Ohs-Pr-09-25-F03 Audit Action Plan - Woa
Ohs-Pr-09-25-F03 Audit Action Plan - Woa
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
OHS-PR-02-01
Risk Profile
prepared
PR-02-01
1. Risk profile not prepared properly EHS Engineer 25-07-2023 Hierarchy wise 03-08-2023 06-08-2023
N0.3
Low ,Medium
,High
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
Goals and
PR-02-01
2. To identify specific goals and objectives PM/SM 25-07-2023 Objectives 03-08-2023 06-08-2023
N0.4
2023 Year
prepared
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
PR-02-01
3. OHS plans not specified for the whole year EHS Engineer 25-07-2023 Completed 03-08-2023 06-08-2023
N0.5
Completed
PR-02-01 KPI available but OHS indicators are not
4. EHS Engineer 25-07-2023 Indicators 03-08-2023 06-08-2023
N0.6 identified
record
5. OHS-PR-02-02
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
Discussed
PR-02-02 objectives and
6. Discussion not involve employees EHS Engineer 25-07-2023 03-08-2023 06-08-2023
N0.3 Target in
meetings
Safety
PR-02-02 Representative
7. Safety rep appointments not available EHS Engineer 25-07-2023 03-08-2023 06-08-2023
N0.5 appointed Total
05 Nos
8. OHS-PR-02-03
9. PR-02-03 HIRA not completely filled EHS Engineer 25-07-2023 Completed 03-08-2023 06-08-2023
N0.1
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
Completed as
PR-02-03 Risk profile in wrong format and not
10. EHS Engineer 25-07-2023 designated 03-08-2023 06-08-2023
11 properly prepared
format
Risk register
PR-02-03 prepared as
11. Risk Register EHS Engineer 25-07-2023 03-08-2023 06-08-2023
12 low medium
high
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
PR-02-03
12. CTA/CTI not properly prepared EHS Engineer 25-07-2023 Prepared 03-08-2023 06-08-2023
15
PR-02-03
13. PPE required not identified EHS Engineer 25-07-2023 Completed 03-08-2023 06-08-2023
16
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
PR-02-03 Training
14. No third party training SM 25-07-2023 03-08-2023 06-08-2023
21 Requested
25-07-2023
Prepared from
April onwards
PR-02-03
15. Not prepared for the whole year EHS Engineer Because project 03-08-2023 06-08-2023
25
full mobilized
on April
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
25-07-2023
PR-02-03
16. Wrong format used PJO EHS Engineer Closed 03-08-2023 06-08-2023
27
17. OHS-PR-02-05
25-07-2023 Closed
25-07-2023 Closed
19. PR-02-05-2 Objectives and targets no inputs EHS Engineer 03-08-2023 06-08-2023
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
25-07-2023 Closed
22. OHS-PR-02-06
25-07-2023 Training to be
requested
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
25-07-2023 Completed
26. PR-02-06-8 OHS Training plan not implemented EHS Engineer 25-07-2023 Completed 03-08-2023 06-08-2023
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
28. OHS-PR-02-07
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
Indicate the level of effectiveness of the -
record control system to
meet the OHS Standard and management SEC format
30. PR-02-07-2 EHS Engineer 25-07-2023 03-08-2023
system needed
Requirements? Most documents are in
wrong formats
Does the document control process -
SEC format
31. PR-02-07-3 address all the requirements? Sec formats EHS Engineer 25-07-2023 03-08-2023
needed
should be used
32. OHS-PR-02-09
25-07-2023
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
25-07-2023
25-07-2023
Waste Removal
Has a formal waste management program disposed once
PR-02-09-
35. been established and Store Keeper reach the 03-08-2023 06-08-2023
15
Implemented? Waste removal no records sufficient
quantity.
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
25-07-2023
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
25-07-2023
25-07-2023
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
25-07-2023
25-07-2023
Noise surveys been conducted for all
workplace premises by a
PR-02-09- competent appointed person using a
40. EHS Engineer Completed 03-08-2023 06-08-2023
21 suitable calibrated sound
level? Generator area not included
insurvey
25-07-2023
Are noise zones indicated on a layout plan
of the premises and
boundaries of all the identified noise
PR-02-09-
41. zone(s) demarcated and EHS Engineer Completed 03-08-2023 06-08-2023
22
mandatory hearing protection signage
displayed at each
access point? Layout plan not available
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
25-07-2023
43. OHS-PR-02-10
25-07-2023
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
25-07-2023
25-07-2023
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
25-07-2023
Are all Motorized Equipment are
registered and maintained and a
OHS-PR-02- Licensing and competence of
47. EHS Engineer Completed 03-08-2023 06-08-2023
10-9 driver/operators are assessed and
Checked? Should include all light vehicles
in registry.
48. OHS-PR-02-11
25-07-2023
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
Have
competent loto
The issuance keys to 'locked-out' electrical
OHS-PR-02- supervisor and
51. panels must be HSE Engineer 25-07-2023 03-08-2023 06-08-2023
11-6 electrician
Controlled.
available in
site.
25-07-2023
Generator risk
Risk assessment completed for all high risk assessment
OHS-PR-02-
52. electrical equipment. A teams not HSE Engineer implemented 03-08-2023 06-08-2023
11-9
indicated in the risk assessments and RA team
updated.
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
25-07-2023
Electrical equipment shall be inspected Generator
and maintained as per the checklist only
OHS-PR-02- Standard. OBSERVED CONTRACTORS have in sec
53. HSE Engineer 03-08-2023 06-08-2023
11-10 ACTION TAKEN format other
List is not complete; Bending / cutting format not
machine not in list available
25-07-2023
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
25-07-2023
56. OHS-PR-02-12
25-07-2023
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
25-07-2023
59. OHS-PR-02-13
25-07-2023
Action plans to correct deviations? ITEMS
OHS-PR 02- OBSERVED CONTRACTORS ACTION TAKEN Need
60. EHS Engineer 03-08-2023 06-08-2023
13- 2 No action plan on deviations during the clarification
assessments
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
25-07-2023
25-07-2023
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
25-07-2023
OHS-PR 02-
63. Fire teams and volunteer’s availability. EHS Engineer Completed 03-08-2023 06-08-2023
13- 7
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
25-07-2023
65. OHS-PR-02-14
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
25-07-2023
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
25-07-2023
25-07-2023
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
25-07-2023
25-07-2023
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
25-07-2023
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
25-07-2023
25-07-2023
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
below the work area to protect others
below from falling objects?
25-07-2023
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
25-07-2023
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
25-07-2023
25-07-2023
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
82. OHS-PR-02-17
25-07-2023
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
25-07-2023
25-07-2023
87. OHS-PR-02-018
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
25-07-2023
25-07-2023
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
25-07-2023
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
25-07-2023
25-07-2023
94. OHS-PR-02-19
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
25-07-2023
OHS-PR 02-
95. Are all lifting gear Identified in a register? EHS Engineer Closed 03-08-2023 06-08-2023
19- 2
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
EHS Engineer
99. OHS-PR-02-21
101. OHS-PR-02-22
Conduct quarterly evaluation of contractor EHS Engineer 25-07-2023 No Evaluation reports
OHS-PR 02- Loss Prevention Plan
102. closed 03-08-2023 06-08-2023
22- 9 OHS compliance implementation and
nonconformance’s
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
No records
Are non-compliance documented and 1st audit conducted 24th July. So
OHS-PR 02- corrective actions no previous report available.
103. EHS Engineer 25-07-2023 Closed 03-08-2023 06-08-2023
22- 10 Identified, implemented and reviewed?
No records
104. OHS-PR-02-23
Dedicated control center and alternative EHS Engineer 25-07-2023 -
one.
Check for
-availability and accessibility
-Types of equipment
OHS-PR 02- Requested for
105. -Communications equipment 03-08-2023 06-08-2023
23- 8 materials
-Emergency equipment & PPE
-Plans, P&ID, monitors etc. Responsibility:
Mgr. (Auditable unit)
Limited emergency equipment available;
stretcher, bed etc not available
106. OHS-PR-02-25
At least bi-annually self-audits including EHS Engineer 25-07-2023 No bi-annually audit conducted.
Management.
Check for:
OHS-PR 02-
107. -Documented self-audit bi-annually open 03-08-2023 06-08-2023
25- 2
-Documented report for Non-
conformances recorded
-Documented report for Corrective Actions
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
Not conducted
EHS Engineer 25-07-2023
Annual Safety Perception Survey EHS Engineer 25-07-2023 After After completion of one year
OHS-PR 02-
110. conducted to gauge prevalent completion of 03-08-2023 06-08-2023
25- 9
Not implemented one year
111. OHS-PR-02-26
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
EHS Engineer 25-07-2023
Reportable accidents being reported to
OHS-PR 02- authorities. Need updated
112. 03-08-2023 06-08-2023
26- 1 Records format.
Wrong format used
CLOSE-OUT
No. OHS REF. RESPONSIBLE DATE DATE
ACTION REQUIRED PROGRESS PERIOD PROOF OF CLOSE OUT PICTURES
(ITEM) (Question No.) PERSON ISSUED CLOSED
(Deadline)
Statistics circulated to managers and EHS Engineer 25-07-2023
OHS-PR 02- discussed
117. Closed 03-08-2023 06-08-2023
26- 11 at safety committee meetings
Not included in safety committee meeting
OHS-PR 02- Statistics circulated to Executive Director. EHS Engineer 25-07-2023 Requested to -
118. 03-08-2023 06-08-2023
26- 12 No records PM
EHS Engineer 25-07-2023
Talks by foreman/supervisors used in
conjunction with safety
OHS-PR 02-
119. Talks, meetings. Closed 03-08-2023 06-08-2023
26- 13
Near miss incidents not discussed to
manpower
Reviewed By Approved By
Prepared By
Balachandran Ganesan