Professional Documents
Culture Documents
CONSULTING ENGINEERS
Date:
☐ B: Approved to proceed
Subject to ☐ D: Information only
Comments:
المهندس
Fichtner Consulting Engineers Limited
ENGINEER
مقاول
ACCIONA – RTCC (JV)
CONTRACTOR
LOCATION TITLE:
SUBCONTRACTOR: Sheet 1 of 3
SA06C2-WM-00-M-0017
TABLE OF CONTENTS:
Contents
1. Introduction .................................................................................................................... 6
2. Scope of work ................................................................................................................. 6
3. Installation drawings Abbreviation and Symbols .............................................................. 6
4. Reference Documents ..................................................................................................... 6
5. Design basis and Methodology ........................................................................................ 7
5.1 Structure Details .............................................................................................................. 7
5.2 Proposed CP system Details............................................................................................. 7
5.2.1 Temporary CP system .............................................................................................. 7
5.2.2 Permanent CP system .............................................................................................. 8
5.2.3 Existing Pipeline in Common Corridor ..................................................................... 8
5.2.4 Existing CP system of nearby structures .................................................................. 8
5.2.5 Over Head High Voltage Power Line ........................................................................ 8
5.2.6 Thrust Boring Crossing ............................................................................................. 9
5.2.7 Isolation Test Station................................................................................................ 9
5.2.8 Potential Test Station ............................................................................................... 9
5.2.9 CP Equipment Monitoring........................................................................................ 9
6. Design Consideration .................................................................................................... 10
6.1 Soil Resistivity ................................................................................................................ 10
6.2 Design current density ................................................................................................... 10
6.3 Protection criteria .......................................................................................................... 11
6.4 System Design Life ......................................................................................................... 11
7. Design calculation for Temporary CP system .................................................................. 12
7.1 Variable Constant .......................................................................................................... 12
7.2 Design guidelines and parameters ................................................................................ 12
7.3 Design Current ............................................................................................................... 13
7.4 Anode to ground Resistance .......................................................................................... 13
7.5 Anode current output .................................................................................................... 13
7.6 Anode Quantity based on current output ..................................................................... 13
7.7 Anode Quantity based on Anode weight....................................................................... 13
7.8 Design Life ...................................................................................................................... 14
7.9 Recommendation .......................................................................................................... 14
1. Introduction
Three Lions have been contracted by Acciona to provide an engineering design for a Cathodic Protection
system for underground Pipelines for the Replacement of Ended Lifetime Technologies and Assets for
the Shuqaiq Phase 1 Desalination Plant. The Pipelines details are tabulated below in Table 1.
Table-1
Sr. No Service Dia. (Inch) Dia. (m) Length (M)
1 Product Pipeline-1 56 1.4 1700
2 Product Pipeline-2 56 1.4 1795
The report provides a design for U/G pipelines of 1.4m dia based on information supplied by the
contractor and a site visit conducted by TLF.
TLF will develop the cathodic protection detail design to meet the cathodic protection required for this
project as per the Latest SWCC specifications.
2. Scope of work
The scope of work is limited to providing cathodic protection detail design, material supply, installation
testing, and commissioning of the CP system as per applicable engineering standards, drawing, and
mandatory requirements.
This document will cover Temporary and Permanent Cathodic Protection system designs supported by
detailed calculations as per applicable standards and SWCC specifications.
This detailed design package for pipelines includes the following for Temporary and Permanent Cathodic
Protection System
• Design basis
• Design calculations
• Bill of Materials
• Material Specifications
3. Installation drawings Abbreviation and Symbols
In the context of these documents, the following abbreviations shall apply while the rest is defined
accordingly throughout the documents.
CP : Cathodic Protection
DC : Direct current
HMWPE : High Molecular weight Polyethylene
ICCP : Impressed Current Cathodic Protection
NACE : National Association of Corrosion Engineers
SACP : Sacrificial Anode Cathodic Protection
THHN : Thermoplastic High Heat Nylon
3LPE : 3 Layer Polyethylene
4. Reference Documents
This section lists the Codes, Standards, and project documents/ drawings, which apply to the detailed
design.
Reference No Standard Description
Volume IX Electrical
SWCC Spec Specification B.9 Cathodic Protection
Works
Control of external corrosion of buried metallic and
RP0169-2013 NACE
submerged pipeline
Petroleum and natural gas industries Cathodic
ISO-15589-1 ISO
protection of pipeline transportation system
Project Drawings
Reference No Rev Description
20SWCG00051-1-100-0000LE-
A General Arrangement & schematic drawings
1E0-20-909301
5. Design basis and Methodology
5.1 Structure Details
The proposed pipelines are 1700 & 1795 meters long starting from the plant to the water tanks.
5.2 Proposed CP system Details
5.2.1 Temporary CP system
Pipelines will be provided with temporary CP for a minimum lifetime of (2) years / until the
commissioning of the permanent CP system. The temporary CP will be achieved using a pre-packed
magnesium Ribbon anode. Anode will be connected to the pipeline utilizing the installed
permanent CP test stations and temporary CP. These test stations can be normal potential test
stations and isolation test stations. A temporary CP system shall be installed to provide short-term
cathodic Protection only when:
a. The Permanent ICCP will not be energized within 30 days of the burial of any portion of
the pipeline and
b. The Magnesium anode installed during pipeline construction for permanent cathodic
Protection requirements will not provide enough CP (to achieve Temporary criteria) for
new pipelines or pipeline segments.
Sacrificial Cathodic Protection shall be considered for the following locations:
• For sections of the pipeline that are not electrically continuous with the bonded sections
and are buried for more than 30 days.
• For the section of the Pipeline where the measured potential is below the minimum
criteria.
The proposed arrangement for the Temporary Cathodic Protection system shall be as follows.
• Magnesium Ribbon anodes shall be connected to the pipeline via the Big Fink test station,
which shall also be utilized for a permanent CP system as a test point.
Notes:
1. At the middle of pipelines approx. 850 meters, a sacrificial CP system is proposed as a
temporary system that may be hooked to any test station as per convenience.
2. A sacrificial CP system is designed to provide the requirements for how long the pipeline
section should be provided and how many anodes; therefore, it can be installed in those
pipeline sections that can be backfilled after installation.
3. The temporary CP system shall be disconnected once the ICCP system is energized.
6. Design Consideration
6.1 Soil Resistivity
The purpose of soil resistivity measurement is to ensure proper Cathodic protection design is done
based on the actual site conditions. The resistivity is used to calculate anode-to-earth resistance,
which affects the number of anodes required. The resistivity is also an indication of the
aggressiveness of the environment. Resistivity and corrosiveness have an inverse relationship. The
higher the soil resistivity, the lower the corrosiveness.
The following table (ASTM Special Publication 741) provides general guidelines for evaluating the
corrosiveness of an environment concerning resistivity values.
1. For Temporary CP
There is no defined standard for an acceptable current density with a 2-year end-
of-life as this temporary cathodic protection requires. Various papers deal with
coatings but none provide a definitive end-of-life current density requirement.
Because of the lack of definitive criteria, it is proposed to use a required current
density of 0.005mA/m2 as is the current Saudi Aramco practice (reference SAES-X-
400 Table 2 for temporary cathodic protection current density).
So, a current density of 0.005mA/m² is considered to calculate the protective
current required for the Temporary CP.
2. For Permanent CP, current density = 0.015mA/m²
6.3 Protection criteria
Temporary CP System
Section 18.10 of B.9, the protection potential to be reached shall be -0.85 V measured against a
Cu/CuSO4 reference electrode.
Permanent CP system
As per B.9 SECTION 18.5
The impressed current cathodic protection systems shall be designed to provide sufficient current
to achieve an “OFF” potential over the equipment and/or material to be protected, equal to or
more negative than – 1 V (measured against a Cu/CuSO4 reference electrode). “OFF” potentials
with a value more negative than – 1.5 V should be avoided.
OR
As per NACE standard SP-0169:
The negative (cathodic) potential of at least 850 mV with the CP applied. This potential is measured
concerning a saturated copper/copper sulphate reference electrode contacting the electrolyte.
Voltage drops other than those across the structure-to-electrolyte boundary must be considered
for a valid interpretation of this voltage measurement.
OR
The negative polarized potential of at least 850 mV relative to a saturated copper/copper sulphate
reference electrode.
OR
A minimum of 100 mV of cathodic polarization between the structure surface and a stable
reference electrode contacting the electrolyte. The formation or decay of polarization can be
measured to satisfy this criterion.
At the site, any of the above criteria shall be met.
6.4 System Design Life
As mentioned in Specs B.9 the service life of the cathodic protection systems shall not be less than
fifty (50) years. Anode ground beds with a lifetime of twenty-five (25) years will be accepted.
For an Anode ground bed, the design life shall be 25 years for Permanent CP.
For Temporary CP the design life shall be 2 Years.
Where:
%VOUT = % voltage rise that r is outside
Er = voltage rise at distance "r'' meters from the anode
IR = voltage of the anode measures to remote earth at current I Ampere
L = length of anode below grade (meters)
d = diameter of the anode (m)
r = distance (m) from anode to point of measurement
The below chart is a plot of the previous formula and given the remoteness curve for a single
anode bed with 12 m active length and 25.4 cm diameter.
Separation from the pipeline to the anode bed should be assured that the pipeline is outside
90% of the anode voltage gradient.
Anode Remoteness
100.0%
Anode Gradient Inside Distance (%)
95.0%
90.0%
85.0%
80.0%
75.0%
70.0%
65.0%
10 20 30 40 50 60 70 80 90 100
Distance from Anode (Meter)
This chart indicates that the anode bed should be located at least 50m distance from the new
pipelines, however, the proposed anode bed will be installed at a 50m distance from the pipeline.
The exact location for the proposed anode bed is shown in the drawings.
8.2.5 Circuit Resistance
The circuit resistance includes the anode bed resistance, parallel resistance of anode cable tails,
Positive cable resistance, negative cable resistance, pipe-to-ground resistance, and effective
resistance caused by back EMF. These resistances are required to be evaluated to drive the total
circuit resistance.
a. Target Anode bed Resistance
Applying Dwight’s equation for vertical installation, the resistance of the anode bed to the
ground shall be
𝜌𝜌 8𝐿𝐿𝑎𝑎
𝑅𝑅𝐴𝐴 = �𝐿𝐿𝑛𝑛 � � − 1�
2𝜋𝜋𝐿𝐿𝑎𝑎 𝐷𝐷𝑎𝑎
Where,
ρ = Soil Resistivity (20 ohm-m) from survey data
La = Anode bed Active Length (12m)
Da = Anode Bed Diameter (0.254m)
Anode to ground Resistance (Rg) = 1.3 Ohm
b. Parallel Resistance of Anode Cable Tail
Cable Size Resistance per Cable
Cable Resistance
Anode No 1/Ra
(mm2) meter Length (m)
Ra (ohm)
A1 16 0.001672 52 0.086944 11.50
A2 16 0.001672 47 0.078584 12.72
A3 16 0.001672 42 0.070224 14.24
Total of 1/Ra 38.46
Equivalent Resistance of Anode Cables (RCA) 0.025
c. Positive cable resistance from TR to AJB, AJB Location
9. Installation Guideline
9.1 General
In all cases, the Cathodic Protection system installation work shall be carried out in a manner such
that the requirement of B.9, related drawings, and the project drawings and specifications are met.
9.2 Scope
These specifications shall be applicable for all work related to cathodic protection system
installation. These works include but are not limited to the installation of impressed current anode
ground bed, Junction boxes, DC power supplies, and DC cables as a sundry item for support and
finishing of each Facility.
9.3 Quality Control
Installation work at all times be carried out within an appropriate quality control system, this should
be affected by strictly adhering to all materials approval requirements.
9.4 Safety
The installation work shall always be carried out safely, with all site personnel, staff, and Labour
fully adopting the project safety procedures.
All parties shall be particularly aware of the safety requirement concerning working in trenches,
hot work, and installation of electrical equipment.
9.5 Material Handling
All material associated with the installation work shall be considered fragile and shall be treated
accordingly. In particularly impressed current anodes shall be carefully handled. They shall not be
removed from their packing crates until immediately before installation. Any anode, which is
dropped, shall be rejected.
All DC cables shall be handled and stored to avoid damage to the insulation, and inspection of
insulation shall take place before installation.
9.6 Transformer Rectifier Installation
The transformer Rectifier shall be installed following the project drawing. The designated location
for TR shall be verified on-site before installation works take place. Oil-immersed rectifiers shall be
mounted a minimum of 300 mm above ground to minimize sand accumulation against the rectifier.
The unit shall be securely grounded before the connection of AC and DC cables. It shall be assured
that the applicable AC breaker at the associated substation is locked off before the connection of
AC cables. It shall be assured that the DC cables are connected with the correct polarity.
9.7 Deep well Anode Bed Installation
The deep anode ground beds shall be constructed as specified on the project cathodic protection
system layout drawing and shall conform to project specifications and applicable project drawings.
Before installation, the location for the ground bed shall be verified, and it is sufficiently distant
from buried structures to meet the requirements of the project specification.
Following verification of the design, or modified design, the ground bed shall be installed to include
the indicated anode quantity. The anode quantity shall not be less than that provided in the design
documents.
12.4 Cables
• SACP Anode cable tail shall be THNN insulated #8AWG (10sqmm) cable 10 meters in length.
• The Monitoring cable shall be 1C x 6sqmm HMWPE Insulation.
• ICCP Anode Cable shall be 1C x 16 sqmm KYNAR/HMWPE
• Positive and Negative Header Cable shall be 25 sqmm HMWPE
12.5 Junction Box
Type : Anode Junction Box
Terminals : 5
Shunt value : 50mV/50A
Weather Protection : NEMA 4X (IP 65)
Enclosure Type : Aluminium
Area Classification : Non-Hazardous
Installation : Steel support PVC Coated with Concrete Pad
12.6 Test Stations (Potential/Current/Coupon/Isolation coupling)
The Big FINK ® cathodic protection test station is a field-proven, high-strength, maintenance-free
terminal for monitoring electric currents and potentials. Since 1976, the Big FINK ® cathodic
protection test station has been utilized worldwide by gas, oil, chemical, and water pipeline
companies.
These test stations are supplied with PVC or Galvanized Steel conduits.
Type : Big Fink (Lockable Type)
Head Colour : Orange
Number of Terminals : Minimum 5 Terminal
Conduit size : 3 Inch
Area Classification : Non-Hazardous
Installation : Steel support hot dip galvanized with Concrete Pad
12.7 Permanent Reference Electrode
Type : Cu/CuSO4
Cable : HMWPE or XLPE/PVC or THHN/THWN
Installation Location : ICCP station.
12.8 Coating Repair
Type : Epoxy coating
Area of Application : At pin brazing Location.
12.9 Connection to Pipeline
Connection method : Pin Brazing
NOTE: ALL EQUIPMENT AND TEST STATION LOCATIONS MAY CHANGE ACCORDING TO SITE CONDITIONS
AND SHALL BE UPDATED ACCORDINGLY IN THE AS-BUILT DRAWING.
to-4.5-meter Depth
(X:187837.807 450 0.60 450-300 1.50 1413
Y:1955663.027)
600 0.40 600-450 1.20 1130
150 5.40 0-150 5.40 5087
SR-02
KM 0+800 300 2.50 300-150 4.66 4385
(X: 188299.030 450 0.95 450-300 1.53 1443
Y:1955780.167)
600 0.53 600-450 1.20 1129
Remarks:
Anode shall be installed at a 3.0 to 4.5-meter depth. For the design calculation, a soil resistivity value of 20 Ω-m
shall be taken and used.
Measured by Reviewed by
Signature
cm
Anode shall be installed in the active column length between depths of (30 to 60) meters. For the design
calculation, a soil resistivity value of 20 Ω-m shall be taken and used.
Measured by Reviewed by
Signature
The measurement depths could be decided as per client specifications and it is usually performed at 3
and 6 meters for temporary CP systems and shallow impressed current CP systems, whereas it could
reach up to 100 meters for impressed current deep anode beds. For the pipeline’s temporary CP
system, the test shall be performed at an interval of 1-2 kilometers along the pipeline and varies as
per client requirement, while for impressed current systems, the test shall be performed directly over
the proposed anode bed span of land.
Moreover, another formula which is called “Barnes” could be used to calculate the resistivity of soil layers:
Rlayer= (R1 x R2)/(R1-R2)
ρlayer= 2 x π x Rlayer x Slayer
Where:
Rlayer is the calculated resistance of the soil layer. R1 is the displayed resistance at depth no. 1.
R2 is the displayed resistance at a depth no. 2.
Slayer is the spacing between the top & bottom edges of the desired layer.
Practical Testing Recommendations
• It has been found that special care is required when testing: Eliminate interference due to leads
parallel to power lines.
• Cable reels with parallel axes for current injection and voltage measurements, and small cable
separation for large spacing (>100m) can result in errors.
• Ensure the instrumentation and setup are adequate (i.e., power levels, interference, and
filtering). Undertake operational checks for accuracy (i.e., a field calibration check).
• Reduce contact resistance (use salt water).
• Instruct staff to use finer test spacing in areas showing sharp changes (i.e., to identify the effect
of local un-homogeneities and give increased data for interpretation). Plot test results
immediately during testing to identify such problem areas.