screws again.

Vertical adjustment is not required because the Tube-Collimator


Assembly can be placed at any vertical position.

8. Repeat exposure and procedure until the result is satisfactory (top ball
must be inside of the first circle).

37
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

Illustration 16
Safety Screws and Rods for Perpendicularity Adjustment

SAFETY SCREWS (M6)

COUPLING PLATE

LEVELING RODS (M5)


ARM SAFETY SCREWS (ALLEN)

COUPLING PLATE OF COLUMN ARM

SAFETY SCREWS

TUBE-COLLIMATOR SUPPORT LEVELING RODS

38
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

5.2.3 CENTERING OF X-RAY FIELD AND IMAGE RECEPTOR BUCKY ASSEMBLY

The error between centers of the X-ray Field and the Image Receptor should
not be greater than 2% of the SID. (for SID 1m = 2 cm tolerance).

CENTER OF THE X--RAY FILM CENTER OF THE IMAGE

DEVIATION

If the deviation is greater than 2% of SID, perform the following procedure:

1. Check on the processed film the correction required for centering the
X-ray Field with the Image Receptor. Adjustments will be performed as
the same way described for Perpendicularity correction, so only re-adjust
it if really is necessary.

Centering adjustments may affect to perpendicularity


corrections.

2. Repeat exposure and check centering until the result is satisfactory


(centers position are within tolerance).

39
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

5.3 ALIGNMENT OF X-RAY BEAM WITH WALL BUCKY STAND

1. Wall Bucky Stand has to be properly positioned and aligned respect to


the Tube--Collimator Assembly in its central position.

2. Place the Tube--Collimator Assembly at 1 meter SID centered in front of


the Vertical Bucky. Check with a level correct vertical position of
Tube--Collimator Assembly and Bucky Table--Top.

3. Turn on Collimator light and center the Collimator in relation to the Bucky
Table--Top. Horizontal and transverse position of the light axes projected
by the Collimator Lamp must be in line with the axes or film sizes marked
on the Table--Top. Horizontal and vertical position of the light axes
projected by the Collimator Lamp must be in line with the horizontal and
vertical axes of the Table--Top. (Alignment can also be performed by
placing a mirror in the center of the Table--Top and checking the
Collimator light reflection). If needed, readjust position of the Wall Bucky
Stand.

4. Load Cassette film Tray with cassette film 24x30 and insert it.

5. Make an exposure at 60 kVp / 5 mAs.

6. Process film and check that the X--ray Beam is properly centered with the
Image Receptor. To determine the center of the Image Receptor, draw
diagonal lines from corner to corner of the X--ray film. (Alternately, the film
can be folded in half and creased at the center). The two lines will cross
in the center of the Image Receptor (film). Then draw diagonal lines from
the corners of the imaged X--ray Field.If the center of the X--ray Field
and Image Receptor is the same, the diagonals of both sets of lines
should cross at the same point. The maximum misalignment allowed is
2 % of SID (for SID 1m = 2 cm tolerance).

7. If the deviation is greater than 2 % of SID, correct position of the Wall


Bucky Stand adjusting its anchors at the wall and floor.

8. Repeat exposure and check centering until the result is satisfactory


(centers position are within tolerance).

40
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

5.4 FIELD SIZE INDICATOR TEST

Note . Before starting with the Field Size Indicator Test, the Alignment of
X-Ray Beam Test and the Alignment of Light Field with X-Ray Field
Test should be performed.

1. Place the Tube-Collimator Assembly perfectly centered with the


Horizontal Bucky (use the mark at Bucky Tray Handle as reference for
centering). Check with a level correct horizontal position of
Tube-Collimator Assembly and Table-Top.

2. Position SID at 1 meter.

3. Open the Collimator blades to set a Field Size of 24 x 30 cm for SID 1 m.

4. Turn on the Collimator Light and center the Collimator in relation to the
Horizontal Bucky. Horizontal and Transferral position of the light axes
projected by the Collimator Lamp must be in line with the axes of the
Horizontal Bucky.

5. Load on the Cassette Film Tray with a Cassette Film of 35 x 43 cm


centered and insert it.

6. Make an exposure at 60 kVp, 1 mAs.

7. Process film and check the following measurements known (refer to


Illustration 17):

a. Measure the length of the X-ray Field on the Processed Film


(identified as L)

b. Measure the width of the X-ray Field on the Processed Film


(Identified as W)

Illustration 17
X-ray Field Size

FILM 35x43 cm
WIDTH DIMENSION (W)

X-RAY FIELD SIZE ON THE FILM

PROCESSED FILM

LENTH DIMENSION (L)

41
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

8. With the measurements obtained and according to the field size


indication selected, the results should be:

G Length dimension (L) = 300 mm

G Width dimension (W) = 240 mm

9. The difference between the indicated Field Size and the obtained Field
Size may not exceed 1.5 % (rejection limit) of the SID in either direction.
Therefore the deviation in any direction should not be higher than 15 mm
(rejection limit) for SID at 1 meter.

10. If the deviation of Field Size Indication is out acceptance limits, it is


necessary to readjust the index of Collimator Blades Control Knobs. For
that, loosen each Collimator Control Knob and position it according to
deviation. Repeat the complete tests until the X-Ray Field Size selected
(24 x 30 cm) is obtained.

5.5 COLLIMATOR LAMP BRIGHTNESS TEST

5.5.1 COLLIMATOR LIGHT FIELD INTENSITY

1. Place the Tube-Collimator Assembly perfectly centered with the


Horizontal Bucky (use the mark at Bucky Tray Handle as reference for
centering). Check with a level correct horizontal position of
Tube-Collimator Assembly and Table-Top.

2. Position SID at 1 meter.

3. Open the Collimator Blades by means of Collimator Control Knobs and


set a Field Size of 25 x 25 cm for SID 1m.

4. Turn on the Collimator Light and center the Collimator in relation to the
Horizontal Bucky. Horizontal and transverse position of the light axes
projected by the Collimator Lamp must be in line with the axes of
Horizontal Bucky.

5. Place the Light Meter on the Table-Top with sensor directed toward the
Light Source.

42
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

6. Place the Light Meter in the center of one quadrant of the light field (refer
to Illustration 18).

Illustration 18
Light Meter on Table-Top

1st QUADRANT LIGHT SENSOR ON THE 2nd QUADRANT

4th QUADRANT
3rd QUADRANT

LIGHT FIELD
LIGHT METER

7. With Collimator Lamp OFF, measure and keep record of the ambient light
level.

8. Do not move the Light Meter. With the Collimator Lamp ON, measure and
keep record of light level of that quadrant.

9. Determine the light intensity of that quadrant by subtracting the ambient


light level from the corresponding light level.

10. Repeat measurements at the approximate center of remaining three


quadrants of light field.

11. With the measurements obtained on the step-10., the results of Light
Field Intensity in all quadrants should be higher of 170 lux
(16 foot-candles) and among all the quadrants the intensity light field
shall be not differ more than 10%.

12. The average illumination at a distance of 1 meter from the focal spot shall
not be less than 160 lux (15 foot-candles). Rejection limit is 170 lux
(16 foot-candles).

13. If the deviation of Light Field Intensity is out acceptance limits, it is


necessary to take into account the following:

a. If the difference of Light Field Intensity among all quadrants is


higher than 10%, we need to readjust the Collimator Lamp socket.
Refer to Collimator Manual.

43
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

b. If the light level in all quadrants is less than 170 lux, it is necessary
to check the following:

G The lamp voltage level when it is ON shall not be lower of


24VAC. (Measure on the Bulb socket contact).

G Check that the Collimator Lamp, the Mirror and the Mylar
window are not dirty or discolored.

G Check the correct position of the Mirror (Refer to Collimator


Manual).

c. If the light level is still low:

G Replace the Collimator Bulb.

G Replace the Collimator Bulb socket.

5.5.2 COLLIMATOR LIGHT FIELD CONTRAST RATIO

1. Place the Tube-Collimator Assembly perfectly centered with the


Horizontal Bucky (use the mark at Bucky Tray Handle as reference for
centering). Check with a level correct horizontal position of
Tube-Collimator Assembly and Table-Top.

2. Position SID at 1 meter.

3. Open the Collimator Blades to set a Field Size of 25 x 25 cm for SID 1m.

4. Turn ON the Collimator Light and center the Collimator in relation to the
Horizontal Bucky. Horizontal and transverse position of the light axes
projected by the Collimator Lamp must be in line with the axes of
Horizontal Bucky.

5. Place the Light Meter on the Table-Top with sensor directed toward Light
Source.

6. Place the Light Meter in the center of one quadrant of the light field. (Refer
to Illustration 19).

7. Minimize the room lighting. With the Collimator Lamp OFF, measure and
record the ambient light level.

44
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

8. Turn ON the Collimator Light. Measure the maximum illumination; this


should occur near the field center. Slide the light sensor along the
Table-Top, and locate the point where the illumination drops to a 75% of
the maximum. This point is defined by BRH as lying on the edge of the
Light Field (refer to Illustration 19). All subsequent measurements will be
referenced to this point and to this definition of “edge”.

Illustration 19
Light Contrast Calculation
EDGE OF A QUADRANT

LIGHT SENSOR ON THE LEFT EDGE LIGHT SENSOR ON THE RIGHT EDGE

BRH POINT
(LIGHT DROPS 25%)

9. Measure the illumination at a point 3 mm from the edge of the field toward
the center of the field (Light sensor on the left of edge). (Refer to
Illustration 19). Record this as I1.

10. Measure the illumination at a point 3 mm from the edge of the field away
from the center of the field (Light sensor on the right of edge). (Refer to
Illustration 19). Record this as I2.

11. Correct the values of I1 and I2 by subtracting from each value the ambient
light level measured in step-7. Now divide the corrected value of I1 by
I2. This ratio should be 4 or more.

12. Repeat the process from step-8. for all quadrants of Light Field.

13. If the deviation of Light Field Contrast Ratio is out acceptance limits, it is
necessary check the following:

G Check that the Collimator Lamp, the Mirror and the Mylar window
are not dirty or discolored.

G The Light Field Intensity level shall be higher of 170 lux.

G The ambient light level shall be low as it affects the accuracy of the
measurements.

45
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

This page intentionally left blank.

46
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

SECTION 6 PERIODIC MAINTENANCE

The first maintenance service is to be performed before the end of twelve


months after installation. The rest of maintenance services will be performed
according to the following table.

Table 1
Periodic Maintenance

Adjustment and
Cleaning Lubrication Functional Check
calibration

Tube--Collimator Assembly Yearly N/A Yearly Yearly

Radiographic Table Yearly Yearly Yearly Yearly

Floor Mounted Tube Stand Yearly Yearly Yearly Yearly

Vertical Bucky Yearly Yearly Yearly Yearly

Cleaning: Clean from dust or moist inner components as Electronic Racks,


grids, filters, bearings and rails.

Lubrication: Lubricate mobile components such as chains, guides, bearings


etc.

Functional Check: Perform a functional check of all Room equipment, motion


of Vertical Bucky, Table--top, Column travel, brakes, keys of consoles, lamps
and indicators, Collimator etc.

Adjustments and calibrations: Perform adjustments and Calibration of Table,


Column and Vertical Bucky.

6.1 CHECKING OF RADIOGRAPHIC TABLE

1. Turn OFF generator and mains. Check that there is not voltage at table.

2. Disassemble Front covers and clean electronic Racks and PCBs.

3. Check anchoring screws of the Table, they should be strongly tighten.

4. Press the mushroom shaped switch and verify that table is disconnected
and the table travels are blocked.

5. Release the mushroom shaped switch.

6. Connect Table power and check operator switches (foot switches and
hand switches).

47
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

7. Check the status of the motors of the table. (if elevating Table).

8. Assemble front covers of table.

9. Check table--top brakes and correct motion.

10. Release the horizontal Bucky brakes and check correct traveling.

11. Take out the Cassette film tray and check correct functioning.

6.2 CHECKING OF FLOOR MOUNTED TUBE STAND

1. Turn OFF generator and mains. Check that there is not voltage at
Tube--Stand.

2. Disassemble Front covers and check steel cable and brakes.

3. Check anchoring screws, they should be strongly tighten.

4. Turn ON mains and generator and check that the column and
Tube-Collimator Assembly is blocked in all motions.

5. Check motion of Column: horizontal and rotation.

6. Check motion of Tube-Collimator Assembly: vertical, Telescopic Arm


motion and rotation. Detents configured should be checked too.

7. Place the Tube at 0 on the Table--Top and check that X--ray indicator lamp
and the chassis centering indicator are aligned and they turn off after 30
seconds.

8. Check in the Collimator that light beam is centered with the X--ray beam
and the tolerance is not above 1% from focus--film distance.

6.3 CHECKING OF VERTICAL BUCKY

1. Turn OFF Generator and mains. Check that there is not voltage at
Vertical Bucky.

2. Disassemble Front covers of Wall Bucky Stand and clean steel cable and
brakes.

3. Check anchoring screws, they should be strongly tighten.

4. Turn ON mains and generator and check that the Vertical Bucky is
blocked.

5. Check the mechanical brake.

6. Press Bucky brake and verify that vertical motion is released and
counterweighted at any point.

7. Take out the Cassette film tray and check correct functioning.

48
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

SECTION 7 RENEWAL PARTS OF THE RAD ROOM

FRU Codes:1 = Repuestos que deben estar en Stock /Replacement Part


should be in Stock.
2 = No es necesario tener en stock / No need to have it in stock; easy to get after
order.
_ = Piezas existentes en Stock / All parts exist in our stock.

Table 2
Wall Bucky Spare Parts

Item GEMs Ref. MFG Ref. FRU Rep Name QTY Notes

2406963 7810-01 2 N Tabletop 1 584x572x4

2406964 50613014 2 N Pushbutton 1 4959111

51501116 2 N Bearing 20x37x9 2 61904--ZZ

2406961 52301010 1 N Electro Brake 24VDC 1 LM--35--N/24V

7810--01 7810--01 2 N Table--top 1

2406966 7205--02 2 N Steel Cable 2

7807-01 2 N Cover for Right Side of Bucky 1

7807-02 2 N Cover for Left Side of Bucky 1

2406982 S02.05.012 2 N Handgrip 2

7835--01 2 N Wheel 30 4

7836--01 2 N Wheel 28 4

Table 3
Wall Support Spare Parts

Item GEMs Ref. MFG Ref. FRU Rep Name QTY Notes

2406963 7810-01 2 N Tabletop 1 584x572x4

7835--01 2 N Wheel 30 4

7836--01 2 N Wheel 28 4

54505106 2 N Hand Grip (Carriage) 1 Rubber D= 22, 100mm long.

51501116 2 N Bearing 20x37x9 2 61904--ZZ

2406966 7205--02 2 N Steel Cable 2

49
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

Table 4
Radiographic Table Spare Parts

Item GEMS Ref. MFG Ref. FRU Rep Name QTY Notes

2406968 A6880-01 2 N Electromagnet 2

51501204 2 N Bearing 12x30x8 6 LR6001NPPU

51501001 2 N Bearing 12x28x8 2RS 2

2406972 52301011 2 N Electrobrake 24 -- 35 VDC 3 LM35P

2406975 50605015 2 N Microswitch 10A/250V 1 X0213981

2406964 50613014 2 N PushButton 1 4959111

53810025 2 N Wheel (Nylon) D=24 mm 1 NY24675

2403969 54402014 2 N Handle 4735--08--010 1

51501030 2 N Bearing 26x10x8 4 6000 2RS

51501013 2 N Bearing 12x32x10 8 6201-ZZ

11347-01 2 N Tabletop 1

Table 5
Sliding Column Spare Parts

Item MFG Ref. GEMS Ref. FRU Rep Name QTY Notes

2406962 7205--05 2 N Steel Cable (1880 mm) 2

2406967 52301011 2 N Electrobrake 24 VDC 35Dia 8 LM35P

51501116 2 N Bearing 20x37x9 2 61904--ZZ

51501204 2 N Bearing 12x30x8 4 LR6001NPPU

51520501 2 N Bearing 12x28x8 4 LR6000NPPU

51501304 2 N Bearing Axial Needle 1 AXK 160200 A


160x200x1

51501305 1 N Rolling Surface for bearing 1 AS 160200


160x200x1

51503004 2 N Bearing Conical 1 32012

2406964 50613014 2 N Switch ITW--49591 1

2406982 S02.05.012 2 N Handgrip 2

2406973 50613014 2 N PushButton 4 4959111

2406974 55801362 2 N Overlay 1

50
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

Table 6
Collimator Renewal Parts

Item GEMS Ref. MFG Ref. FRU Rep Name QTY Notes

2407010 6693--06 2 N Collimator 1

-- 2406992 RS006 2 N Lamp (Collimator) 1

-- 2408137 RS390 2 N External Cover 1

-- 2408138 RS393 2 N Antidust Plastic Pane 1

-- 2408139 RS312 2 N Control Knob right 1

-- 2408140 RS178 2 N Control Knob left 1

-- 2408141 RS425 2 N Metric Tape 1

-- 2408142 RS0147 2 N Push Button 1

-- 2408143 RS063 2 N Timer FM 338--24V 1

Table 7
Bucky Renewal Parts

Item GEMS Ref. MFG Ref. FRU Rep Name QTY Notes

2406970 6685--01 2 N Bucky 1

2406971 6694--02 2 N Tray Cassette 1

Table 8
X-Ray Tubes

Item GEMS Ref. MFG Ref. FRU Rep Name QTY Notes

2404346 6690--06 2 N X--Ray Tube E7239X 1

2403383 6690--09 2 N X--Ray Tube E7252X 1

2403384 6690--08 2 N X--Ray Tube E7299X 1

2403385 6690--10 2 N X--Ray Tube E7242X 1

6690--29 2 N X--Ray Tube E7865X 1

Table 9
Manuals Renewal Parts

Item GEMS Ref. MFG Ref. FRU Rep Name QTY Notes

-- SATXR/eOM 2 N Operator Manual Package 1

51
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

This page intentionally left blank.

52
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

SECTION 8 SYSTEM INTERCONNECTION MAPS

Refer to the following maps for details of the wire connections.

SYSTEM INTERCONNECTION

• General Purpose Rad System Interconnection . . . . . . . . . IM-341

• Rot Mobile Column Connections . . . . . . . . . . . . . . . . . . . . . 54301085

• Radiographic Table Interconnections . . . . . . . . . . . . . . . . . 54302065

• Wall Bucky Interconnections . . . . . . . . . . . . . . . . . . . . . . . . . 54301056

• Wall Support Interconnections . . . . . . . . . . . . . . . . . . . . . . . 54301068

Note . For System Interconnection Maps I/F-001, I/F-002, I/F-003,


IM-015 refer to Generator Service Manual -- Installation Chapter.

53
GE Medical Systems Proteus XR/e
REV 2 sm 2401594--100

This page intentionally left blank.

54
A B C D E

ROT MOBILE COLUMN Note 2.- Cable code:


See schematic 54301085
GENERATOR CABINET
A3052-XX for only Low Speed
for interconnections A7014-XX for Low/High Speed
Note 1.- Cable code:
TUBE STATOR CABLE (See Note 2) A8410-01 for Compact Generator - single phase
X-RAY TS2 HV A8411-01 for Compact Generator - three phase
4
TUBE TANK A8412-01 for Battery Generator 4
CATHODE CABLE
C C A8413-01 for Capacitor Generator
ANODE CABLE
A A VAC SUPPLY
GENERATOR SUPPLY CABLE (See Note 1)
GND CABLE (A6383-XX) AC LINE
Chassis Chassis
GND GND

COLLIMATOR COLLIMATOR CABLE (A3111-XX) LOCKS


TB7 BOARD

SUPPLY CABLE (A6736-XX)


TS1 TB7

RAD TABLE
See schematic 54302065
3 for interconnections SUPPLY CABLE (A7235-XX) 3

TS1 Note 3:
GND CABLE (A6383-XX) AEC CABLE, AEC INTERFACE CABLE AND
Chassis AEC ADAPTATION BOARD NOT USED FOR
Chassis GND RAD ROOM STANDARD (without ION
GND CHAMBER)

BUCKY
GENERATOR CONSOLE
TABLE BUCKY CABLE (A3091-XX) AEC ADAPTATION BOARD
TS1 (A3263-03)
See schematic I/F-001
See schematic IM-015 ATP CONSOLE BOARD

ION CHAMBER AEC CABLE (A3253-XX)


(Preamplifier) J1,J2,J3 AEC INTERFACE CABLE (A3251-XX)
(See Note 3) J4 J5
(See Note 3)
(See Note 3)
TB1 (See Note 3)
POWER CABLE (A7021-XX)
J2 J1

2 2
COMMUNICATION CABLE (A7022-XX)
J3 J3

VERTICAL BUCKY INTERFACE CABLE (A7069-XX)


TS1/TS3 J2
(See Note 3)

ION CHAMBER AEC CABLE (A7656-XX)


(Preamplifier) GND CABLE (A6383-XX)
(See Note 3) Chassis
Chassis GND
(See Note 3) GND
POWER I/F CABLE (A3252-03)

WALL BUCKY CABLE (A6703-XX)


BUCKY TS1

See schematic I/F-002


GND CABLE (A6383-XX)
Chassis
Chassis GND
GND
1 THIS SHEET ONLY APPLIES with CONVENTIONAL CONSOLE 1

NAME DATE SHEET / OF


DRAWING F.GARCIA 05/05/04 IM - 341
1/2
REVISED A.DIAZ 02/06/04 B A REV

B new interface F. García 10/10/05


SEDECAL RAD ROOM STANDARD
A new interface F. García 30/11/04
REV DESCRIPTION ISSUED BY DATE
& with AEC SYSTEM
A B C D E
A B C D E

ROT MOBILE COLUMN Note 2.- Cable code: GENERATOR CABINET


A3052-XX for only Low Speed
See schematic 54301085
A7014-XX for Low/High Speed
for interconnections

TUBE STATOR CABLE (See Note 2) Note 1.- Cable code:


X-RAY TS2 HV A8410-01 for Compact Generator - single phase
4
TUBE CATHODE CABLE TANK A8411-01 for Compact Generator - three phase 4

C C A8412-01 for Battery Generator


ANODE CABLE A8413-01 for Capacitor Generator
A A
VAC SUPPLY
GND CABLE (A6383-XX)
Chassis Chassis GENERATOR SUPPLY CABLE (See Note 1)
GND GND AC LINE

COLLIMATOR CABLE (A3111-XX) LOCKS


COLLIMATOR TB7 BOARD

SUPPLY CABLE (A6736-XX)


TS1 TB7

RAD TABLE
See schematic 54302065
3 for interconnections SUPPLY CABLE (A7235-XX) 3

TS1
GND CABLE (A6383-XX)
Chassis
Chassis GND
GND

BUCKY
TABLE BUCKY CABLE (A3091-XX)
TS1
See schematic I/F-001
ATP CONSOLE BOARD

ION CHAMBER AEC CABLE (A3253-XX)


(Preamplifier) J5
(See Note 3)
(See Note 3) Note 3:
AEC CABLE, AEC INTERFACE CABLE AND
AEC INTERFACE CABLE (A3251-02) AEC ADAPTATION BOARD NOT USED FOR
RAD ROOM STANDARD (without ION
(See Note 3)
CHAMBER)
2 2

AEC ADAPTATION BOARD GENERATOR CONSOLE


VERTICAL BUCKY (A3263-03) (TOUCH SCREEN)
See schematic IM-015
J4
ION CHAMBER AEC CABLE (A7656-XX)
(Preamplifier) J1,J2,J3 INTERFACE BOX CABLE (A7067-XX)
(See Note 3) (See Note 3) TB1 J5 GENERATOR
(See Note 3)
TPC SUPPLY CABLE (A7059-XX)
TS1 AC-SUPPLY
WALL BUCKY CABLE (A6703-XX) POWER I/F CABLE (A3252-03)
BUCKY TS1 GND CABLE (A7023-XX)
(See Note 3) Chassis Chassis
See schematic I/F-002 GND GND
GND CABLE (A6383-XX)
Chassis
Chassis GND
GND
1 1

THIS SHEET ONLY APPLIES with TPC CONSOLE

NAME DATE SHEET / OF


DRAWING F.GARCIA 05/05/04 IM - 341
2/2
REVISED A.DIAZ 02/06/04 B A REV

B new interface F. García 10/10/05


SEDECAL RAD ROOM STANDARD
A new interface F. García 30/11/04
& with AEC SYSTEM
REV DESCRIPTION ISSUED BY DATE
A B C D E
A B C D E

COLUMNA MOVIL (MOBILE COLUMN)


GENERADOR COMPACT
(COMPACT GENERATOR)
TS1 COLUMNA (COLUMN) Cable Freno Vertical (Vertical Lock Cable)
(A7219-01)
1
4 TARJETA FRENOS 4

(LOCKS BOARD) 2
Cable Alimentación Soporte Tubo
(Tube Support Power Supply Cable)
TB7 (A6736-XX) 3

+24 VDC LOCKS


5,7 4

0 VDC LOCKS
6,8 5
Freno Vertical CARRO LONG.
(Vertical Lock) (LONG. CARRIAGE)
6
GND GND
STUD GND Cable STUD

Cable Freno Longitudinal (Long. Lock Cable) Freno Long.


(A7005-01) TS3 (Long. Lock)
1
Nota.- Para modelos de Generador A6380-2x,
conectar el Cable a la regleta TS1 (+24 VDC
2
LOCKS a TS1-31 y 0 VDC LOCKS a TS1-32)
Note.- For A6380-2x Generator models, connect
the Cable to terminal strip TS1 (+24 VDC LOCKS
to TS1-31 and 0 VDC LOCKS to TS1-32)
3
BRAZO (ARM) 3

J1
Optional
1
Freno Transversal
(Transverse Lock)
2

J2
1
Freno Rotación
(Rotation Lock)
2

Cable Freno Rot/Transv (Rot/Transv Lock Cable)


(A7220-01)

2 2
6
5
4
3
2
1

PANEL CONTROL
TS2
(CONTROL PANEL)

Optional

TRANSV ROT LONG VERT


SW4 SW2 SW3 SW1

1 1

NAME DATE SHEET / OF


DRAWING F.GARCIA 23/07/04 54301085
REVISED A.DIAZ 23/07/04 1/1 REV

SEDECAL COLUMNA MOVIL


(MOBILE COLUMN)
REV DESCRIPTION ISSUED BY DATE
A B C D E
A B C D E

MESA (TABLE)
TS2
Bucky Lock Cable (A7096-01)
4 4
1 D2
1N4007
Freno Bucky
2 (Bucky Lock)

Transv. Solenoid Cable (A7098-02)

Solenoide Transversal
GENERADOR COMPACT
(COMPACT GENERATOR) (Transversal Solenoid)
TS1
Long. Solenoid Cable (A7098-01)
1
TARJETA FRENOS D1 Solenoide Longitudinal
1N5408
(LOCKS BOARD)
Cable Alimentación (Longitudinal Solenoid)
(Power Supply Cable) 2
TB7 (A7235-XX) TS3
Transversal Lock Cable (A7097-01)
+24 VDC LOCKS 1 D3
5,7 1N4007
Freno Transversal
3
0 VDC LOCKS 2 (Transversal Lock)
6,8
3
Foot Switch Cable (A7095-01) 3

4 SW1
GND GND
STUD GND Cable STUD PEDAL (FOOT SWITCH)

5 PULSADOR (HAND SWITCH)


SW2
Hand Switch Cable (A7094-01)
Nota.- Para modelos de Generador A6380-2x,
conectar el Cable a la regleta TS1 (+24 VDC
6
LOCKS a TS1-31 y 0 VDC LOCKS a TS1-32)
Note.- For A6380-2x Generator models, connect
the Cable to terminal strip TS1 (+24 VDC LOCKS
to TS1-31 and 0 VDC LOCKS to TS1-32)

Tracking
Bucky Tracking Cable (A7099-01) SW3

2 Nota.- La función de tracking con el SW3 y el Cable Bucky Tracking es opcional. Si no se usa esta opción, hacer puente entre TS1-5 y TS1-6. 2
Note.- The tracking function with the SW3 and the Bucky Tracking Cable is optional. Make jumper between TS1-5 and TS1-6 when that option is not used.

1 1

NAME DATE SHEET / OF


DRAWING F.GARCIA 05/05/04 54302065
1/1
REVISED A.DIAZ 06/06/04 B A REV

B new interface F. García 16/11/04


A CN 04/156 F. García 14/10/04 SEDECAL FIXED TABLE
REV DESCRIPTION ISSUED BY DATE
A B C D E
BUCKY MURAL
(WALL BUCKY) CARRO BUCKY
Tarjeta ADAPTACION AEC (Opcional) (BUCKY CARRIAGE)
(AEC ADAPTATION board – Optional)
MANGUERA CAMARA IONIZACION SOPORTE MURAL – ver nota 2
(WALL SUPPORT ION CHAMBER CABLE – see note 2) CABLE CAMARA IONIZACION
(A3253–01) (A6704–01)
IC J2 CAMARA IONIZACION
( ION CHAMBER )
1 1 1
2 FLD1 DR (LEFT) 2 2
3 FLD2 DR (CENTER) 3 3
Conector IC puede ser J1, J2, o
J3 dependiendo de la Cámara 4 STRT DR (RESET) 4 4
Ionización seleccionada
(Connector IC could be J1, J2, 5 IC OUTPUT 5 5
or J3 depending on the Ion
Chamber selected) 6 FLD3 DR (RIGHT) 6 6
7 –12 VDC 7 7
8 +12 VDC 8 8
9 GND 9 9

Shield Shield

Nota 2.– Para sistemas con sólo una sóla Cámara de Ionización
compatible con el Generador, no es necesario instalar la “Tarjeta de
Adaptación AEC” (opcional), conectar directamente la Cámara de
Ionización a 3TS1 del Armario y a J5 de la “Tarjeta ATP Console CPU”

Note 2.– For systems with only one Ion Chamber compatible with the PANEL
Generator, installation of “AEC Adaptation Board” (optional) is not INTERFACE
GENERADOR COMPACT required, connect the Ion Chamber directly to 3TS1 in the Generator
(COMPACT GENERATOR) Cabinet and to J5 in the “ATP Console CPU Board”.

MANGUERA BUCKY MURAL


(WALL BUCKY CABLE)
TS1 (A6703–01) J1 CABLE BUCKY BUCKY
(A6705–01)
12 BUCKY 2 MOTION 1 B1
13 BUCKY 2 MOTION RTN 2 B2
11 BUCKY 2 DR 3 B3
8 115/220 VAC 4 B4
10 0 VAC 5 B8
Añadir Puente
(Add Jumper) 9 6 B6

TARJETA FRENOS
(LOCKS BOARD) MANGUERA POTENCIA BUCKY MURAL (ver nota 1) PULSADOR FRENO BUCKY
(WALL BUCKY POWER CABLE – see note 1) TS2 CABLE PULSADOR (BUCKY LOCK PUSH–BUTTON)
TB7 (A6707–01/02/03) (A6706–01)
1
5, 7 +24 VDC LOCKS 2
6, 8 0 VDC LOCKS
3

4
5 FRENOS BUCKY
(BUCKY LOCKS)
GND GND CABLE GND

Nota 1.– Para Generador de Baterias con Millennium, conectarla a la regleta TS8 de
NAME DATE SHEET / OF DWG:
la Mesa (+24 VDC LOCKS a TS8–6, y 0 VDC LOCKS a TS8–5) 54301056
DRAWING F. GARCIA 05/05/01
Note 1.– For Battery Generator with Millennium, connect the cable to TS8 terminal 1/1
REVISED A. DIAZ 05/05/01 B A REV
strip of the Table (+24 VDC LOCKS to TS8–6, and 0 VDC LOCKS to TS8–5).

B new interface F. GARCIA 11/03/03 INTERCONEXIONES BUCKY MURAL


A CN 01/205 F. GARCIA 19/11/01 SEDECAL WALL BUCKY INTERCONNECTIONS
REV DESCRIPTION ISSUED BY DATE
SOPORTE MURAL
(WALL SUPPORT ) CARRO SOPORTE MURAL
Tarjeta ADAPTACION AEC (Opcional) (WALL SUPPORT CARRIAGE)
(AEC ADAPTATION board – Optional) MANGUERA CAMARA IONIZACION SOPORTE MURAL – ver nota
(WALL SUPPORT ION CHAMBER CABLE – see note)
CABLE CAMARA IONIZACION
(A3253–01)
(A6704–01)
IC J2 CAMARA IONIZACION
( ION CHAMBER )
1 1 1
2 FLD1 DR (LEFT) 2 2
3 FLD2 DR (CENTER) 3 3
Conector IC puede ser J1, J2, o
J3 dependiendo de la Cámara 4 STRT DR (RESET) 4 4
Ionización seleccionada
(Connector IC could be J1, J2, 5 IC OUTPUT 5 5
or J3 depending on the Ion
Chamber selected) 6 FLD3 DR (RIGHT) 6 6
7 –12 VDC 7 7
8 +12 VDC 8 8
9 GND 9 9

Shield Shield

GND GND
PANEL
Nota.– Para sistemas con sólo una sóla Cámara de Ionización compatible con el Generador, INTERFACE
no es necesario instalar la “Tarjeta de Adaptación AEC” (opcional), conectar directamente la
Cámara de Ionización a 3TS1 del Armario y a J5 de la “Tarjeta ATP Console CPU”

Note.– For systems with only one Ion Chamber compatible with the Generator, installation of
“AEC Adaptation Board” (optional) is not required, connect the Ion Chamber directly to
3TS1 in the Generator Cabinet and to J5 in the “ATP Console CPU Board”.

GENERADOR COMPACT
(COMPACT GENERATOR)

TARJETA FRENOS
(LOCKS BOARD) MANGUERA POTENCIA SOPORTE MURAL PULSADOR FRENO SOPORTE MURAL
(WALL SUPPORT POWER CABLE) TS2 CABLE PULSADOR (WALL SUPPORT LOCK PUSH–BUTTON)
TB7 (A6707–01/02/03) (A6706–01)
1
5, 7 +24 VDC LOCKS 2
6, 8 0 VDC LOCKS
3

4
5 FRENOS SOPORTE
(SUPPORT LOCKS)
GND GND CABLE GND

NAME DATE SHEET / OF DWG:


DRAWING F. GARCIA 09/09/02
54301068
1/1
REVISED A. DIAZ 09/09/02 A REV

INTERCONEXIONES SOPORTE MURAL


A CN 03/044 F. GARCIA 06/03/03 SEDECAL WALL SUPPORT INTERCONNECTIONS
REV DESCRIPTION ISSUED BY DATE