Inspection Procedure

Bore Pull Out Angle / Internal


Bevel Angle Inspection

Document Number TSH-IP-00.0027


Revision 02
Revision Date 29-Jan-2009
Effective Date 26-Jun-2009
Page(s) 4

This document as well as the information or data contained herein are confidential and shall not be copied, recopied,
reproduced, transmitted, disclosed or distributed to others or otherwise used for any purpose without the express, prior
and written permission of Tenaris Connections AG and/or Hydril Company and/or its affiliated companies ("Tenaris").
This document as well as the information or data contained herein are the exclusive property of Tenaris, and are to be
returned upon request therefore. All rights in proprietary and novel features of the subject matter are expressly reserved
by Tenaris. Recipient’s agreement to the foregoing is indicated by acceptance of this document. Copyrighted 2008 as an
unpublished work. ALL RIGHTS RESERVED.
For PVD Qualification Document Type Inspection Procedure
Document Number TSH-IP-00.0027
Bore Pull Out Angle / Internal Bevel Angle
Inspection Revision 02

Page Number 2

1. REVISION HISTORY

Effective
Rev. # Change Referenced Sections Prepared By: Reviewed by: Approved By:
Date

26-Jun-2009 02 New Document New Document


Name: R. Stubelt Name: M. Soptick Name: D. Baiz

Document Change

Disposition of
Affected Material

Raw Material X
In Process X
Completed X
For PVD Qualification Document Type Inspection Procedure
Document Number TSH-IP-00.0027
Bore Pull Out Angle / Internal Bevel Angle
Inspection Revision 02

Page Number 3

2. PURPOSE

2.1 The Purpose of this document is to explain the measurement of the Bore Pull Out Angle / Internal
Bevel Angle.

3. PERSONS AFFECTED

3.1 This document is applicable to all:


3.1.1 All Tenaris Premium Connections Manufacturing Services Personnel.
3.1.2 Facilities licensed to thread TenarisHydril connections.

4. REFERENCES

4.1 Not Applicable.

5. DEFINITIONS AND ABBREVIATIONS

5.1 Definitons and Abbreviations are defined in the most current revision of TenarisHydril document
TSH-GP-00.0001.

5.2 Bore Pull Out Angle: is the angle of the conical transition between the Bore diameter and the
internal diameter of the pipe.

5.3 Internal Bevel Angle: is the angle of the tapered internal bevel

6. RESPONSIBILITIES

6.1 Responsibilities are defined in the most current revision of TenarisHydril document
TSH-GP-00.0002.

7. PERSONNEL QUALIFICATION

7.1 Personnel qualification is defined in the most current revision of TenarisHydril document
TSH-GP-00.0003.

8. PROCEDURES

8.1 Inspection
Bore Pull Out Angle: The measurement is made by performing a mold in the intersection between
the pin bore and the nominal material ID. The angle is then measured with the optical
comparator.

Internal Bevel Angle: With a Protractor measure the transition angle between the pin shoulder
and the nominal material ID

8.2 Acceptance / Rejection Criteria


For PVD Qualification Document Type Inspection Procedure
Document Number TSH-IP-00.0027
Bore Pull Out Angle / Internal Bevel Angle
Inspection Revision 02

Page Number 4

Bore Pull Out angle / Internal Bevel Angle is acceptable if the measured value is within the limits
prescribed on the IR.

8.3 Records
The result of this inspection shall be recorded on the IR.