Subject: Work Order for Construction of Integrated check posts 1st and 2nd ghat roads at Tirumala.
Scope of Works :
Earthwork Excavation.
Filling of foundations.
Laying of PCC.
Laying of RCC.
Footings.
Plinth Beam.
Plastering.
12mm Inside plastering.
20mm Outside Plastering.
Shed Fabrication.
1. Materials Scope: The procurement of materials falls within the scope of Mirum Infra's
responsibilities.
2. Compliance: The subcontractor must comply with all relevant laws, regulations, and safety standards
throughout the duration of the project.
3. Quality Assurance: All work must meet the specified quality standards and be subject to inspection
and approval by our designated representative.
4. Timely Completion: The subcontractor is required to adhere to the agreed-upon schedule and ensure
timely completion of the project.
5. Change Orders: Any changes to the scope of work must be documented and approved in writing by
both parties.
6. Indemnification: The subcontractor is responsible for any damages or liabilities resulting from their
work.
7. If materials provided by Mirum Infra are misused, the corresponding costs will be deducted from the
running bills of the subcontractor.
8. Termination: Mirum Infra retains the unilateral right to terminate the contract and the contractor
without prior notice.
Locations:
1. Up Ghat Road:
a) 4.4 Km up ghat road.
b) At Harini.
c) At Line Road.
2. Down Ghat Road:
a) Near Enugula Arch.
b) At 20 Km Turning.
c) At 2nd Turning.
Please acknowledge receipt of this work order and confirm your acceptance of the terms and
conditions outlined herein. We extend our sincere appreciation for your commitment to excellence
and look forward to a successful collaboration.
MIRUM INFRA.