You are on page 1of 1

DAILY PROGRESS REPORT

DEVELOPMENT OF CLUSTER 8 MARGINAL FIELDS PROJECT


BARGE LTS-3000 DPR No: DPR-C8MFP-LTS3000-007
CLIENT / COMPANY OIL & NATURAL GAS CORPORATION LTD. (ONGCL) Progress Date: 10.03.2020 (00:00 to 24:00 Hrs.)
CONTRACTOR L&T HYDROCARBON ENGINEERING Reporting Date 11.03.2020
ONGC – CA ABS INDUSTRIAL VERIFICATION ( INDIA ) PVT LTD Vessel Location D30-2 Platform
ONGC – TPI VCS QUALITY SERVICES
A) Planned Activities for LTS-3000 in Construction Season 2019-2020
Sl. No. Activity Description Start Date Completion Date Remarks
1 D30-2 Jacket Installation 27.02.2020
2 WO 24-3 Jacket Installation
3 WO 24-3 Deck Installation
4 B192-10 Jacket Installation
5 B192-10 Deck Installation
6 D30-2 Deck Installation
B) Activities of 10.03.2020
1 Air diving operations in progress at LTS-3000 stern by DP DSV Hal Anant.

C) Activities Planned on 11.03.2020


1 Continue air diving operations at LTS-3000 stern.

D) General
1 Mr. Animas Das (Deck Officer / ONGC - TPI) demobilized from LTS-3000.
2 Mr. Deepak Yadav (Mech / ONGC - TPI) infield transferred to Vessel HAL Anant
3 Mr. Krishnan Elangovan (Mech / ONGC - CA ) and Mr. Bregish Puthoor ( HSE / ONGC -CA) will be infield transferred to Barge Falcon Chief in the next available Boat for HRP-III Project

E) Area of Concern
1 Since LTS-3000 main crane is unoperational, recovery of jacket and crane boom is to be carried out on-priority.
2 Evaluation of Jacket condition to be carried out after its recovery.

F) On Board ONGC - CA & TPI Manpower details


1 ONGC – CA (Mech) – KRISHNAN ELANGOVAN
2 ONGC – TPI (Mech) – DEEPAK YADAV
3 ONGC - TPI ( Deck Officer) - BIBHUTI RANJAN PADHY
4 ONGC - TPI ( Deck Officer) - ANIMESH DAS
5 ONGC - CA (Safety Officer) - NIKHIL S SHELAR
6 ONGC - CA (Safety Officer) - BREGISH PUTHOOR

KRISHNAN ELANGOVAN DEEPAK YADAV PULKIT JAIN


ABSIV-Mech. (ONGC-CA) VCS-Mech. (ONGC-TPI) ONGC Representative

Page 1 of 1