Professional Documents
Culture Documents
Boiler Hydrolic
Boiler Hydrolic
FOR
Boiler Hydraulic Test
Document No : TO7119-UT00-P1HA-740025
WP NO : WP-M-025
Date I Prepared by
Reviewed by
Mech. General Manager
Approved by
Site Representative
Table of Contents
1. Objective
2. Application Scope
3. Guidance
4. Work Procedure
5. Attachments
1.0 Objective
This work procedure is aimed at performing hydraulic test and repairing defects and
damages in accordance with the related code until assuring an airtight on all pressure
parts and main pipes of boiler.
This work procedure is applied to perform all hydraulic tests for boiler pressure parts
and main pipes( superheater, reheater, all systems)
2.1 High Pressure Parts : Water Pipes + Boiler High Pressure Parts + Main Steam
Pipes
3.0 Guidance
Hydraulic tests for boiler pressure parts and main pipes pressure parts would be
performed in accordance with this work procedure.
Unit : kglcd
I Max. Working
Pressure Parts Test Pressure Remark
Pressure
Max. Working
Pressure x 1.5
( HDR at Super
heater Outlet)
Max. Working
I Low Pressure Parts 53 80
Pressure x 1.5
~ ( HDR at Rehe
ater Outlet)
Use demi water (above PH 10) added hydrazine and ammonia but following items
should be satisfied.
After pressurization, If the terr~peratureof water inside of the furnace goes down
below 20 "Cduring holding time or inspection, proceed the remaining test
continuously.
4.3.1 Preparations
(1) Pressure Gauge (The precision of the test pressure gauge should be not
less than first grade)
O Quantity
D For High Pressure (Pressurization): 2 EA (0- 500 kglc11f.g)
D For Low Pressure (Pressurization): 2 EA (0 - 100 kg1cd.g)
O Install Location
D For High Pressure: TIG BOP Heater 8 Outlet, Boiler Outlet
I PAGE : 6611
Quantity: 3 EA
D DEMI.WATER TANK
2) Communication Facilities
(1) Remove all lifting lugs on all pressure parts like tube bundle, header, etc to prevent
material defects and Perform penetrant tests on the parts where lifting lugs
removed.
(3) Check completion status of all sorts of thermocouple, fin, thermowell, casing plate
and etc.
(9) Check all sorts of drain valves and vent valves related hydraulic test.
Perform air leak test on all welded points using air applying 0.5 kglcm' pressure
(Air compressor requirement: Max. pressure 8 kglci~f)
(1) Preparations
O Chemical Treatment
O Water Filling
D FILLING METHOD
FILLING PIPE will connect to MS-MV-03 VALVE on MAlN STEAM LINE and
START UP CONNECTION LlNE and perform filling water fully into HIGH
PRESSURE PARTS and STEAM PIPES using BOILER FILLING PUMP.
-After flushing, when certain overflows occur in each vent valve by filling again,
close all valves and apply a pressure up to about 10 Kg1cd.g
- After filling, when the pressure reaches about 10 kg/cd.g, stop the filling pump
and close the filling line valve.
D FILLING METHOD
- For filling reheater system, the temporary filling pipes will be connected from the
filling pump to the CR-MV-03 on the HOT R/H LlNE and the CRP DRAIN LlNE
and fill water fully into the reheater and the high & low temp. pipes.
D SYSTEM FLUSHING
If overflow occurs in each vent, stop the boiler filling pump and perform system
flushing by opening boiler drain valves.
-After flushing, when certain overflows occur in each vent valve by filling again,
close all valves and apply a pressure up to about 10 Kg/cm2.g
- After filling, When the pressure reaches about 10 kg/cm'.g, stop the filling pump
and close the filling line valve.
4.3.4 Pressurization
Refer to the attachment of the boiler hydraulic test time-pressure diagram
@ L o w Pressure Parts
If a leakage on the welding part is terrible, stop the test immediately and bring
back to original condition and re-test after repair works.
4.3.7 Depressurization
When the hydraulic test has been finished, open the drain valves. depressurize
with less than 2 kglcd per minute until the pressure reaches at 180 kg/& and
apply 10 kglcd per minute when pressure is less than 180 kglcln'.
When the hydraulic test has been finished, open the drain valves. depressurize
with less than 2 kglcuf per minute until the pressure reaches at 45 kglcmi and
apply 10 kglclu' per minute when pressure is less than 45 kglcmf.
(3) After depressurizing, open the vent valves on the top of the boiler and drain
off water inside of the boiler.
If draining is needed, open all the air vent valves first and drain off water to
prevent a vacuum in the boiler.
Confirm the water inside of the boiler has been drained off and then, remove
moisture completely using oil-less-air and inhibit corrosion holding low humidity
by blowing instrument air into the boiler continuously before chemical cleaning.
5.0 Attachments
Temperature Record
(Air Leak Test, Hydrostatic Test)
T I : Atmospheric Temperature T2 :
NOTE T3 :
Pressure Record
(Air Leak Test, Hydrostatic Test)
I
NOTE P I : #8 Heater Outlet P2 : Separator Outlet
Pressure Record
(Air Leak Test, Hydrostatic Test)
I
NOTE P I : HOT RIH LINE Inlet P 2 : Cold Reheater Line Inlet