You are on page 1of 4

For PVD Qualification

Prepared by: Reviewed by: Approved by:

Michael Soptick Rubén Stubelt Daniel Baiz


Premium Connections Premium Connections Premium Connections
Manufacturing Services Specialist Manufacturing Services Coordinator Manufacturing Engineering Manager
Tenaris Tenaris Tenaris

Inspection Procedure

OD Chamfer Diameter

Document Number TSH-IP-00.0093


Revision 01
Revision Date 01-Sep-2008
Effective Date 20-Oct-2008
Page(s) 4

This document as well as the information or data contained herein are confidential and shall not be copied, recopied,
reproduced, transmitted, disclosed or distributed to others or otherwise used for any purpose without the express, prior
and written permission of Tenaris Connections AG and/or Hydril Company and/or its affiliated companies ("Tenaris").
This document as well as the information or data contained herein are the exclusive property of Tenaris, and are to be
returned upon request therefore. All rights in proprietary and novel features of the subject matter are expressly reserved
by Tenaris. Recipient’s agreement to the foregoing is indicated by acceptance of this document. Copyrighted 2008 as an
unpublished work. ALL RIGHTS RESERVED.
For PVD Qualification Document Type Inspection Procedure
Document Number TSH-IP-00.0093
OD Chamfer Diameter Revision 01

Page Number 2

1. REVISION HISTORY

Effective
Rev. # Change Referenced Sections Prepared By: Reviewed by: Approved By:
Date

20-Oct-2008 01 New Document New Document


Name: M. Soptick Name: R. Stubelt Name: D. Baiz

Document Change

Disposition of
Affected Material

Raw Material X
In Process X
Completed X
For PVD Qualification Document Type Inspection Procedure
Document Number TSH-IP-00.0093
OD Chamfer Diameter Revision 01

Page Number 3

2. PURPOSE

2.1 The purpose of this document is to explain how the measurement of the OD chamfer is
performed.

3. PERSONS AFFECTED

3.1 This document is applicable to all:


3.1.1 All Tenaris Premium Connections Manufacturing Services Personnel.
3.1.2 Facilities licensed to thread TenarisHydril connections.

4. REFERENCES

4.1 Not Applicable.

5. DEFINITIONS AND ABBREVIATIONS

5.1 Definitions and Abbreviations are defined in the most current revision of TenarisHydril document
TSH-GP-00.0001.

6. RESPONSIBILITIES

6.1 Responsibilities are defined in the most current revision of TenarisHydril document
TSH-GP-00.0002.

7. PERSONNEL QUALIFICATION

7.1 Personnel qualification is defined in the most current revision of TenarisHydril document
TSH-GP-00.0003.

8. PROCEDURES

8.1 Inspection:

Inspection of the OD chamfer diameter is performed by measuring the diameter of the OD


chamfer at the intersection of the box face to the same location 180° across. Measure in two
places approximately 90° apart . Average the results.
The formula for obtaining the average is as follows:

Maximum Diameter + Minimum Diameter


2

8.2 Acceptance / Rejection criteria

OD chamfer diameter is acceptable if the measured diameter is within limits prescribed on the IR.
For PVD Qualification Document Type Inspection Procedure
Document Number TSH-IP-00.0093
OD Chamfer Diameter Revision 01

Page Number 4

8.3 Records

The result of these inspections shall be recorded on the IR.

9. ANNEX

9.1 Not Applicable.